High Court Dismisses Employer's Challenge to Arbitral Award Under Section 34 of Arbitration Act in Road Construction Contract; Upholds Contractor's Entitlement to Royalty Reimbursement Under Clause 14. Award Found Reasonable on Merits as Interpretation Consistent with Conduct and Corrigendum.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 5
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a highway construction contract for Four Laning of Satara-Kolhapur on NH4. The petitioner, Maharashtra State Road Development Corporation Ltd. (MSRDC), a government undertaking, awarded the contract to the respondent joint venture. Work commenced on 4 March 2002 with a stipulated completion by 17 August 2004 but was completed on 31 December 2005. Disputes emerged over reimbursement of increased royalty charges under Clause 14 of the Special Conditions of Contract, payment for rock cutting through wedging and chiseling with hydraulic excavator, and additional expenses for steel laps. The respondents referred the disputes to the Engineer, who rejected the claims. The matter then went to the Steering Committee and subsequently to arbitration. The sole arbitrator, a retired Chief Secretary, allowed the claims. For royalty, he awarded Rs. 59,56,232 plus Rs. 6,28,322 with interest at 15% per annum from respective dates. For rock cutting, he determined a rate of Rs. 465.21 per cum plus escalation, after a detailed rate analysis. The petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, contending that the interpretation of Clause 14 was erroneous, the Steering Committee's decision was not binding, the rock cutting rate was incorrectly fixed, and the interest rate was excessive. The High Court, after noting that two similar petitions had been decided on the same day, examined the awards on merits. It held that the arbitrator's interpretation of Clause 14, bolstered by a corrigendum and the parties' contemporaneous conduct of reimbursing 83% of royalty during execution, was reasonable and not perverse. The court found that the employer could not unilaterally change its interpretation after completion. Regarding the Steering Committee, the court observed that it was an in-house expert body whose advice the arbitrator had accepted; the employer could not then challenge its own committee's decision. As to rock cutting, the arbitrator's rate analysis was based on material on record and was a plausible factual determination. On interest, the court noted that no rate was agreed, and 15% simple interest was not excessive for a commercial transaction. Consequently, the petition was dismissed, and the award was upheld in its entirety.

Headnote

A) Arbitration - Interference with Award - Section 34, Arbitration and Conciliation Act, 1996 - Arbitral award can be interfered with under Section 34 only if perverse or patently illegal; court cannot reappreciate facts. - The High Court held that the arbitrator's interpretation of contractual clause 14 on royalty reimbursement, based on contemporaneous conduct and corrigendum, was reasonable and not perverse. Held, no interference warranted. (Paras 5–9)

B) Contract - Interpretation of Clause 14 (Special Conditions) - Royalty charges included in 'other taxes' - Law of Contract - The arbitrator found that a corrigendum clarified that 'other taxes' included royalty charges; the employer had reimbursed 83% of the claim during execution and reversed its stand only after completion. The court upheld this as a correct interpretation. (Paras 6, 19–21 of Award)

C) Arbitration - Binding Nature of Steering Committee Decision - Clauses 67.2, 67.3 of Contract - The contract provided for a Steering Committee of experts whose advice, if followed by the arbitrator, cannot be challenged by the employer. The court held the employer is bound by its own expert committee's decision when the arbitrator accepts it. (Paras 7–9)

D) Contract - Works - Determination of Rate for Rock Cutting - General Principles - The arbitrator's rate analysis for rock cutting by hydraulic excavator, considering machinery hours, credits, and lead, was found reasonable; the court declined to interfere with the factual determination. (Paras 10–11)

E) Interest - Arbitral Award - Interest Rate of 15% p.a. - Arbitration and Conciliation Act, 1996 - No specific rate agreed; arbitrator awarded 15% simple interest considering commercial nature of transaction. Court held not excessive. (Paras 11)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Arbitrator's interpretation of contractual clauses regarding royalty reimbursement and rock cutting rates was perverse or patently illegal, warranting interference under Section 34 of the Arbitration and Conciliation Act, 1996. Whether the Steering Committee's decision was binding on the employer.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The petition was dismissed. The court found no ground to interfere with the award under Section 34 of the Arbitration and Conciliation Act, 1996. The arbitrator's interpretation of the contract and factual findings were reasonable and not perverse. The award was upheld in its entirety.

Law Points

  • Arbitration award can be set aside only if perverse or patently illegal
  • Contractual interpretation by arbitrator is final and not open to reappraisal
  • Contemporaneous conduct of parties relevant to construing contract terms
  • In-house expert committee decision binding on employer when adopted by arbitrator
  • Interest rate of 15% per annum not excessive in commercial contract
Subscribe to unlock Law Points Subscribe Now

Case Details

2012 LawText (BOM) (08) 60

Arbitration Petition No. 272 of 2008

2012-08-17

Anoop V. Mohta, J.

