High Court of Bombay Upholds Arbitral Award in Favor of Contractor in Railway Contract Dispute — Rejects Challenge Based on Excepted Matters and Delay in Raising Counterclaim. The court found no ground to interfere under Section 34 of the Arbitration and Conciliation Act, 1996, as the Arbitral Tribunal had considered the contractual provisions and extensions granted by consent.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 11
Judgement Image
Font size:
Print

Case Note & Summary

The case involves a challenge by the Union of India (Petitioner) against an Arbitral Award dated 16 December 2005 passed by the Arbitral Tribunal in a dispute arising out of a Contract Agreement for Works dated 17 December 1999 between the Union of India and M/s. Sagar Thermit Corp. Ltd. (Respondent). The contract was for cutting and cropping of rails and Almino Termite welding of rails by SKV process for a railway gauge conversion project, with a tendered cost of Rs.1,21,07,000 and a completion period of 5 months from 21 September 1999. The work was completed on 31 January 2001 after obtaining five extensions. The Respondent raised disputes/claims on 20 August 2001 and 21 February 2003, leading to the constitution of the Arbitral Tribunal by order of the High Court dated 21 February 2003. The Petitioner refuted the claims as 'Excepted matters' under the contract. The Arbitral Tribunal awarded nine out of thirteen claims in favor of the Respondent and rejected the Petitioner's counterclaim of Rs.1,61,50,000 on the ground of delay, as it was raised for the first time in a letter dated 14 August 2003, after arbitration proceedings had commenced. The Petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996. The court held that the Arbitral Tribunal had considered the contractual provisions and the extensions granted by consent, and found no ground to interfere with the award. The petition was dismissed.

Headnote

A) Arbitration Law - Challenge to Arbitral Award - Section 34 of the Arbitration and Conciliation Act, 1996 - Excepted Matters - The court considered whether claims that were 'Excepted matters' under the contract could be arbitrated. The Arbitral Tribunal had awarded nine out of thirteen claims in favor of the contractor. The court upheld the award, finding no ground to interfere under Section 34, as the tribunal had considered the contractual provisions and the extensions granted by consent. (Paras 1-10)

B) Arbitration Law - Counterclaim - Delay in Raising - Section 21 of the Arbitration and Conciliation Act, 1996 - The Railways' counterclaim for Rs.1,61,50,000 was rejected by the Arbitral Tribunal on the ground of delay, as it was raised for the first time in a letter dated 14/08/2003, after the arbitration proceedings had commenced. The court upheld this rejection, noting that extensions of time were granted by consent and the counterclaim was not raised earlier. (Paras 8-10)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Arbitral Tribunal's award granting claims to the contractor despite the claims being 'Excepted matters' under the contract and rejecting the Railways' counterclaim for delay is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court dismissed the Arbitration Petition, upholding the Arbitral Award dated 16 December 2005.

Law Points

  • Arbitration and Conciliation Act
  • 1996
  • Section 34
  • Section 21
  • Section 85
  • Excepted matters
  • Counterclaim
  • Delay
  • Extension of time
  • Public policy
Subscribe to unlock Law Points Subscribe Now

Case Details

2011:BHC-OS:688

Arbitration Petition No. 182 of 2006

2011-01-14

Anoop V. Mohta, J.

2011:BHC-OS:688

Mr. T.J. Pandiyan for the petitioners, Mr. Uday Samudrala for respondents

Union of India, through Dy. Chief Engineer (Const.) HQ Central Railway, Mumbai CST.

M/s. Sagar Thermit Corp. Ltd., B67, A.P.I.E., Balanagar, Hyderabad 500 037.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Challenge to an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996.

Remedy Sought

The Petitioner (Union of India) sought to set aside the Arbitral Award dated 16 December 2005.

Filing Reason

The Petitioner challenged the award on the ground that the claims were 'Excepted matters' under the contract and that the Arbitral Tribunal wrongly rejected its counterclaim.

Previous Decisions

The Arbitral Tribunal awarded nine out of thirteen claims in favor of the Respondent and rejected the Petitioner's counterclaim. The High Court had earlier referred the disputes to arbitration by order dated 21 February 2003.

Issues

Whether the Arbitral Tribunal erred in entertaining claims that were 'Excepted matters' under the contract? Whether the Arbitral Tribunal correctly rejected the Petitioner's counterclaim on the ground of delay?

Submissions/Arguments

The Petitioner argued that the claims were 'Excepted matters' under the contract and thus not arbitrable. The Petitioner also argued that its counterclaim for delay in execution should have been allowed. The Respondent contended that the Arbitral Tribunal had considered the contractual provisions and extensions granted by consent, and the award was not liable to be set aside.

Ratio Decidendi

The court held that the Arbitral Tribunal had considered the contractual provisions and the extensions granted by consent, and there was no ground to interfere with the award under Section 34 of the Arbitration and Conciliation Act, 1996. The rejection of the counterclaim on the ground of delay was also upheld as the counterclaim was raised after arbitration proceedings had commenced.

Judgment Excerpts

The Petitioners have challenged an Award dated 16 December 2005 passed by the Arbitrator appointed in a dispute arising out of a Contract Agreement for Works dated 17 December 1999, between the parties with regard to a rail contract work. The Petitioners’ counter claim for an amount of Rs.1,61,50,000/ was rejected totally on the ground of delay in execution of work.

Procedural History

The contract was awarded on 21 September 1999. Work completed on 31 January 2001 after five extensions. Respondent raised claims on 20 August 2001 and 21 February 2003. High Court referred disputes to arbitration on 21 February 2003. Arbitral Tribunal constituted on 14 August 2003. Award passed on 16 December 2005. Petitioner filed Arbitration Petition No. 182 of 2006 challenging the award. Judgment pronounced on 14 January 2011.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 21, Section 34, Section 85
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Petition Seeking Inclusion of Area in Municipal Limits — No Cause of Action as Government Already Considering Inclusion. Petitioners Sought Mandamus for Inclusion of 'Collectors Patta' in Malegaon Municipal Corporation b...
Related Judgement
High Court High Court of Bombay at Goa Allows Appeal in Land Acquisition Case — Market Value Enhanced to Rs.66 per Square Metre for Konkan Railway Project. Comparable Sale Deeds of Nearby Land at Rs.64 and Rs.66 per Square Metre Form Basis for Valuation Under...