Case Note & Summary
The dispute arose from a highway construction contract for Four Laning of Satara-Kolhapur on NH4. The petitioner, Maharashtra State Road Development Corporation Ltd. (MSRDC), a government undertaking, awarded the contract to the respondent joint venture. Work commenced on 4 March 2002 with a stipulated completion by 17 August 2004 but was completed on 31 December 2005. Disputes emerged over reimbursement of increased royalty charges under Clause 14 of the Special Conditions of Contract, payment for rock cutting through wedging and chiseling with hydraulic excavator, and additional expenses for steel laps. The respondents referred the disputes to the Engineer, who rejected the claims. The matter then went to the Steering Committee and subsequently to arbitration. The sole arbitrator, a retired Chief Secretary, allowed the claims. For royalty, he awarded Rs. 59,56,232 plus Rs. 6,28,322 with interest at 15% per annum from respective dates. For rock cutting, he determined a rate of Rs. 465.21 per cum plus escalation, after a detailed rate analysis. The petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, contending that the interpretation of Clause 14 was erroneous, the Steering Committee's decision was not binding, the rock cutting rate was incorrectly fixed, and the interest rate was excessive. The High Court, after noting that two similar petitions had been decided on the same day, examined the awards on merits. It held that the arbitrator's interpretation of Clause 14, bolstered by a corrigendum and the parties' contemporaneous conduct of reimbursing 83% of royalty during execution, was reasonable and not perverse. The court found that the employer could not unilaterally change its interpretation after completion. Regarding the Steering Committee, the court observed that it was an in-house expert body whose advice the arbitrator had accepted; the employer could not then challenge its own committee's decision. As to rock cutting, the arbitrator's rate analysis was based on material on record and was a plausible factual determination. On interest, the court noted that no rate was agreed, and 15% simple interest was not excessive for a commercial transaction. Consequently, the petition was dismissed, and the award was upheld in its entirety.
Headnote
A) Arbitration - Interference with Award - Section 34, Arbitration and Conciliation Act, 1996 - Arbitral award can be interfered with under Section 34 only if perverse or patently illegal; court cannot reappreciate facts. - The High Court held that the arbitrator's interpretation of contractual clause 14 on royalty reimbursement, based on contemporaneous conduct and corrigendum, was reasonable and not perverse. Held, no interference warranted. (Paras 5–9) B) Contract - Interpretation of Clause 14 (Special Conditions) - Royalty charges included in 'other taxes' - Law of Contract - The arbitrator found that a corrigendum clarified that 'other taxes' included royalty charges; the employer had reimbursed 83% of the claim during execution and reversed its stand only after completion. The court upheld this as a correct interpretation. (Paras 6, 19–21 of Award) C) Arbitration - Binding Nature of Steering Committee Decision - Clauses 67.2, 67.3 of Contract - The contract provided for a Steering Committee of experts whose advice, if followed by the arbitrator, cannot be challenged by the employer. The court held the employer is bound by its own expert committee's decision when the arbitrator accepts it. (Paras 7–9) D) Contract - Works - Determination of Rate for Rock Cutting - General Principles - The arbitrator's rate analysis for rock cutting by hydraulic excavator, considering machinery hours, credits, and lead, was found reasonable; the court declined to interfere with the factual determination. (Paras 10–11) E) Interest - Arbitral Award - Interest Rate of 15% p.a. - Arbitration and Conciliation Act, 1996 - No specific rate agreed; arbitrator awarded 15% simple interest considering commercial nature of transaction. Court held not excessive. (Paras 11)
Issue of Consideration
Whether the Arbitrator's interpretation of contractual clauses regarding royalty reimbursement and rock cutting rates was perverse or patently illegal, warranting interference under Section 34 of the Arbitration and Conciliation Act, 1996. Whether the Steering Committee's decision was binding on the employer.
Final Decision
The petition was dismissed. The court found no ground to interfere with the award under Section 34 of the Arbitration and Conciliation Act, 1996. The arbitrator's interpretation of the contract and factual findings were reasonable and not perverse. The award was upheld in its entirety.
Law Points
- Arbitration award can be set aside only if perverse or patently illegal
- Contractual interpretation by arbitrator is final and not open to reappraisal
- Contemporaneous conduct of parties relevant to construing contract terms
- In-house expert committee decision binding on employer when adopted by arbitrator
- Interest rate of 15% per annum not excessive in commercial contract



