Bombay High Court Dismisses Appeal Against Arbitral Award in Pipeline Construction Dispute. Court Upholds Arbitrator's Findings of Fact and Reduces Interest Rate from 18% to 12% Under Section 34 of the Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY
  • 127
Judgement Image
Font size:
Print

Case Note & Summary

The appellant, Mahanagar Gas Limited, awarded a work order to the respondent, M/s. Babulal Uttamchand & Co., for project management and construction of a pipeline network for domestic supply of natural gas in Santacruz, valued at Rs. 3.87 crores, to be completed within three years. The respondent mobilised resources and completed the pipeline work, but the appellant failed to supply gas to customers for about 18 months, causing non-payment by customers and consequent non-payment to the respondent. The respondent raised claims before the arbitrator, and the appellant filed counterclaims. After pleadings and examination of one witness each, the arbitrator passed an award allowing certain claims of the respondent and dismissing the counterclaims. The appellant challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996 before the learned Single Judge, who dismissed the petition with the modification of reducing the future rate of interest from 18% to 12% per annum from the date of the award till realisation. The appellant appealed against this order. The Division Bench held that the findings of fact recorded by the arbitrator are not open to challenge under Section 34 unless they are perverse or contrary to the public policy of India. The court found no perversity in the arbitrator's findings regarding breach of contract and quantification of claims. The court also upheld the modification of the interest rate, finding the original rate of 18% to be excessive. The appeal was dismissed, and the judgment of the learned Single Judge was confirmed.

Headnote

A) Arbitration - Section 34 of the Arbitration and Conciliation Act, 1996 - Scope of Interference - The court held that findings of fact recorded by the arbitrator are not open to challenge under Section 34 unless they are perverse or contrary to the public policy of India. The court found no perversity in the arbitrator's findings regarding breach of contract and quantification of claims. (Paras 4-6)

B) Arbitration - Interest Rate - Section 31(7)(b) of the Arbitration and Conciliation Act, 1996 - The court modified the future rate of interest from 18% to 12% per annum from the date of the award till realisation, as the original rate was considered excessive. (Para 7)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the learned Single Judge erred in dismissing the arbitration petition under Section 34 of the Arbitration and Conciliation Act, 1996, and whether the arbitral award suffers from perversity or is contrary to the public policy of India.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The appeal is dismissed. The judgment and order of the learned Single Judge dated 9 March 2012 is confirmed.

Law Points

  • Arbitration
  • Section 34 of the Arbitration and Conciliation Act
  • 1996
  • Scope of interference
  • Findings of fact
  • Perversity
  • Public policy
  • Interest rate
  • Section 31(7)(b) of the Arbitration and Conciliation Act
Subscribe to unlock Law Points Subscribe Now

Case Details

2012 LawText (BOM) (08) 52

Appeal (Lodging) No.349 of 2012 in Arbitration Petition No. 958 of 2010

2012-08-28

Mohit S. Shah, C.J., N.M. Jamdar, J.

Mr. Pradeep Sancheti, Senior Advocate with Mr. S.A.Bhalwal i/by M/s. Vyas & Bhalwal for the appellant. Mr.Chidanand Kapil i/by Ms.shilpa Kapil for the respondent.

Mahanagar Gas Limited

M/s. Babulal Uttamchand & Co.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against dismissal of arbitration petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award.

Remedy Sought

The appellant sought to set aside the arbitral award and the judgment of the learned Single Judge dismissing the arbitration petition.

Filing Reason

The appellant challenged the arbitral award on grounds of perversity and being contrary to public policy.

Previous Decisions

The learned Single Judge dismissed the arbitration petition with modification of reducing future interest from 18% to 12% per annum.

Issues

Whether the findings of fact recorded by the arbitrator are perverse or contrary to the public policy of India. Whether the rate of interest awarded by the arbitrator is excessive and requires modification.

Submissions/Arguments

The appellant argued that the arbitrator's findings were perverse and contrary to the public policy of India. The respondent supported the award and the judgment of the learned Single Judge.

Ratio Decidendi

Findings of fact recorded by the arbitrator are not open to challenge under Section 34 of the Arbitration and Conciliation Act, 1996 unless they are perverse or contrary to the public policy of India. The court found no perversity in the arbitrator's findings. The rate of future interest was modified from 18% to 12% per annum as the original rate was considered excessive.

Judgment Excerpts

This appeal is directed against the judgment and order dated 9 March 2012 of the learned Single Judge dismissing the arbitration petition of the appellant herein under section 34 of the Arbitration and Conciliation Act, 1996 with the only modification of reducing the future rate of interest from 18% to 12% from the date of the award (5 March 2010) till realisation on the claim as well as the counterclaim. The findings of fact recorded by the arbitrator are not open to challenge under Section 34 of the Arbitration and Conciliation Act, 1996 unless they are perverse or contrary to the public policy of India.

Procedural History

The respondent filed claims before the arbitrator. The appellant filed counterclaims. The arbitrator passed an award on 5 March 2010. The appellant filed Arbitration Petition No. 958 of 2010 under Section 34 of the Arbitration and Conciliation Act, 1996 before the learned Single Judge, who dismissed the petition on 9 March 2012 with modification of interest. The appellant filed the present appeal against that order.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34, Section 31(7)(b)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Writ Petition and Sets Aside Tenancy Authority's Orders in Agricultural Tenancy Dispute. Authorities' Approach of First Examining Plaintiffs' Possession Rather Than Defendant's Burden of Proof Held Perverse.
Related Judgement
High Court Bombay High Court Allows Trade Union Petition Against Unregistered Employer Engaging Security Guards in Violation of Statutory Scheme. Employer Must Register Under Maharashtra Private Security Guards Act, 1981 and Employ Only Board-Allotted Guards.