Bombay High Court Dismisses Summons for Judgment in Licence Fee Dispute Due to Triable Issues. Plaintiff's claim for balance licence fee after premature termination of agreement due to demolition by Municipal Corporation raises triable issues regarding breach and entitlement.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 70
Judgement Image
Font size:
Print

Case Note & Summary

The Plaintiff, Nemichand Jain, filed a Summary Suit against M/s. Vodafone Essar Limited and Sandeep Thakur based on a licence agreement dated 16 April 2006. The agreement permitted the Defendants to install a Cellular Antenna on the Plaintiff's building for a minimum period of three years, from 1 January 2006 to 31 January 2008, with a fixed licence fee of Rs. 4,88,750 per year payable on or before 15 January of every year. The fee was paid for two years. The agreement contained renewal and termination clauses. However, an Assistant Commissioner of the Municipal Corporation, acting under the Mumbai Municipal Corporation Act, issued a notice to the Defendants based on a complaint from tenants, directing removal of the cabin and antenna. The antenna was demolished on 6 September 2007. This led to premature termination of the agreement. The Defendants, by notice dated 7 September 2007, demanded a refund of the licence fee paid in advance for the remaining period from 7 September 2007 to 31 December 2007, as they could no longer operate their cell site. The Plaintiff then took out a Summons for Judgment seeking a decree for the balance licence fee up to December 2008. The Court noted that the agreement did not provide that the Plaintiff was entitled to claim the balance licence fee in advance irrespective of breach or termination. The usual termination clause permitted parties to terminate after due notice. The demolition compelled termination, a situation not contemplated in the agreement. The Court held that the Plaintiff's entitlement to the licence fee up to December 2008 could not be accepted as a foundation for summary judgment. The issues of who committed breach and the consequences, including damages, are matters for trial and cannot be decided on affidavits. The basic burden lies on the Plaintiff to show that the claim falls within the summary procedure. The Court concluded that the Plaintiff failed to make out a case for Summons for Judgment, and the Defendants raised triable issues. Accordingly, the Summons for Judgment was dismissed, and the Defendants were granted unconditional leave to defend the suit.

Headnote

A) Civil Procedure - Summary Suit - Summons for Judgment - Order XXXVII CPC - Triable Issue - Plaintiff sought decree for balance licence fee after agreement terminated prematurely due to demolition by Municipal Corporation - Court held that the circumstances of termination, breach, and entitlement to damages are triable issues not suitable for summary judgment - Held that the Plaintiff failed to prove that the claim falls within summary procedure (Paras 3-4).

B) Contract Law - Licence Agreement - Termination - Force Majeure - Breach - Agreement for installation of cellular antenna terminated after demolition by Municipal Corporation - No clause covering such situation - Court held that who committed breach and consequences are matters for trial (Para 3).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Plaintiff is entitled to a decree on Summons for Judgment under Order XXXVII of the Code of Civil Procedure, 1908 for balance licence fee when the agreement was terminated prematurely due to demolition of the antenna by the Municipal Corporation.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Summons for Judgment dismissed. Defendants granted unconditional leave to defend the suit.

Law Points

  • Summary suit
  • Summons for Judgment
  • Triable issue
  • Licence agreement
  • Breach of contract
  • Unliquidated damages
  • Order XXXVII CPC
Subscribe to unlock Law Points Subscribe Now

Case Details

2010 LawText (BOM) (07) 181

Summons for Judgment No. 103 of 2010 in Summary Suit No. 2390 of 2010

2011-07-22

Anoop V. Mohta, J.

Mr. I.K. Tripathi with Mr. Narendra Dubey i/by Mr. Akhilesh Singh & J.B. Singh for the Plaintiff, Mr. Punit B. Anand for the Defendants

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Summary Suit for recovery of balance licence fee under a licence agreement.

Remedy Sought

Plaintiff sought a decree on Summons for Judgment for balance licence fee up to December 2008.

Filing Reason

Defendants failed to pay licence fee after premature termination of agreement due to demolition of antenna by Municipal Corporation.

Issues

Whether the Plaintiff is entitled to a decree on Summons for Judgment under Order XXXVII CPC for balance licence fee when the agreement was terminated prematurely due to demolition by Municipal Corporation. Whether the claim raises triable issues requiring trial.

Submissions/Arguments

Plaintiff argued entitlement to balance licence fee based on written agreement. Defendants contended that termination was due to circumstances beyond their control and demanded refund of advance fee.

Ratio Decidendi

In a summary suit under Order XXXVII CPC, the plaintiff must prove that the claim falls within the summary procedure. If the defendant raises triable issues, such as breach of contract and entitlement to damages, the court should not grant summary judgment but grant leave to defend. The circumstances of termination and who committed breach are matters for trial.

Judgment Excerpts

The agreement nowhere provides that the irrespective of breach of termination of contract, the Plaintiff is entitled to claim the balance amount/ licence fee in advance till December 2008. Who has committed the breach of clauses of the agreement and the consequences of the same including the damages/compensation if any, is again a matter of trial and just cannot be considered merely on the basis of affidavit filed by the parties.

Procedural History

Plaintiff filed Summary Suit No. 2390 of 2010 based on licence agreement dated 16 April 2006. Plaintiff took out Summons for Judgment No. 103 of 2010 seeking decree. Court heard arguments and dismissed the Summons for Judgment, granting unconditional leave to defend.

Acts & Sections

  • Code of Civil Procedure, 1908: Order XXXVII
  • Mumbai Municipal Corporation Act:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Summons for Judgment in Licence Fee Dispute Due to Triable Issues. Plaintiff's claim for balance licence fee after premature termination of agreement due to demolition by Municipal Corporation raises triable issues regardi...
Related Judgement
High Court High Court of Bombay at Goa Quashes FIR in Rash Driving Case Based on Compromise Between Parties. Offences Under Sections 279, 338, 504 IPC Held to Be Non-Serious and Compoundable with Court's Permission, Allowing Quashing in the Interest of Justice.