Case Note & Summary
The appellant, Biwater Penstocks Ltd., a UK-based company, entered into a contract with the Municipal Corporation of Greater Bombay (first respondent) for the manufacture, supply, and delivery of 171 sluice gates, including supervision of erection and commissioning. Disputes arose, and as per the contract, claims were required to be first made before the Chief Engineer and then the Commissioner before arbitration. A sole Arbitrator was appointed, and the appellant filed a statement of claims on 25 counts. The respondent objected to 17 claims on the ground that they were never raised before the Chief Engineer or Commissioner. The parties agreed to refer the dispute to the Arbitrator to decide whether those 17 claims were within his jurisdiction. The Arbitrator decided the remaining 8 claims and made a non-speaking award directing the respondent to pay UK Pounds 3,77,252.91 plus Rs. 1,67,164.96 with interest. The respondent challenged the award before the Bombay High Court in Arbitration Petition No. 124 of 1994. The learned single Judge held that the Arbitrator committed an error in concluding he had jurisdiction to decide the eight claims, as he had no jurisdiction to entertain claims in excess of the amount claimed before the Chief Engineer and Commissioner. The single Judge found that the Arbitrator ignored relevant material on the jurisdictional fact and set aside the award, remitting the matter to the Arbitrator for de novo consideration. The appellant appealed against this order. The Division Bench of the High Court, comprising Justices P.B. Majmudar and Anoop V. Mohta, dismissed the appeal, upholding the single Judge's order. The Court held that the Arbitrator exceeded his jurisdiction by entertaining claims not raised before the Chief Engineer and Commissioner, and the remission for de novo consideration was appropriate.
Headnote
A) Arbitration Law - Jurisdiction of Arbitrator - Pre-arbitration Procedure - Contractual Condition Precedent - The dispute pertained to a contract for supply of sluice gates where the contract required claims to be first made before the Chief Engineer and Commissioner before arbitration. The Arbitrator entertained claims that were not raised before those authorities. The High Court held that the Arbitrator exceeded his jurisdiction by deciding claims beyond the scope of the pre-arbitration procedure, and the learned single Judge correctly set aside the award and remitted the matter for de novo consideration. (Paras 2-4, 6-7) B) Arbitration Law - Non-speaking Award - Jurisdictional Error - Setting Aside - The Arbitrator passed a non-speaking award without reasons. The learned single Judge found that the Arbitrator ignored relevant material regarding the jurisdictional fact of whether claims were raised before the Chief Engineer and Commissioner. The High Court upheld that this constituted a jurisdictional error warranting setting aside of the award under Section 34 of the Arbitration and Conciliation Act, 1996. (Paras 4-6) C) Arbitration Law - Remission to Arbitrator - De Novo Consideration - After setting aside the award for jurisdictional error, the learned single Judge remitted the matter to the Arbitrator for de novo consideration. The High Court affirmed this order, holding that remission is appropriate to allow the Arbitrator to decide the claims afresh within the proper jurisdictional limits. (Paras 6-7)
Issue of Consideration
Whether the learned single Judge was justified in setting aside the arbitral award and remitting the matter to the Arbitrator for de novo consideration on the ground that the Arbitrator had no jurisdiction to entertain claims in excess of the amount claimed before the Chief Engineer and the Commissioner.
Final Decision
The High Court dismissed the appeal, upholding the order of the learned single Judge setting aside the arbitral award and remitting the matter to the Arbitrator for de novo consideration.
Law Points
- Arbitrator's jurisdiction is limited by contractual pre-arbitration procedure
- Arbitrator cannot entertain claims not raised before Chief Engineer and Commissioner
- Non-speaking award can be set aside if jurisdictional fact is ignored
- Remission to arbitrator for de novo consideration is appropriate when award is set aside for jurisdictional error





