Case Note & Summary
The petitioner, Karam Chand Thapar & Bros. (Coal Sales) Ltd., a subcontractor, filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking to restrain the respondent, Hindustan Construction Company Ltd. (HCC), from invoking a performance bank guarantee of Rs. 15.95 Crores issued by HSBC Bank. The main contract was awarded by Sardar Sarovar Narmada Nigam Limited (SSNNL) to HCC for canal construction, and HCC subcontracted part of the work to the petitioner. The petitioner alleged that HCC had failed to make payments and had committed breaches, and that invocation of the bank guarantee would cause irreparable harm. The Court examined the nature of bank guarantees and held that they are independent contracts between the bank and the beneficiary. The Court found no evidence of fraud or irretrievable injustice that would justify an injunction. The Court also noted that the subcontractor was aware of the main contract terms, including the prohibition on assignment without permission. The petition was dismissed, and the interim relief granted earlier was vacated. The Court directed that the bank guarantee amount be kept in a fixed deposit by HCC pending arbitration, subject to the outcome of the arbitration proceedings.
Headnote
A) Arbitration - Interim Measures - Section 9 of Arbitration and Conciliation Act, 1996 - Bank Guarantee - The Court held that a bank guarantee is an independent contract between the bank and the beneficiary, and the Court cannot restrain its invocation except in cases of established fraud or irretrievable injustice. The subcontractor's disputes with the contractor regarding the main contract do not justify an injunction against the bank guarantee. (Paras 1-16) B) Contract Law - Subcontract - Assignment and Subletting - Clause 62 of Main Contract - The main contract between SSNNL and HCC prohibited assignment or subletting without Chief Engineer's permission. The subcontractor's appointment was subject to the main contract terms, and the subcontractor was deemed to have knowledge of the main contract. (Paras 2-3) C) Bank Guarantee - Independence Principle - Fraud Exception - The Court reiterated the settled legal position that a bank guarantee is a separate contract and can only be restrained if there is a clear case of fraud or irretrievable injustice. The petitioner failed to establish either. (Paras 10-16)
Issue of Consideration
Whether the Court can restrain the invocation of a performance bank guarantee under Section 9 of the Arbitration and Conciliation Act, 1996, at the instance of a subcontractor against the contractor, in the absence of fraud or irretrievable injustice.
Final Decision
The petition was dismissed. The interim relief granted earlier was vacated. The Court directed that the bank guarantee amount be kept in a fixed deposit by the respondent pending arbitration, subject to the outcome of the arbitration proceedings.
Law Points
- Bank guarantee is an independent contract between bank and beneficiary
- Court cannot restrain invocation except in case of fraud or irretrievable injustice
- Subcontractor cannot restrain invocation based on disputes with contractor
- Section 9 of Arbitration and Conciliation Act
- 1996 does not permit blanket injunction against bank guarantee





