Case Note & Summary
The case involves a dispute between Oil and Natural Gas Corporation Limited (ONGC), the petitioner, and Oil Country Tubular Limited, the respondent, arising from a contract for supply of casing pipes. ONGC issued a tender on 25/10/1995, and an order was placed on 04/03/1996 for two lots of casing pipes, with delivery to be completed within 135 days. The respondent delivered the consignments on 30/11/1996, resulting in delays of 182 days for the first consignment and 136 days for the second. ONGC deducted an aggregate sum of US$42260.87 as liquidated damages from the price payable. The respondent disputed the deduction, leading to arbitration. The former Chief Justice of India, Mr. P.N. Bhagwati, was appointed as the sole arbitrator. The respondent filed a claim petition on 13/01/1999, ONGC filed a reply on 07/02/2001, and the respondent filed a rejoinder on 28/02/2001. The arbitrator passed an award on 30/06/2007, setting aside the deduction of liquidated damages, holding that ONGC had not proved any actual loss. ONGC challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, before the Bombay High Court. The court considered the limited scope of interference under Section 34, emphasizing that the court cannot reappreciate evidence or substitute its own view unless the award is patently illegal or against public policy. The court examined the arbitrator's findings on liquidated damages under Section 74 of the Indian Contract Act, 1872, and held that the arbitrator's conclusion that no actual loss was proved was a plausible view based on the evidence. The court rejected ONGC's argument that as a public sector undertaking, it was entitled to deduct liquidated damages without proof of loss. The court found no patent illegality or perversity in the award and dismissed the petition, upholding the arbitral award.
Headnote
A) Arbitration - Section 34 Petition - Challenge to Arbitral Award - Scope of Interference - The court considered the limited grounds for setting aside an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, including patent illegality and public policy. Held that the court cannot reappreciate evidence or substitute its own view unless the award is perverse or contrary to law (Paras 1-10). B) Contract Law - Liquidated Damages - Section 74 Indian Contract Act, 1872 - Actual Loss Requirement - The dispute pertained to deduction of US$42260.87 as liquidated damages for delayed supply of casing pipes. The court upheld the arbitral award setting aside the deduction, holding that under Section 74, the claimant must prove actual loss suffered; mere delay does not entitle automatic deduction. Held that the arbitrator's finding of no loss was a plausible view and not perverse (Paras 11-20). C) Public Sector Undertaking - Liquidated Damages - Applicability of Section 74 - The court rejected ONGC's argument that as a public sector undertaking, it was entitled to deduct liquidated damages without proof of loss. Held that the same principle of actual loss applies to all parties, including government entities, and the arbitrator's interpretation of the contract was reasonable (Paras 21-25).
Issue of Consideration
Whether the arbitral award setting aside liquidated damages deducted by ONGC for delayed supply of casing pipes is contrary to the terms of the contract and Section 74 of the Indian Contract Act, 1872, and whether it is patently illegal or against public policy under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The Bombay High Court dismissed the petition and upheld the arbitral award dated 30/06/2007, finding no patent illegality or perversity in the arbitrator's decision.
Law Points
- Liquidated damages
- Section 74 Indian Contract Act
- 1872
- actual loss requirement
- public sector undertaking
- arbitration award
- Section 34 Arbitration and Conciliation Act
- 1996
- public policy




