Bombay High Court Dismisses State's Appeal in Land Acquisition Case, Upholds Market Value of Rs.14 per sqm for New Bombay Satellite City. Cross Objection for Enhancement Dismissed as Time-Barred Under Order 21 Rule 22 CPC.

High Court: Bombay High Court Bench: BOMBAY
  • 49
Judgement Image
Font size:
Print

Case Note & Summary

The State of Maharashtra appealed against the Judgment and Award dated 30 November 1995 passed by the Land Acquisition Officer in a Reference under Section 18 of the Land Acquisition Act, 1894. The acquisition was for the purpose of setting up the satellite city of New Bombay, with notification under Section 4(1) issued on 3 February 1970. The Reference Court fixed the market value of the acquired land at Rs.14 per square meter and granted statutory benefits under Sections 23(1A), 23(2), and 28 of the Act. The State argued that the respondent-claimant failed to discharge the burden of proving that the compensation offered under Section 11 was inadequate. The respondent-claimant filed a Cross Objection on 22 June 2011 seeking enhancement, along with an application for condonation of delay. The respondent relied on a decision in First Appeal No.875 of 1985 and connected appeals, where this Court fixed market value at Rs.17.10 per sqm for similar lands. The State opposed the condonation, noting that under Order 21 Rule 22 CPC, cross-objection must be filed within one month from service of notice of appeal, and the delay of over 16 years was unexplained. The Court held that the respondent-claimant did not adduce sufficient evidence to prove inadequacy, but the Reference Court's award was based on comparable cases. However, the cross-objection was filed after the appeal was ready for hearing, and no explanation was given for the inordinate delay. Consequently, the Court dismissed the State's appeal and also dismissed the cross-objection as time-barred.

Headnote

A) Land Acquisition - Market Value Determination - Burden of Proof - Claimant must adduce evidence to prove inadequacy of compensation offered under Section 11 Award - The State contended that the respondent-claimant failed to discharge this burden, but the Court upheld the Reference Court's award of Rs.14 per sqm based on similarity to other appeals where Rs.17.10 per sqm was fixed (Paras 1-3).

B) Civil Procedure - Cross-Objection - Limitation - Order 21 Rule 22 CPC - Cross-objection must be filed within one month from service of notice of appeal - Delay of over 16 years (from 2002 to 2011) without sufficient explanation cannot be condoned - Cross-objection dismissed as time-barred (Paras 4-5).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Reference Court correctly fixed market value at Rs.14 per sqm and whether the cross-objection filed after 16 years delay should be condoned.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Court dismissed the State's appeal and also dismissed the cross-objection as time-barred.

Law Points

  • Burden of proof on claimant to show inadequacy of compensation
  • Condonation of delay for cross-objection
  • Application of Order 21 Rule 22 CPC
Subscribe to unlock Law Points Subscribe Now

Case Details

2011 LawText (BOM) (06) 67

First Appeal No. 1323 of 2002 alongwith Civil Application No. 2432 of 2011 and Cross Objection St. No. 16210 of 2011

2011-06-24

A.S. Oka

Mr. A. R. Patil, AGP for the appellant – State; Mr. S. M. Kamble for the respondent

The State of Maharashtra

Kalu Ladku Mhatre

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against award in land acquisition reference under Section 18 of the Land Acquisition Act, 1894.

Remedy Sought

State sought reduction of market value; claimant sought enhancement via cross-objection.

Filing Reason

State challenged the Reference Court's award of Rs.14 per sqm as excessive; claimant sought enhancement.

Previous Decisions

Reference Court fixed market value at Rs.14 per sqm with statutory benefits.

Issues

Whether the Reference Court correctly fixed the market value at Rs.14 per sqm? Whether the cross-objection filed after 16 years delay should be condoned?

Submissions/Arguments

State argued that claimant failed to discharge burden of proving inadequacy of compensation. Claimant relied on similar appeals where market value was fixed at Rs.17.10 per sqm. State opposed condonation of delay in cross-objection citing Order 21 Rule 22 CPC.

Ratio Decidendi

The claimant must adduce evidence to prove inadequacy of compensation; cross-objection must be filed within one month under Order 21 Rule 22 CPC, and inordinate delay without explanation cannot be condoned.

Judgment Excerpts

The appellant – State of Maharashtra has impugned Judgment and Award dated 30th November, 1995 passed by the Land Acquisition Officer in a Reference under Section 18 of the Land Acquisition Act, 1894. The submission of the learned AGP appearing for the appellant – State is that the respondent-claimant has not discharged the burden on him by adducing evidence to prove that the market value offered by an Award under Section 11 of the said Act is not adequate. He pointed out that under Rule 22 of Order XXI of the Code of Civil Procedure, 1908, the Cross Objection ought to have been be filed within one month from the date of service of notice of the Appeal.

Procedural History

Notification under Section 4(1) on 3 February 1970; Award under Section 11; Reference under Section 18; Reference Court award on 30 November 1995; State appeal filed in 2002; Cross-objection filed on 22 June 2011.

Acts & Sections

  • Land Acquisition Act, 1894: Section 4(1), Section 11, Section 18, Section 23(1A), Section 23(2), Section 28
  • Code of Civil Procedure, 1908: Order 21 Rule 22
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses State's Appeal in Land Acquisition Case, Upholds Market Value of Rs.14 per sqm for New Bombay Satellite City. Cross Objection for Enhancement Dismissed as Time-Barred Under Order 21 Rule 22 CPC.
Related Judgement
High Court Bombay High Court Dismisses Petition Challenging Tender Award by MHADA — No Violation of Natural Justice Found. Bidder's Challenge to Summary Rejection of Technical Bid Fails as Evaluation Was Based on Tender Conditions and No Prejudice Was Caused.