Bombay High Court Quashes BMC Order Restricting Developer to G+4 Floors for Public Parking Lot, Finds Construction Substantially Progressed Under Section 51 MRTP Act. Court Holds Protection Under Proviso to Section 51(1) Available Once Operations Have Substantially Progressed, Not Just Substantially Completed.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a development project on plot bearing Final Plot No. 46 of Town Planning Scheme-III at Shivaji Park, Mumbai, owned by Kohinoor CTNL Infrastructure Company Private Limited. The developers proposed a highrise IT Park, residential and public parking building comprising three wings. Wing-C was to include municipal public parking on ground plus thirteen floors and residential units above. The Municipal Corporation of Greater Mumbai (MCGM) sanctioned plans and issued an IOD in 2006, and commencement certificates were issued up to the fourteenth floor. The state government granted in-principle approval for the public parking lot under DCR 33(24) in 2010. Later, the state directed the MCGM to propose amendments to DCR 33(24) to limit parking towers to ground plus four floors. On 22 June 2011, MCGM issued a circular incorporating such conditions and directed that all proposals be considered subject to them. Subsequently, on 29 November 2011, a show cause notice under Section 51 of the MRTP Act was issued to the petitioners, calling upon them to explain why the commencement certificate should not be revoked based on the circular. The petitioners replied, but on 22 December 2011, a stop work notice was served, directing restriction of work to the fourth floor. The Additional Municipal Commissioner passed an order on 27 April 2012. Finding that construction had progressed substantially on the core portion—about fifty percent beyond the stage of being termed 'substantially completed'—the order allowed the already executed construction on that portion but directed that in the remaining portion, the public parking lot be limited to ground plus four floors and plans be modified accordingly. The petitioners filed a writ petition under Article 226, contending that the order misapplied Section 51, as the proviso protects operations that have substantially progressed, and once substantial progress was found, no restrictive order could be passed. They also pointed to the huge expenditure incurred in building foundations for the full sanctioned height. MCGM argued that the circular and proposed amendments to DCR 33(24) were intended to ensure usability of parking facilities and that only partial work had been done, justifying the restriction. The court analyzed Section 51(1) proviso, which in clause (a) protects operations previously carried out and prohibitions orders being passed after operations have substantially progressed or been completed. The court emphasized that 'substantially progressed' is distinct from 'completed' and does not mean merely 'substantially completed'. The Additional Municipal Commissioner had applied an erroneous test, treating the question as one of substantial completion. Given the finding that fifty percent of the area had construction beyond the substantial stage, the direction to restrict to G+4 was illegal. The court also noted that MCGM could not rely on a circular reflecting draft amendments not yet finalized, particularly after representing in earlier court proceedings that it would not apply such circular. Consequently, the writ petition was allowed. The impugned order insofar as it restricted the parking lot to G+4 and directed plan modification was quashed. The stop work notice and related impounding of plans were set aside. The petitioners were held entitled to proceed with construction of the public parking lot comprising ground plus thirteen floors as per originally sanctioned plans. MCGM was directed to approve revised plans within four weeks. No costs were awarded.

Headnote

A) Planning Law - Revocation of Permission - Substantial Progress Protection - Maharashtra Regional and Town Planning Act, 1966, Section 51(1) - The proviso protects operations that have substantially progressed, not only those completed. The expression 'substantially progressed' means work has advanced to a significant degree short of completion. The Additional Municipal Commissioner erred by applying a test of 'substantially completed', thereby misdirecting himself. Held, where construction had reached a stage where substantial progress was found, the order restricting development to G+4 was unsustainable. (Paras 9-12)

B) Administrative Law - Exercise of Planning Authority Power - Reliance on Proposed Amendments - Maharashtra Regional and Town Planning Act, 1966, Section 51 - The Municipal Corporation's order was based on a circular reflecting proposed not finalised amendments to DCR. The court found that the Corporation could not rely on such a draft to revoke an existing valid permission, especially when the corporation had made earlier representations to the court that the circular would not be applied. (Paras 13-14)

C) Constitutional Law - Judicial Review - Correctness of Administrative Decision - Constitution of India, Article 226 - The High Court exercised writ jurisdiction to quash an administrative order that was based on an erroneous application of law and facts. Held that the order was patently illegal and thus set aside. (Para 15)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Additional Municipal Commissioner's order restricting the public parking lot to G+4, despite finding that substantial construction had progressed, was lawful under Section 51 of the MRTP Act.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The petition is allowed. The impugned order dated 27 April 2012 to the extent it directs the petitioner to restrict the public parking lot to G+4 floors and to modify plans is quashed and set aside. The stop work notice is quashed. The petitioner is entitled to proceed with construction of G+13 floors for public parking lot as per original sanctioned plans. The Municipal Corporation is directed to approve revised plans within 4 weeks. No order as to costs.

