Case Note & Summary
The case arises from a contract between the Union of India (UOI) and M/s. Arctic India (the Contractor) for replacing a BER A.C. Plant at NAD, Karanja. The contract was awarded on 9 April 1996 with a completion period of 15 months, but work was completed on 29 July 1999, with delays attributed by each party to the other. Disputes arose, and the Contractor invoked arbitration under Condition 70 of the General Conditions of Contract. The sole arbitrator, Shri T.K. Saha, passed an award on 29 March 2004, granting the Contractor Rs.27,55,350 with interest. The UOI challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, seeking to set aside several claims, while the Contractor cross-challenged the setting aside of one claim. The Learned Single Judge partly allowed the UOI's petition, setting aside the claim for escalation under Clause 70-C but upholding other claims. Both parties appealed. The Division Bench of the Bombay High Court considered whether the Arbitrator's award was patently illegal or perverse. The court held that the Arbitrator's findings on claims for loss of productivity, idle establishment, and interest were based on evidence and not perverse, and thus not liable to be interfered with. However, the claim for escalation under Clause 70-C was set aside because the contract contained a price variation clause, making the claim unsustainable. The court also upheld the award of interest at 18% per annum from the date of the award until payment. The appeals were disposed of accordingly, with the UOI's appeal partly allowed and the Contractor's appeal dismissed.
Headnote
A) Arbitration - Arbitral Award - Setting Aside - Section 34 Arbitration and Conciliation Act, 1996 - The court considered whether the Arbitrator's award on various claims was liable to be set aside on grounds of patent illegality or perversity. The court held that the Arbitrator's findings on claims for loss of productivity, idle establishment, and interest were based on evidence and not perverse, and thus not liable to be interfered with. However, the claim for escalation under Clause 70-C was set aside as the contract contained a price variation clause, making the claim unsustainable. (Paras 1-30) B) Contract - Price Variation Clause - Escalation - Clause 70-C of General Conditions of Contract - The court held that where a contract contains a specific price variation clause, a claim for escalation under Clause 70-C (which provides for compensation for delay) cannot be awarded, as the price variation clause is the exclusive mechanism for adjusting prices. The Arbitrator's award of escalation was contrary to the terms of the contract and thus patently illegal. (Paras 20-25) C) Arbitration - Interest - Section 31(7)(a) Arbitration and Conciliation Act, 1996 - The court upheld the Arbitrator's award of interest at 18% per annum from the date of the award until payment, holding that the rate was within the Arbitrator's discretion and not excessive. (Paras 26-28)
Issue of Consideration
Whether the Learned Single Judge was correct in refusing to set aside certain claims awarded by the Arbitrator in favour of the Contractor, and whether the Learned Single Judge was correct in setting aside the claim for escalation under Clause 70-C.
Final Decision
Appeal No. 121 of 2009 filed by Union of India is partly allowed to the extent that the claim for escalation under Clause 70-C is set aside; Appeal No. 782 of 2010 filed by Contractor is dismissed. The rest of the award is upheld.
Law Points
- Arbitration
- Contract Interpretation
- Price Variation Clause
- Compensation for Delay
- Loss of Productivity
- Idle Establishment
- Interest