2012:BHC-OS:10328

Mr. D.D. Madon, Mr. P.P. Chavan, Mr. Nooruddin Dhilla, Mr. S.U. Kamdar, Mr. Vinit Naik

Maharashtra State Road Development Corporation Ltd. (MSRDC)

M/s. B. Seenaiah & Co. (Projects) Ltd., M/s. Shrinivasa Construction Limited, and Joint Venture

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Challenge to arbitral award under section 34 of the Arbitration and Conciliation Act, 1996 in a construction contract dispute.

Remedy Sought

The Petitioner sought to set aside the arbitral award dated 3 March 2008 that had allowed the Respondent's claims for royalty reimbursement and rock cutting charges with interest.

Filing Reason

The Petitioner, a government undertaking, contended that the award was contrary to the contract terms and that the arbitrator's interpretation of Clause 14 and rate determination was erroneous.

Previous Decisions

The Engineer rejected the claims; the Steering Committee gave advice; the Sole Arbitrator allowed the claims in the impugned award.

Issues

Whether the arbitral award granting royalty reimbursement under Clause 14 of the Special Conditions was perverse and liable to be set aside. Whether the arbitrator correctly determined the rate for rock cutting works. Whether the interest rate of 15% per annum was excessive. Whether the Steering Committee's decision under clauses 67.2 and 67.3 was binding on the employer.

Submissions/Arguments

Petitioner argued that the royalty reimbursement was mistakenly paid and that Clause 14 did not cover royalty as 'other taxes'. Petitioner contended that the Steering Committee's decision was not binding and that the arbitrator erred in accepting it. Petitioner challenged the rock cutting rate analysis as flawed, claiming improper computation of machinery hours and lead. Respondent asserted contemporaneous conduct and corrigendum supported inclusion of royalty, and that the employer was estopped from changing interpretation after completion. Respondent argued rate determination was factual and supported by evidence, and interest rate was reasonable.

Ratio Decidendi

An arbitral award can be set aside under Section 34 only if it is perverse or patently illegal; the court cannot reappreciate evidence. Contemporaneous conduct of parties is relevant in interpreting contractual terms. An in-house expert committee's decision, when accepted by the arbitrator, binds the employer. Determination of rates for work is a finding of fact not open to challenge unless perverse. Interest rate of 15% per annum is not excessive in a commercial contract absent agreed rate.

Judgment Excerpts

During the entire execution of the Works and after reimbursing practically 83% of the claim in respect of enhanced Royalty, at no stage the Employer informed or gave inclination to the Claimant that he is modifying the interpretation given to clause 14 by the parties during execution of the work and on which the parties have acted during execution of work for a period of nearly 3 years. It is not now permissible for the Respondent to disown the interpretation given by both the parties to the contract during the execution of the Work and unilaterally change it after completion of Work and taking over of the Work. The decision, therefore, if made by the Steering Committee and the learned Arbitrator had accepted the same, I see there is no reason to accept the submission that the award so passed by the learned Arbitrator by accepting the Steering Committee's decision read with his expertized reasons, is unjust, contrary to the law and/or the record. no particular rate of interest was agreed by the parties. The learned Arbitrator, considering the nature of business however, granted 15% interest.

Procedural History

The Petitioners invited tender for Four Laning of Satara Kolhapur stretch. A contract was signed on 4 March 2002. Work commenced on 18 May 2002, to be completed by 17 August 2004, but completed on 31 December 2005. Disputes arose regarding royalty reimbursement and rock cutting rates. The Engineer rejected the claims. On 22 February 2006, the matter was referred to the Steering Committee. Subsequently, referral to arbitration. Sole Arbitrator Shri Sharad P. Upasani was appointed first for Claim No.1 on 18 December 2006, later for other claims. The Respondents filed claims, Petitioners filed defense. Impugned award passed on 3 March 2008. Petitioners filed this petition under Section 34 of Arbitration and Conciliation Act, 1996.

Acts & Sections

  • Arbitration and Conciliation Act, 1996:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court Dismisses Employer's Challenge to Arbitral Award Under Section 34 of Arbitration Act in Road Construction Contract; Upholds Contractor's Entitlement to Royalty Reimbursement Under Clause 14. Award Found Reasonable on Merits as Interpretati...
Related Judgement
High Court Bombay High Court Decides Five First Appeals Filed by Original Defendant No.6 Against Eviction Decree in Suit Brought by Public Trust. The Appeals Were Disposed of Along with Civil Applications on 13/14 December 2005.