Case Note & Summary
The petitioner, Rolta India Limited, filed two arbitration petitions under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an interim award dated 26th July 2012 passed by an arbitral tribunal. The tribunal had rejected the petitioner's counterclaims against the respondent, Voltas Limited, on the ground of limitation. The dispute arose from a construction agreement dated 22nd July 2001, whereby the respondent agreed to construct two new buildings and modify an existing building for the petitioner. On 20th June 2002, the petitioner issued two work orders for supply and installation of chillers. The petitioner terminated the construction agreement on 3rd December 2004, citing delays and incomplete work, and asserted its right to claim damages. The respondent denied any delay and contended that the termination was illegal. On 1st March 2005, the respondent submitted its final bill, including claims for compensation. The petitioner denied the bill and reiterated its claims for damages. The respondent invoked arbitration, and the petitioner filed counterclaims. The arbitral tribunal, by the impugned interim award, held that the counterclaims were barred by limitation as they arose on the date of termination (3rd December 2004) and were filed beyond three years. The High Court, after hearing both sides, observed that the tribunal had not considered the petitioner's argument that the counterclaims were based on continuing breach and that the limitation period could start from the date of the final bill (1st March 2005). The court held that the tribunal's finding on limitation was patently erroneous and liable to be set aside. The court allowed the petitions in part, setting aside the portion of the award rejecting the counterclaims as time-barred, and remanded the matter to the arbitral tribunal for fresh consideration on the issue of limitation, directing the tribunal to decide the same in accordance with law.
Headnote
A) Arbitration - Limitation for Counterclaims - Section 34 Arbitration and Conciliation Act, 1996 - Article 1 Limitation Act, 1963 - The court considered whether the arbitral tribunal erred in rejecting counterclaims as time-barred. The petitioner's counterclaims arose from the same construction contract as the respondent's claims. The tribunal held that the cause of action for counterclaims accrued on the date of termination of the contract (3rd December 2004) and that the counterclaims filed in 2012 were beyond the three-year limitation period. The High Court found that the tribunal failed to consider that the counterclaims were based on continuing breach and that the final bill submitted by the respondent on 1st March 2005 could be the starting point of limitation. The court set aside the impugned portion of the award and remanded the matter for fresh consideration on the issue of limitation. (Paras 1-10)
Issue of Consideration
Whether the arbitral tribunal correctly rejected the petitioner's counterclaims as barred by limitation under the Limitation Act, 1963, and whether the High Court can interfere under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The High Court allowed the petitions in part, setting aside the portion of the interim award dated 26th July 2012 rejecting the counterclaims as time-barred, and remanded the matter to the arbitral tribunal for fresh consideration on the issue of limitation in accordance with law.
Law Points
- Limitation for counterclaims in arbitration
- Section 34 of Arbitration and Conciliation Act
- 1996
- Article 1 of Limitation Act
- 1963
- continuing breach
- date of accrual of cause of action





