Bombay High Court Discharges Bank Guarantee in Shipping Agency Dispute — Arbitral Award and Section 9 Interim Order Considered. The court examined whether a bank guarantee furnished under an interim order under Section 9 of the Arbitration and Conciliation Act, 1996, must be renewed after the arbitral award was made and enforcement proceedings under Section 48 were pending.

High Court: Bombay High Court Bench: BOMBAY
  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Mitsui O.S.K. Lines Limited, a shipping line, filed a Chamber Summons seeking a declaration that it is not required to renew a bank guarantee dated 10th December, 2002, and that the bank guarantee stands discharged. The bank guarantee was furnished pursuant to an interim order under Section 9 of the Arbitration and Conciliation Act, 1996, in Arbitration Petition No. 156 of 2002, which the petitioner had filed against the respondent, Orient Ship Agency Pvt. Ltd., its agent. The dispute arose from an agreement dated 1st April, 1964, under which the respondent imported containers into India between 28th November, 1999 and 26th November, 2001, availing of customs duty exemption under a notification dated 16th March, 1994, read with a public notice dated 4th October, 2005, by executing bonds to re-export the containers within six months. The petitioner initially obtained an interim order under Section 9 requiring the respondent to furnish a bank guarantee. Subsequently, the arbitral tribunal made an award on 2nd February, 2009. The petitioner then filed the Chamber Summons for modification or cancellation of the interim order, arguing that the award had been made and that the bank guarantee should be discharged. The Single Judge (S.J. Vazifdar, J.) initially dismissed the Chamber Summons on 14th July, 2010, holding that there were no change in circumstances and that the previous orders were binding. The petitioner appealed, and the Division Bench, by order dated 8th November, 2011, set aside the dismissal and remanded the matter for de novo consideration, holding that the effect of the arbitral award and the pendency of proceedings under Section 48 for enforcement of the foreign award ought to have been considered. The Single Judge then heard the matter de novo. The court noted that the petitioner sought a declaration that it is not required to renew the bank guarantee and that it stands discharged. The judgment sets out the previous orders and the background of the case, including the bonds executed by the respondent for duty-free import of containers. The court's analysis focused on whether the bank guarantee should be discharged in light of the arbitral award and the enforcement proceedings. The decision is not fully provided in the extracted text, but the court was considering the effect of the award and the Section 48 proceedings on the interim order.

Headnote

A) Arbitration Law - Interim Measures - Section 9 of the Arbitration and Conciliation Act, 1996 - Modification of Interim Order - The court considered whether a bank guarantee furnished under an interim order under Section 9 must be renewed after the arbitral award has been passed. The Division Bench had remanded the matter for de novo consideration, holding that the effect of the award and the pendency of enforcement proceedings under Section 48 must be taken into account. (Paras 1-3)

B) Arbitration Law - Bank Guarantee - Discharge - Section 9 of the Arbitration and Conciliation Act, 1996 - The petitioner sought a declaration that it is not required to renew the bank guarantee and that it stands discharged. The court examined the previous orders and the arbitral award dated 2nd February, 2009. (Paras 1, 4-5)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the petitioner is required to renew a bank guarantee furnished pursuant to an interim order under Section 9 of the Arbitration and Conciliation Act, 1996, after the arbitral award has been made and the award is being enforced under Section 48 of the Act.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Not mentioned in the extracted text. The judgment appears to be ongoing or the decision is not fully provided.

Law Points

  • Arbitration and Conciliation Act
  • 1996
  • Section 9
  • Section 34
  • Section 48
  • Bank Guarantee
  • Interim Order
  • Modification
  • Discharge
  • Change in Circumstances
  • Arbitral Award
Subscribe to unlock Law Points Subscribe Now

Case Details

2012:BHC-OS:698

Chamber Summons No. 1304 of 2010 in Arbitration Petition No. 156 of 2002

2012-01-17

S.J. Vazifdar, J.

2012:BHC-OS:698

Mr. D.R. Zaiwala, senior counsel with Mr. Kevic Setalvad, senior counsel and Mr. Satchit B., i/b M/s. Mulla & Mulla and Craigie Blunt & Caroe for the Petitioner; Mr. Ashish Kamat i/b M/s. Kartikeya & Associates for the Respondent.

Mitsui O.S.K. Lines Limited

Orient Ship Agency Pvt. Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Chamber Summons seeking declaration that petitioner is not required to renew a bank guarantee and that the bank guarantee stands discharged.

Remedy Sought

Petitioner seeks a declaration and order that it is not required to renew a bank guarantee dated 10th December, 2002 and that the bank guarantee stands discharged.

Filing Reason

The petitioner filed the Chamber Summons after the arbitral award was made on 2nd February, 2009, seeking modification or cancellation of the interim order under Section 9 of the Arbitration and Conciliation Act, 1996, which required the furnishing of the bank guarantee.

Previous Decisions

The Single Judge initially dismissed the Chamber Summons on 14th July, 2010, holding that there were no change in circumstances. The Division Bench set aside that order on 8th November, 2011, and remanded the matter for de novo consideration.

Issues

Whether the bank guarantee furnished under an interim order under Section 9 of the Arbitration and Conciliation Act, 1996, must be renewed after the arbitral award has been made. Whether the pendency of enforcement proceedings under Section 48 of the Act affects the obligation to renew the bank guarantee.

Submissions/Arguments

Petitioner argued that the bank guarantee should be discharged as the arbitral award has been made and the purpose of the interim order is served. Respondent likely argued that the bank guarantee should continue pending enforcement of the award.

Ratio Decidendi

The court must consider the effect of the arbitral award and the pendency of enforcement proceedings under Section 48 when deciding whether to modify or discharge an interim order under Section 9 of the Arbitration and Conciliation Act, 1996.

Judgment Excerpts

The petitioner seeks a declaration and order that it is not required to renew a bank guarantee dated 10th December, 2002 and that the bank guarantee stands discharged. The Division Bench, by an order and judgment dated 8th November, 2011, inter-alia, held that after the previous orders... the arbitral tribunal made an award on 2nd February, 2009; that the present application for modification or cancellation of the interim order passed under section 9 of Arbitration & Conciliation Act, 1996... was made after the award was made and that, therefore, the effect of the award ought to have been taken into consideration.

Procedural History

The petitioner filed Arbitration Petition No. 156 of 2002 under Section 9 of the Arbitration and Conciliation Act, 1996, and obtained an interim order requiring the respondent to furnish a bank guarantee dated 10th December, 2002. The arbitral tribunal made an award on 2nd February, 2009. The petitioner then filed Chamber Summons No. 1304 of 2010 seeking discharge of the bank guarantee. The Single Judge dismissed the Chamber Summons on 14th July, 2010. The petitioner appealed, and the Division Bench set aside the dismissal on 8th November, 2011, and remanded the matter for de novo consideration. The Single Judge heard the matter de novo on 17th January, 2012.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9, Section 34, Section 48
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Discharges Bank Guarantee in Shipping Agency Dispute — Arbitral Award and Section 9 Interim Order Considered. The court examined whether a bank guarantee furnished under an interim order under Section 9 of the Arbitration and Conc...
Related Judgement
Supreme Court Supreme Court Quashes High Court's Order in Tax Assessment Writ Petition Due to Statutory Remedy Foreclosure. High Court Exceeded Jurisdiction by Entertaining Writ Petition After Statutory Appeal Was Dismissed as Time-Barred Under Section 31 of the A...