Bombay High Court Dismisses Union of India's Challenge to Arbitral Award in Contract Dispute. Court upholds award granting compensation for work done, security deposit refund, and loss of profit under Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 27
Judgement Image
Font size:
Print

Case Note & Summary

The Union of India, through the Chief Project Manager (Conversion), Central Railway, Mumbai, filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated 26.12.2008. The dispute arose out of a contract between the petitioner and M/s. Quick Communication Systems Pvt Ltd for the execution of certain works. The arbitrator had awarded the respondent (claimant) a total of Rs. 30,29,111/- under various heads, including work done not paid (Rs. 9,40,580/-), payment of the 6th bill (Rs. 5,75,431/-), refund of security deposit (Rs. 10,88,100/-), loss of profit (Rs. 2,00,000/-), loss of advance (Rs. 1,00,000/-), loss due to infrastructure (Rs. 75,000/-), and under utilization of overheads (Rs. 50,000/-). The petitioner's counterclaims for delay in completion and risk and cost were rejected. The petitioner contended that the award was contrary to the terms of the contract, perverse, and against public policy. The court, after examining the award and the submissions, held that the arbitrator had considered the evidence and provided reasoned findings. The court reiterated the limited scope of interference under Section 34, stating that the court cannot reappreciate evidence or substitute its own view unless the award is so perverse that no reasonable person could have arrived at it. The court found no such perversity or violation of public policy. Consequently, the petition was dismissed, and the award was upheld.

Headnote

A) Arbitration - Section 34 of Arbitration and Conciliation Act, 1996 - Scope of Interference - The court considered the limited grounds for setting aside an arbitral award under Section 34, emphasizing that the court does not sit in appeal over the arbitrator's findings of fact or interpretation of contract terms unless the award is perverse or contrary to public policy. Held that the award was based on evidence and reasoning, and no interference was warranted (Paras 1-10).

B) Contract - Compensation for Work Done - The arbitrator awarded Rs. 9,40,580/- for work done not paid and Rs. 5,75,431/- for the 6th bill, based on evidence of actual work performed. The court upheld these findings as the arbitrator had considered the contract terms and the evidence on record (Paras 2-5).

C) Contract - Refund of Security Deposit - The arbitrator awarded Rs. 10,88,100/- as refund of security deposit, which was not disputed by the petitioner. The court confirmed this part of the award (Para 2).

D) Damages - Loss of Profit and Other Losses - The arbitrator awarded Rs. 2,00,000/- for loss of profit, Rs. 1,00,000/- for loss of advance, Rs. 75,000/- for loss due to infrastructure, and Rs. 50,000/- for under utilization of overheads. The court held that these awards were based on the arbitrator's assessment of evidence and were not perverse (Paras 2-6).

E) Interest - The arbitrator did not award any interest, and the court noted that the claimant had claimed 24% p.a. but was awarded nil (Para 2).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award dated 26.12.2008 is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on the grounds of being contrary to the terms of the contract, perverse, and against public policy.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court dismissed the petition and upheld the arbitral award dated 26.12.2008.

Law Points

  • Section 34 of Arbitration and Conciliation Act
  • 1996
  • Scope of interference with arbitral award
  • Public policy
  • Reasoned award
  • Appreciation of evidence by arbitrator
Subscribe to unlock Law Points Subscribe Now

Case Details

2012 LawText (BOM) (07) 79

Arbitration Petition No.305 of 2009

2012-07-02

Anoop V. Mohta, J.

Mr. T.J. Pandian for the petitioner; Ms. Shilpa Kapil with Mr. C. Kapil, Mr. Dubey & Ms. Jyoti Jadhav for the respondent

Union of India, through The Chief Project Manager (Conversion), Central Railway, Wadi Bunder, Mumbai

M/s. Quick Communication Systems Pvt Ltd, Quick House, D79, MIDC Nerul, Behind London Pilsner, Navi Mumbai

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Challenge to an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996.

Remedy Sought

The petitioner (Union of India) sought to set aside the arbitral award dated 26.12.2008.

Filing Reason

The petitioner contended that the award was contrary to the terms of the contract, perverse, and against public policy.

Previous Decisions

The arbitral tribunal passed an award on 26.12.2008 granting various amounts to the respondent and rejecting the petitioner's counterclaims.

Issues

Whether the arbitral award is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on the grounds of being contrary to the terms of the contract, perverse, and against public policy.

Submissions/Arguments

The petitioner argued that the award was contrary to the terms of the contract, perverse, and against public policy. The respondent supported the award, submitting that the arbitrator had considered the evidence and provided reasoned findings.

Ratio Decidendi

The court held that under Section 34 of the Arbitration and Conciliation Act, 1996, the scope of interference with an arbitral award is limited. The court cannot reappreciate evidence or substitute its own view unless the award is so perverse that no reasonable person could have arrived at it, or it is contrary to public policy. In this case, the arbitrator had considered the evidence and provided reasoned findings, and no such perversity or violation of public policy was found.

Judgment Excerpts

The petitioner (The Chief Project Manager, Central Railway, Mumbai through the Union of India), has challenged Award dated 26.12.2008 passed by the learned Arbitral Tribunal, by filing the present petition under section 34 of the Arbitration and Conciliation Act, 1996. The summary of Award is as under: ... The court held that the arbitrator had considered the evidence and provided reasoned findings, and no such perversity or violation of public policy was found.

Procedural History

The arbitral tribunal passed an award on 26.12.2008. The Union of India filed Arbitration Petition No.305 of 2009 under Section 34 of the Arbitration and Conciliation Act, 1996 before the Bombay High Court challenging the award. The petition was reserved on 12.06.2012 and pronounced on 02.07.2012.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Union of India's Challenge to Arbitral Award in Contract Dispute. Court upholds award granting compensation for work done, security deposit refund, and loss of profit under Arbitration and Conciliation Act, 1996.
Related Judgement
High Court Bombay High Court Dismisses PIL Seeking Recognition of 'No Religion' as a Form of Religion. Article 25 of the Constitution does not confer a right to compel State recognition of 'No Religion' as a religion, and a writ of mandamus cannot be issued wit...