Case Note & Summary
The judgment concerns two arbitration petitions under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated 7 April 2010. The original claimant, Dolphin Drilling Limited (DDL), a company incorporated under English law, and the respondent, Oil and Natural Gas Corporation Ltd. (ONGC), a public sector undertaking, entered into a contract on 17 October 2003 for the hire of DDL's drilling unit 'Bedford Dolphin'. Disputes arose regarding payment for wellhead tools and services provided by DDL. The arbitral tribunal awarded DDL US$ 2,699,235.63 for those services, along with costs of Rs. 71,68,723 and post-award interest at 18% per annum under Section 31(7)(b) of the Act. However, the tribunal denied pre-award interest under Section 31(7)(a). DDL challenged only the denial of pre-award interest, while ONGC challenged the award on various grounds, including the merits of the claim. The court examined the scope of interference under Section 34, which is limited to grounds of public policy, patent illegality, or lack of jurisdiction. The court upheld the tribunal's findings on the merits, noting that the tribunal had considered the evidence and contractual terms. Regarding interest, the court held that the tribunal's discretion to deny pre-award interest was not arbitrary and did not warrant interference. The court dismissed DDL's petition and partially allowed ONGC's petition only to the extent of modifying the interest component, but ultimately upheld the award as passed. The court emphasized that the arbitral tribunal's decision on interest was within its discretion and not contrary to law.
Headnote
A) Arbitration Law - Challenge to Arbitral Award - Section 34 of the Arbitration and Conciliation Act, 1996 - Both parties challenged the award dated 7 April 2010 passed by the Arbitral Tribunal. The original claimant, Dolphin Drilling Limited (DDL), challenged only the denial of pre-award interest, while the respondent, Oil and Natural Gas Corporation Ltd. (ONGC), challenged the award on multiple grounds. The court examined the scope of interference under Section 34 and upheld the award on merits but modified the interest component. (Paras 1-4) B) Interest - Pre-award Interest - Section 31(7)(a) of the Arbitration and Conciliation Act, 1996 - DDL contended that the tribunal erred in not granting interest on the unpaid invoices from the date of accrual of cause of action until the date of award. The court held that the tribunal's discretion under Section 31(7)(a) was not exercised arbitrarily and that the denial of pre-award interest was justified in the facts and circumstances. (Paras 3, 10-15) C) Interest - Post-award Interest - Section 31(7)(b) of the Arbitration and Conciliation Act, 1996 - The tribunal awarded interest at 18% per annum from the date of award till payment. The court upheld this rate as statutory and reasonable. (Para 2) D) Contract Law - Interpretation of Contract - Wellhead Tools and Services - The dispute arose from a contract dated 17 October 2003 for hire of a drilling unit. The tribunal awarded US$ 2,699,235.63 for providing wellhead tools and services. The court found no patent illegality or perversity in the tribunal's findings and upheld the award on this count. (Paras 6-9)
Issue of Consideration
Whether the arbitral tribunal erred in denying pre-award interest on the awarded amount from the date of cause of action to the date of award under Section 31(7)(a) of the Arbitration and Conciliation Act, 1996, and whether the award is liable to be set aside under Section 34 of the Act.
Final Decision
The court dismissed Arbitration Petition No. 1065 of 2010 (DDL's petition) and partially allowed Arbitration Petition No. 1063 of 2010 (ONGC's petition) only to the extent of modifying the interest component, but ultimately upheld the award as passed by the tribunal.
Law Points
- Arbitral award under Section 34 of Arbitration and Conciliation Act
- 1996
- Interest under Section 31(7)(a) and (b)
- Pre-award interest
- Post-award interest
- Public sector undertaking
- Contract interpretation
- Wellhead tools and services





