Case Note & Summary
The petitioner, Premlaxmi And Co., filed an Arbitration Petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated 3rd April 2009 passed by the Arbitral Tribunal constituted under an agreement with the respondents, Konkan Railway Corporation Ltd. and others. The dispute arose out of a construction contract for a tunnel at Ratnagiri. The petitioner had earlier filed an application under Section 11 of the Act before the Bombay High Court, which appointed the arbitral tribunal. The tribunal held its meetings in Mumbai and passed the award. The petitioner then filed the Section 34 petition in the Bombay High Court, arguing that since the Section 11 application was filed there, the High Court had jurisdiction under Section 42 of the Act. The respondents opposed, contending that the cause of action arose at Ratnagiri, and therefore only the court at Ratnagiri had jurisdiction. The court analyzed Section 2(e), which defines 'Court' as the Principal Civil Court of Original Jurisdiction in the district where the cause of action arises or the subject matter is situated. It held that the place of arbitration in Mumbai does not confer jurisdiction on the Bombay High Court. The court distinguished between the 'Court' under Section 2(e) and the Chief Justice or designated Judge under Section 11, noting that Section 42 does not apply to equate the two. Relying on the Supreme Court's decision in Garhwal Mandal Vikas Nigam Ltd. v. Krishna Travel Agency, the court reaffirmed that even if the arbitrator is appointed by the High Court, objections to the award must be filed before the District Court. Consequently, the court dismissed the petition for lack of jurisdiction, leaving the petitioner to approach the appropriate court at Ratnagiri.
Headnote
A) Arbitration Law - Jurisdiction - Section 34 read with Section 2(e) of the Arbitration and Conciliation Act, 1996 - The 'Court' for challenging an arbitral award is the Principal Civil Court of Original Jurisdiction where the cause of action arises or the subject matter is situated, not the High Court that appointed the arbitrator under Section 11. - Held that the Court at Ratnagiri, where the construction work was located, has jurisdiction to entertain the Section 34 petition, and the Bombay High Court lacks jurisdiction despite the Section 11 application being filed there. (Paras 3-6) B) Arbitration Law - Section 42 of the Arbitration and Conciliation Act, 1996 - Section 42 does not confer jurisdiction on the High Court merely because a Section 11 application was filed there; the 'Court' under Section 2(e) is distinct from the Chief Justice or designated Judge under Section 11. - Held that the submission based on Section 42 is unacceptable. (Para 4) C) Precedent - Garhwal Mandal Vikas Nigam Ltd. v. Krishna Travel Agency, (2008) 6 SCC 745 - The Supreme Court reaffirmed that even if the arbitrator is appointed by the High Court under Section 11(6), objections to the award must be filed before the Principal Civil Court of Original Jurisdiction as defined in Section 2(1)(e). - Held that the same principle applies here, and the petition is not maintainable before the High Court. (Para 5)
Issue of Consideration
Whether the Bombay High Court has jurisdiction to entertain a petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award, when the cause of action arose at Ratnagiri and the arbitral tribunal was constituted by the High Court under Section 11.
Final Decision
The petition is dismissed for lack of jurisdiction. The petitioner is at liberty to approach the appropriate court at Ratnagiri.
Law Points
- Jurisdiction under Section 34 of the Arbitration and Conciliation Act
- 1996 is determined by the 'Court' as defined in Section 2(e)
- which is the Principal Civil Court of Original Jurisdiction where the cause of action arises or the subject matter is situated
- not the High Court that appointed the arbitrator under Section 11.




