Bombay High Court Dismisses Subcontractor's Petition to Restrain Invocation of Performance Bank Guarantee Under Section 9 of Arbitration Act. Bank Guarantee Held to Be an Independent Contract Between Bank and Beneficiary, Not Subject to Injunction Absent Fraud or Irreparable Injustice.

High Court: Bombay High Court Bench: BOMBAY
  • 4
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Karam Chand Thapar & Bros. (Coal Sales) Ltd., a subcontractor, filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking to restrain the respondent, Hindustan Construction Company Ltd. (HCC), from invoking a performance bank guarantee of Rs. 15.95 Crores issued by HSBC Bank. The main contract was awarded by Sardar Sarovar Narmada Nigam Limited (SSNNL) to HCC for canal construction, and HCC subcontracted part of the work to the petitioner. The petitioner alleged that HCC had failed to make payments and had committed breaches, and that invocation of the bank guarantee would cause irreparable harm. The Court examined the nature of bank guarantees and held that they are independent contracts between the bank and the beneficiary. The Court found no evidence of fraud or irretrievable injustice that would justify an injunction. The Court also noted that the subcontractor was aware of the main contract terms, including the prohibition on assignment without permission. The petition was dismissed, and the interim relief granted earlier was vacated. The Court directed that the bank guarantee amount be kept in a fixed deposit by HCC pending arbitration, subject to the outcome of the arbitration proceedings.

Headnote

A) Arbitration - Interim Measures - Section 9 of Arbitration and Conciliation Act, 1996 - Bank Guarantee - The Court held that a bank guarantee is an independent contract between the bank and the beneficiary, and the Court cannot restrain its invocation except in cases of established fraud or irretrievable injustice. The subcontractor's disputes with the contractor regarding the main contract do not justify an injunction against the bank guarantee. (Paras 1-16)

B) Contract Law - Subcontract - Assignment and Subletting - Clause 62 of Main Contract - The main contract between SSNNL and HCC prohibited assignment or subletting without Chief Engineer's permission. The subcontractor's appointment was subject to the main contract terms, and the subcontractor was deemed to have knowledge of the main contract. (Paras 2-3)

C) Bank Guarantee - Independence Principle - Fraud Exception - The Court reiterated the settled legal position that a bank guarantee is a separate contract and can only be restrained if there is a clear case of fraud or irretrievable injustice. The petitioner failed to establish either. (Paras 10-16)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Court can restrain the invocation of a performance bank guarantee under Section 9 of the Arbitration and Conciliation Act, 1996, at the instance of a subcontractor against the contractor, in the absence of fraud or irretrievable injustice.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The petition was dismissed. The interim relief granted earlier was vacated. The Court directed that the bank guarantee amount be kept in a fixed deposit by the respondent pending arbitration, subject to the outcome of the arbitration proceedings.

Law Points

  • Bank guarantee is an independent contract between bank and beneficiary
  • Court cannot restrain invocation except in case of fraud or irretrievable injustice
  • Subcontractor cannot restrain invocation based on disputes with contractor
  • Section 9 of Arbitration and Conciliation Act
  • 1996 does not permit blanket injunction against bank guarantee
Subscribe to unlock Law Points Subscribe Now

Case Details

2012 LawText (BOM) (05) 29

Arbitration Petition (L) No. 606 of 2012

2012-05-04

G.S. Godbole

Dr. Milind Sathe, Sr. Advocate a/w Mr. Zal Andharjina, Ms. Jyoti Singh, Ms. Madhumita Kothari and Mr. K. Dastoor i/b. Phoenix Legal, Advocate for the Petitioner; Mr. Kevic Setalvad, Sr. Advocate a/w. Rakesh Mandavkar i/b. Harish Joshi & Co., Advocate for the Respondent

Karam Chand Thapar & Bros. (Coal Sales) Ltd.

Hindustan Construction Company Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim relief to restrain invocation of a performance bank guarantee.

Remedy Sought

The petitioner sought an order restraining the respondent from invoking, encashing or receiving any monies under the Performance Bank Guarantee of Rs. 15.95 Crores.

Filing Reason

The petitioner alleged that the respondent had failed to make payments and committed breaches under the subcontract, and that invocation of the bank guarantee would cause irreparable harm.

Issues

Whether the Court can restrain the invocation of a performance bank guarantee under Section 9 of the Arbitration and Conciliation Act, 1996, at the instance of a subcontractor against the contractor, in the absence of fraud or irretrievable injustice.

Submissions/Arguments

Petitioner argued that the respondent had breached the subcontract and that invocation of the bank guarantee would cause irreparable harm. Respondent argued that the bank guarantee is an independent contract and cannot be restrained except in cases of fraud or irretrievable injustice, which were not present.

Ratio Decidendi

A bank guarantee is an independent contract between the bank and the beneficiary. The Court cannot restrain its invocation except in cases of established fraud or irretrievable injustice. The subcontractor's disputes with the contractor do not justify an injunction against the bank guarantee.

Judgment Excerpts

This Petition under Section 9 of the Arbitration and Conciliation Act, 1996 has been filed by a subcontractor against the contractor and principal relief which is sought is that the Respondent shall not invoke, encash or receive any monies under the Performance Bank Guarantee of Rs. 15.95 Crores issued by the HSBC Bank on behalf of the Petitioner to the Respondent. It is well settled that a bank guarantee is an independent contract between the bank and the beneficiary. The Court cannot restrain the invocation of a bank guarantee except in cases of fraud or irretrievable injustice.

Procedural History

The petition was filed under Section 9 of the Arbitration and Conciliation Act, 1996. The Court heard arguments and delivered judgment on May 4, 2012.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Subcontractor's Petition to Restrain Invocation of Performance Bank Guarantee Under Section 9 of Arbitration Act. Bank Guarantee Held to Be an Independent Contract Between Bank and Beneficiary, Not Subject to Injunction Ab...
Related Judgement
High Court Bombay High Court Dismisses Writ Petition Challenging No-Confidence Motion Against Sarpanch. Court upholds validity of motion passed by majority under Maharashtra Village Panchayats Act.