Case Note & Summary
The petitioner, Hotel Corporation of India Ltd., challenged an arbitral award passed by a sole arbitrator under Section 34 of the Arbitration and Conciliation Act, 1996. The dispute arose from a management agreement dated 15 September 2010, whereby the petitioner appointed the respondent, BD & P Hotels (India) Pvt. Ltd., to manage the Centaur Lake View Hotel in Srinagar. The agreement required the petitioner to hand over possession of the hotel and ensure that employees were transferred to the respondent's management. However, due to a pending petition in the Jammu and Kashmir High Court filed by employees, the petitioner was unable to fully hand over possession, leading to disputes. The respondent claimed that the petitioner breached the agreement by failing to hand over possession and by terminating the agreement prematurely. The arbitrator found the petitioner in breach and awarded damages of approximately Rs. 12 crores, including loss of profits and return of security deposit. The petitioner argued that the award was contrary to public policy, as the arbitrator ignored the effect of the court order and the respondent's own breaches. The court held that under Section 34, it cannot re-appreciate evidence or substitute its own view if the arbitrator's findings are plausible. The court found that the arbitrator had considered the court order and the evidence, and the findings were not perverse. The quantification of damages was based on expert evidence and was not shockingly unreasonable. The petition was dismissed.
Headnote
A) Arbitration Law - Section 34 of Arbitration and Conciliation Act, 1996 - Challenge to Arbitral Award - Public Policy - The court examined whether the arbitral award suffered from perversity or was contrary to the fundamental policy of Indian law. Held that the arbitrator's findings were plausible and based on evidence, and the court cannot substitute its own view under Section 34. (Paras 1-13) B) Contract Law - Management Contract - Breach of Contract - The dispute arose from a management agreement for a hotel. The arbitrator found that the petitioner had breached the agreement by failing to hand over possession and by terminating the agreement without cause. Held that the findings of breach were supported by evidence and were not perverse. (Paras 2-8) C) Damages - Quantification of Damages - The arbitrator awarded damages for loss of profits and return of security deposit. The court held that the quantification was based on expert evidence and was not so unreasonable as to shock the conscience of the court. (Paras 9-12)
Issue of Consideration
Whether the arbitral award is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on the ground of being contrary to the public policy of India, particularly on the findings of breach of contract and quantification of damages.
Final Decision
The court dismissed the arbitration petition, upholding the arbitral award. The court held that the arbitrator's findings were plausible and not perverse, and the quantification of damages was not shockingly unreasonable. The petition was dismissed with no order as to costs.
Law Points
- Arbitration Act
- 1996
- Section 34
- Public Policy
- Perversity
- Plausible View
- Management Contract
- Breach of Contract
- Damages