Law Points

  • Section 51 of the Maharashtra Regional and Town Planning Act
  • 1966 protects operations that have substantially progressed or completed
  • 'substantially progressed' means not merely substantially completed
  • an order revoking or modifying permission cannot be passed after operations have substantially progressed
  • the proviso balances planning authority's power with developers' rights
Subscribe to unlock Law Points Subscribe Now

Case Details

2012 LawText (BOM) (07) 118

Writ Petition No. 143 of 2012

2012-07-09

Dr. D.Y. Chandrachud, R.D. Dhanuka

2012:BHC-OS:8812-DB

V.V. Tulzapurkar, Nikhil Sakhardande, E.P. Bharucha, Geeta Joglekar

Kohinoor CTNL Infrastructure Company Private Limited & anr.

The Municipal Corporation of Greater Mumbai & ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition under Article 226 challenging an administrative order revoking/modifying a building permission for a public parking lot.

Remedy Sought

Petitioners sought to quash the order of Additional Municipal Commissioner dated 27 April 2012 restricting construction of public parking lot to G+4 floors and directing modification of plans.

Filing Reason

The Additional Municipal Commissioner, despite finding that substantial construction had been carried out, directed the petitioners to restrict the public parking lot to G+4 floors in the remaining portion, applying a new DCR amendment circular.

Previous Decisions

The impugned order was passed after a show cause notice under Section 51. There is no mention of earlier court decisions; the matter is a direct challenge to the administrative order.

Issues

Whether the order dated 27 April 2012 was valid under Section 51 of the Maharashtra Regional and Town Planning Act, 1966, given that the Additional Municipal Commissioner found that construction had substantially progressed. Whether the Municipal Corporation could rely on a circular reflecting proposed amendments to restrict construction height after substantial progress had been made.

Submissions/Arguments

Petitioners: The Additional Municipal Commissioner misconstrued Section 51; substantial completion on the core part precludes restriction; huge expenditure incurred; foundation built based on original permission. Respondents: The circular introducing conditions limiting height to G+4 was necessary for usability; only partial work done; draft notification to modify DCR justifies restriction.

Ratio Decidendi

Under Section 51(1) of the Maharashtra Regional and Town Planning Act, 1966, no order revoking or modifying a development permission shall be passed after the operations have substantially progressed. The test is of 'substantial progress', not 'substantial completion'. The protection covers operations that have significantly advanced towards completion. Consequently, once the planning authority finds that substantial progress has been made, it cannot restrict development, and any order to the contrary is illegal.

Judgment Excerpts

Clause (a) of the proviso is in two parts. The first part ... protects those operations which have been previously carried out. The second part has the effect of imposing a restraint upon the passing of an order of revocation or modification where operations have either substantially progressed or have been completed. the expression 'substantially progressed' cannot be read to mean the same thing as the completion of operations. The Additional Municipal Commissioner, has in the present case, proceeded on the basis of a patently wrong appreciation of the underlying legal principles. The test which the Additional Municipal Commissioner applied is : whether the work is substantially complete on site or otherwise on the relevant date

Procedural History

The petitioners obtained IOD and commencement certificates for development including public parking lot of G+13. On 22 June 2011, BMC issued circular limiting height to G+4. On 29 November 2011, show cause notice under Section 51 was issued. Petitioners replied. Then stop work notice on 22 December 2011. On 27 April 2012, Additional Municipal Commissioner passed impugned order partially restricting construction. Petitioners filed Writ Petition No. 143 of 2012 before Bombay High Court.

Acts & Sections

  • Maharashtra Regional and Town Planning Act, 1966: Section 51
  • Constitution of India: Article 226
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Second Appeal in Execution Objection Case — Upholds Summary Rejection of Objection Petition Under Order 21 Rule 97 CPC. Executing Court Not Required to Adjudicate Title When Objection is Frivolous and Collusive.
Related Judgement
High Court Bombay High Court Quashes BMC Order Restricting Developer to G+4 Floors for Public Parking Lot, Finds Construction Substantially Progressed Under Section 51 MRTP Act. Court Holds Protection Under Proviso to Section 51(1) Available Once Operations Hav...