Case Note & Summary
The Government of Goa, represented by the Director of Tourism, filed an appeal under Section 37(1)(a) of the Arbitration and Conciliation Act, 1996, challenging an order dated 29 April 2009 passed by the learned Principal District Judge, South Goa, Margao, in Arbitration Application No. 7 of 2009. The respondent, Jaisu Shipping Co. Pvt. Ltd., had filed an application under Section 9 of the Act seeking interim relief. The respondent was a contractor appointed under an agreement dated 5 January 2007 with the appellant for the removal of a vessel. Disputes arose, and the appellant issued a show cause notice dated 5 June 2008 and encashed a performance guarantee of Rs.5,50,00,000/-. The respondent sought interim orders restraining the appellant from interfering with its work, terminating the agreement, or taking further action pursuant to the show cause notice, and also sought a mandatory injunction for reimbursement of the encashed amount. The District Judge allowed the application, granting both prohibitory and mandatory injunctions. The appellant challenged this order in the High Court. The High Court, after hearing arguments, upheld the District Judge's order, finding that the respondent had made out a strong prima facie case, the balance of convenience was in its favor, and irreparable injury would be caused if the injunction was not granted. The court noted that the performance guarantee was wrongfully appropriated and that the mandatory injunction was necessary to restore the status quo pending arbitration. The appeal was dismissed.
Headnote
A) Arbitration - Interim Measures - Section 9 of the Arbitration and Conciliation Act, 1996 - Mandatory Injunction - The court considered whether a mandatory injunction can be granted under Section 9 to direct reimbursement of an allegedly wrongfully encashed performance guarantee. Held that where a strong prima facie case exists and balance of convenience favors the applicant, a mandatory injunction can be granted to restore status quo ante pending arbitration (Paras 3-10). B) Arbitration - Performance Guarantee - Wrongful Encashment - Section 9 of the Arbitration and Conciliation Act, 1996 - The court examined whether the encashment of the performance guarantee by the appellant was wrongful. Held that the appellant's action in appropriating the guarantee without proper justification constituted a breach, warranting interim protection for the respondent (Paras 5-8). C) Arbitration - Interim Relief - Balance of Convenience - Section 9 of the Arbitration and Conciliation Act, 1996 - The court assessed the balance of convenience between the parties. Held that the respondent would suffer irreparable injury if the injunction was not granted, whereas the appellant could be adequately compensated by damages (Paras 9-12).
Issue of Consideration
Whether the learned District Judge was justified in granting interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, including a mandatory injunction for reimbursement of the amount of the performance guarantee and restraining the appellant from interfering with the respondent's work.
Final Decision
The High Court dismissed the appeal and upheld the order of the learned Principal District Judge, South Goa, Margao, dated 29 April 2009, granting interim relief under Section 9 of the Arbitration and Conciliation Act, 1996.
Law Points
- Section 9 of the Arbitration and Conciliation Act
- 1996
- interim measures
- mandatory injunction
- performance guarantee
- wrongful encashment
- balance of convenience
- prima facie case
- irreparable injury



