Case Note & Summary
The petitioner, Mahanagar Telephone Nigam Ltd. (MTNL), a Central Government Corporation, challenged an arbitral award dated 3 July 2006 passed by a sole arbitrator in favor of the respondent, M/s. Ram Builders, a contractor. The dispute arose from a contract for reinstatement of cable trenches and allied works entered into on 12 November 1997. The respondent carried out work under various work orders and submitted bills, but MTNL withheld payment of certain final bills citing non-compliance with terms, lack of documentary evidence, and pendency of vigilance (CBI) investigations. The arbitrator awarded the respondent Rs. 11,26,478.57 with 12% interest from respective dates of payment to the date of award, an additional Rs. 2,65,082 with 12% interest from 30 September 2000, and future interest at 18% per annum if payment was not made within 90 days. MTNL challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, arguing that the award was contrary to public policy, perverse, and that the arbitrator ignored the vigilance investigation and contractual terms. The court held that the arbitrator's findings on quantum were based on evidence and not perverse; the arbitrator had considered the vigilance issue and found no evidence of fraud. However, the court found the future interest rate of 18% per annum excessive and reduced it to 9% per annum, modifying the award accordingly. The petition was partly allowed.
Headnote
A) Arbitration Law - Challenge to Award under Section 34 - Public Policy - The court examined whether the arbitral award was contrary to public policy or perverse. The arbitrator's findings on quantum were based on evidence and not perverse; thus, the award was not set aside. (Paras 1-5) B) Arbitration Law - Interest Rate - Section 31(7)(b) Arbitration and Conciliation Act, 1996 - The arbitrator awarded future interest at 18% per annum. The court found this rate excessive and reduced it to 9% per annum, consistent with the principle that interest rates should not be punitive. (Paras 2-5)
Issue of Consideration
Whether the arbitral award dated 3 July 2006 is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on grounds of being contrary to public policy, perverse, or in conflict with the terms of the contract; and whether the rate of future interest awarded at 18% per annum is excessive.
Final Decision
The petition is partly allowed. The arbitral award is modified to the extent that the future interest rate of 18% per annum is reduced to 9% per annum. The rest of the award is upheld.
Law Points
- Arbitration award challenge under Section 34
- Public policy
- Perversity
- Interest rate modification
- Section 31(7)(b) Arbitration and Conciliation Act
- 1996




