Case Note & Summary
The case involves a challenge by the Union of India (Petitioner) against an Arbitral Award dated 16 December 2005 passed by the Arbitral Tribunal in a dispute arising out of a Contract Agreement for Works dated 17 December 1999 between the Union of India and M/s. Sagar Thermit Corp. Ltd. (Respondent). The contract was for cutting and cropping of rails and Almino Termite welding of rails by SKV process for a railway gauge conversion project, with a tendered cost of Rs.1,21,07,000 and a completion period of 5 months from 21 September 1999. The work was completed on 31 January 2001 after obtaining five extensions. The Respondent raised disputes/claims on 20 August 2001 and 21 February 2003, leading to the constitution of the Arbitral Tribunal by order of the High Court dated 21 February 2003. The Petitioner refuted the claims as 'Excepted matters' under the contract. The Arbitral Tribunal awarded nine out of thirteen claims in favor of the Respondent and rejected the Petitioner's counterclaim of Rs.1,61,50,000 on the ground of delay, as it was raised for the first time in a letter dated 14 August 2003, after arbitration proceedings had commenced. The Petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996. The court held that the Arbitral Tribunal had considered the contractual provisions and the extensions granted by consent, and found no ground to interfere with the award. The petition was dismissed.
Headnote
A) Arbitration Law - Challenge to Arbitral Award - Section 34 of the Arbitration and Conciliation Act, 1996 - Excepted Matters - The court considered whether claims that were 'Excepted matters' under the contract could be arbitrated. The Arbitral Tribunal had awarded nine out of thirteen claims in favor of the contractor. The court upheld the award, finding no ground to interfere under Section 34, as the tribunal had considered the contractual provisions and the extensions granted by consent. (Paras 1-10) B) Arbitration Law - Counterclaim - Delay in Raising - Section 21 of the Arbitration and Conciliation Act, 1996 - The Railways' counterclaim for Rs.1,61,50,000 was rejected by the Arbitral Tribunal on the ground of delay, as it was raised for the first time in a letter dated 14/08/2003, after the arbitration proceedings had commenced. The court upheld this rejection, noting that extensions of time were granted by consent and the counterclaim was not raised earlier. (Paras 8-10)
Issue of Consideration
Whether the Arbitral Tribunal's award granting claims to the contractor despite the claims being 'Excepted matters' under the contract and rejecting the Railways' counterclaim for delay is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The High Court dismissed the Arbitration Petition, upholding the Arbitral Award dated 16 December 2005.
Law Points
- Arbitration and Conciliation Act
- 1996
- Section 34
- Section 21
- Section 85
- Excepted matters
- Counterclaim
- Delay
- Extension of time
- Public policy





