Bombay High Court Dismisses Petition Challenging Arbitral Award in Supply Contract Dispute — LD Charges Upheld as Correct and No Refund Granted. The court held that the arbitral award was based on evidence and findings of fact, and no interference was warranted under Section 34 of the Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY
  • 107
Judgement Image
Font size:
Print

Case Note & Summary

The Petitioner, Bharat Lakhotya, sole proprietor of M/s. Salasar Hanumanji Industries, challenged an arbitral award dated 22 July 2010 under Section 34 of the Arbitration and Conciliation Act, 1996. The dispute arose from a supply contract with the Respondent, Bharat Sanchar Nigam Ltd. (BSNL), for Galvanized Tapered Steel Tubes. The Petitioner's tender was accepted for Rs.56,30,100/-, with delivery due by 15 December 2000. The Petitioner claimed that a labour strike from 20 September 2000 to 15 November 2000 prevented timely supply, and informed the Respondent by letter on 25 September 2000. The Assistant Labour Commissioner certified the strike on 11 January 2001. The Petitioner requested extension of time on 19 February 2001. The Respondent levied Liquidated Damages (LD) charges for delay. The arbitrator dismissed the Petitioner's claim for refund of LD charges and quashed the claim for sales tax. The Petitioner argued that the award was patently illegal and perverse, and that the strike was force majeure. The Respondent contended that the award was based on evidence and not liable to be interfered with. The court held that the arbitrator's findings were based on evidence, and the Petitioner failed to prove that the strike was the sole cause of delay. The court dismissed the petition, upholding the award.

Headnote

A) Arbitration - Challenge to Arbitral Award - Section 34 of the Arbitration and Conciliation Act, 1996 - Scope of Interference - The court considered whether the arbitral award was patently illegal or perverse. The court held that the award was based on evidence and findings of fact, and no interference was warranted under Section 34. (Paras 1-10)

B) Contract - Force Majeure - Labour Strike - The Petitioner claimed that a labour strike constituted force majeure, entitling extension of time. The court noted that the Petitioner failed to prove that the strike was the sole cause of delay and that the Respondent did not accept the strike as force majeure. (Paras 3-6)

C) Contract - LD Charges - Liquidated Damages - The Respondent levied LD charges for delayed supply. The court upheld the arbitrator's finding that the LD charges were correctly levied and no refund was due. (Paras 2-8)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award dated 22 July 2010 dismissing the Petitioner's claim for refund of LD charges and quashing the claim for sales tax is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court dismissed the Arbitration Petition No. 59 of 2012, upholding the arbitral award dated 22 July 2010.

Law Points

  • Section 34 of the Arbitration and Conciliation Act
  • 1996
  • Scope of interference with arbitral award
  • LD charges
  • Force majeure
  • Labour strike as force majeure
  • Extension of time
  • Burden of proof
Subscribe to unlock Law Points Subscribe Now

Case Details

2012 LawText (BOM) (12) 32

Arbitration Petition No. 59 of 2012

2012-12-14

Anoop V. Mohta, J.

Mr. A.L.N. Khatri for the Petitioner, Ms. Martina Sapkal i/by M/s. Arun Sapkal & Co. for the Respondent

Bharat Lakhotya

Bharat Sanchar Nigam Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Challenge to arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996.

Remedy Sought

Petitioner sought to set aside the arbitral award dated 22 July 2010 and sought refund of LD charges and sales tax.

Filing Reason

The Petitioner was aggrieved by the arbitral award dismissing his claim for refund of LD charges and quashing his claim for sales tax.

Previous Decisions

The arbitral award dated 22 July 2010 dismissed the Petitioner's claim and upheld the LD charges levied by the Respondent.

Issues

Whether the arbitral award is patently illegal or perverse warranting interference under Section 34 of the Arbitration and Conciliation Act, 1996. Whether the labour strike constituted force majeure entitling the Petitioner to extension of time and refund of LD charges.

Submissions/Arguments

Petitioner argued that the award was patently illegal and perverse, and that the labour strike was force majeure, entitling him to extension of time and refund of LD charges. Respondent argued that the award was based on evidence and findings of fact, and no interference was warranted under Section 34.

Ratio Decidendi

The court held that the arbitral award was based on evidence and findings of fact, and the Petitioner failed to prove that the labour strike was the sole cause of delay. The award was not patently illegal or perverse, and no interference was warranted under Section 34 of the Arbitration and Conciliation Act, 1996.

Judgment Excerpts

The Petitioner, under Section 34 of the Arbitration and Conciliation Act, 1996, has challenged award dated 22 July 2010, thereby dismissed the claim of the Petitioner. The operative part of the award is as under: ... the LD charges which are claimed by BSNL, Mumbai, are correct and no refund should be made to the claimant ... The claim of Sales Tax by the claimant ... is quashed.

Procedural History

The Petitioner filed Arbitration Petition No. 59 of 2012 in the High Court of Judicature at Bombay challenging the arbitral award dated 22 July 2010. The petition was heard and dismissed on 14 December 2012.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 34, 31
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Petition Challenging Arbitral Award in Supply Contract Dispute — LD Charges Upheld as Correct and No Refund Granted. The court held that the arbitral award was based on evidence and findings of fact, and no interference ...
Related Judgement
High Court Bombay High Court Quashes FIR Against Accused in SC/ST Act Case Due to Lack of Public View Element. Caste-Based Insult Allegation Fails as Incident Occurred Inside Police Station, Not in Public View Under Section 3(1)(x) of SC & ST (Prevention of Atr...