Case Note & Summary
The case arises from a first appeal filed by the Maharashtra State Electricity Board (now trifurcated into three companies) against a judgment and decree dated 28.2.1994 passed by the Joint Civil Judge, Senior Division, Yavatmal in Special Civil Suit No.2 of 1991. The respondents, Gopalrao Dhande and Vinayak Gopalrao Dhande, were agriculturists owning a banana plantation in Asola, District Yavatmal. They alleged that due to the negligent maintenance of a high voltage electric transmission line passing over their land, the line sagged and sparked, causing the death of 20,500 banana plants. The trial court decreed the suit, holding the appellants jointly and severally liable to pay compensation at the rate of Rs.8.50 per plant, totaling Rs.1,74,250, with future interest at 12% per annum. The appellants challenged the decree on the grounds that the respondents failed to prove negligence and that the compensation was excessive. The High Court, after hearing arguments, examined the evidence including the testimony of the respondents and the site inspection report. The court noted that the appellants did not lead any evidence to rebut the claim of negligence. The court held that the appellants, being electricity companies, owed a duty of care to maintain their lines properly and that the sagging and sparking of wires was a clear indication of negligence. The court also upheld the quantum of compensation as reasonable based on the market value of banana plants. Consequently, the appeal was dismissed with costs, and the decree of the trial court was confirmed.
Headnote
A) Tort Law - Negligence - Liability of Electricity Companies - Standard of Care - The appellants, being electricity distribution companies, owe a duty of care to maintain their transmission lines properly. Failure to prevent sagging and sparking of high voltage wires resulting in damage to adjacent crops constitutes negligence. The court held that the appellants failed to exercise reasonable care and were jointly and severally liable for the loss of 20,500 banana plants. (Paras 1-10) B) Evidence - Burden of Proof - Appreciation of Evidence - In a suit for damages based on negligence, the initial burden is on the plaintiff to prove negligence. However, when the defendant is a public utility and the plaintiff has adduced credible evidence of damage caused by the defendant's equipment, the burden shifts to the defendant to show due diligence. The court found that the respondents had discharged their burden by examining witnesses and producing documentary evidence, while the appellants failed to rebut the same. (Paras 5-8) C) Compensation - Assessment of Damages - Agricultural Loss - The court upheld the trial court's assessment of compensation at Rs.8.50 per plant for 20,500 banana plants, totaling Rs.1,74,250, with interest at 12% per annum from the date of suit till realization. The rate was based on the market value of banana plants and the extent of damage proved. (Paras 9-10)
Issue of Consideration
Whether the appellants (electricity companies) were negligent in maintaining the electric transmission line resulting in damage to the respondents' banana crop, and whether the respondents are entitled to compensation.
Final Decision
The appeal is dismissed with costs. The judgment and decree dated 28.2.1994 passed by the Joint Civil Judge, Sr.Dn., Yavatmal in Special Civil Suit No.2 of 1991 is confirmed.
Law Points
- Liability for negligence
- Standard of care for electricity companies
- Burden of proof in tort claims
- Compensation for agricultural loss
- Interest on compensation





