High Court of Bombay Dismisses Petition Challenging Arbitral Award in Contract Dispute — Rejects Challenge Under Section 34 of Arbitration and Conciliation Act, 1996. Arbitrator's findings on delay and damages held to be plausible and not perverse.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 4
Judgement Image
Font size:
Print

Case Note & Summary

The Union of India (Petitioner) challenged an arbitral award dated 28th March, 2007 (amended on 19th April, 2007) passed by the sole Arbitrator (Chief Engineer, Pune) in a dispute arising out of a contract for replacement of Central Airconditioning Plant at Wecors, Naval Dockyard, Mumbai. The contract was awarded to M/s. Arctic India (Respondent) on 15th June, 1996 for Rs. 2,85,83,220/-, with work order issued on 2nd July, 1996, site handed over on 4th July, 1996, and completion date set as 3rd May, 1997. The respondent commenced work but delays occurred. The arbitrator allowed the respondent's claims for additional costs, damages, and interest, and rejected the petitioner's counterclaim for damages due to delay. The petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, arguing that the award was contrary to public policy, perverse, and based on no evidence. The court examined the arbitrator's findings and held that the arbitrator had considered all evidence and given plausible reasons. The court noted that the arbitrator found the delay attributable to the petitioner, not the respondent. The court reiterated that under Section 34, the court cannot re-appreciate evidence or substitute its own view if the arbitrator's view is plausible. The court found no perversity or error of law, and dismissed the petition, upholding the award.

Headnote

A) Arbitration Law - Challenge to Arbitral Award - Section 34 of the Arbitration and Conciliation Act, 1996 - Public Policy - The court considered whether the award was contrary to public policy or perverse. Held that the court cannot re-appreciate evidence or substitute its own view if the arbitrator's view is plausible. The award was based on evidence and reasoning, and no ground for interference was made out. (Paras 1-20)

B) Contract Law - Delay and Damages - Breach of Contract - The dispute pertained to delay in completion of a contract for replacement of Central Airconditioning Plant. The arbitrator found that the delay was attributable to the petitioner (Union of India) and not the respondent contractor. Held that the findings on delay and damages were based on evidence and were not perverse. (Paras 2-15)

C) Arbitration Law - Counterclaim - Rejection of Counterclaim - The arbitrator rejected the petitioner's counterclaim for damages due to delay. The court held that the arbitrator's decision was plausible and not arbitrary, as the delay was not caused by the respondent. (Paras 16-20)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award dated 28th March, 2007 (amended on 19th April, 2007) is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on the grounds of being contrary to public policy, perverse, or based on no evidence.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court of Bombay dismissed the Arbitration Petition No. 388 of 2007, upholding the arbitral award dated 28th March, 2007 (amended on 19th April, 2007). No order as to costs.

Law Points

  • Arbitration and Conciliation Act
  • 1996
  • Section 34
  • Public policy
  • Perversity
  • Plausible view
  • Counterclaim
  • Damages
  • Interest
Subscribe to unlock Law Points Subscribe Now

Case Details

2011 LawText (BOM) (01) 53

Arbitration Petition No. 388 of 2007

2011-01-21

Anoop V. Mohta, J.

Mr. S.R. Rajguru i/by Ms. Anamika Malhotra for the Petitioners, Mr. Zal Andhyrujina i/by M/s. Thakore Jariwala & Co. for the Respondents

Union of India

M/s. Arctic India & Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Challenge to an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996.

Remedy Sought

The Petitioner (Union of India) sought to set aside the arbitral award dated 28th March, 2007 (amended on 19th April, 2007) passed by the sole Arbitrator.

Filing Reason

The Petitioner contended that the award was contrary to public policy, perverse, and based on no evidence.

Previous Decisions

The sole Arbitrator had allowed the Respondent's claims and rejected the Petitioner's counterclaim.

Issues

Whether the arbitral award is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on the grounds of being contrary to public policy, perverse, or based on no evidence.

Submissions/Arguments

The Petitioner argued that the award was contrary to public policy and perverse, as the arbitrator ignored evidence and failed to consider the delay caused by the Respondent. The Respondent argued that the arbitrator's findings were based on evidence and were plausible, and that the court should not interfere under Section 34.

Ratio Decidendi

Under Section 34 of the Arbitration and Conciliation Act, 1996, the court cannot re-appreciate evidence or substitute its own view if the arbitrator's view is plausible. The award is not liable to be set aside merely because another view is possible. The arbitrator's findings on delay and damages were based on evidence and were not perverse.

Judgment Excerpts

The Petitioner has challenged an award dated 28th March, 2007, amended on 19th April, 2007 passed by the sole Arbitrator... The court cannot re-appreciate evidence or substitute its own view if the arbitrator's view is plausible.

Procedural History

The contract was awarded on 15th June, 1996. Disputes arose, and the matter was referred to arbitration. The sole Arbitrator passed an award on 28th March, 2007 (amended on 19th April, 2007). The Petitioner filed Arbitration Petition No. 388 of 2007 under Section 34 of the Arbitration and Conciliation Act, 1996 challenging the award. The petition was dismissed on 21st January, 2011.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Bombay Dismisses Petition Challenging Arbitral Award in Contract Dispute — Rejects Challenge Under Section 34 of Arbitration and Conciliation Act, 1996. Arbitrator's findings on delay and damages held to be plausible and not perverse.
Related Judgement
Supreme Court Supreme Court Allows Secured Creditor's Appeal in Customs Duty Priority Dispute Over Wound-Up Company's Hypothecated Goods. Held that customs authorities do not have priority over secured creditors under Section 529A of Companies Act, 1956 for sale o...