High Court of Bombay at Goa Upholds Interim Injunction in Arbitration Matter — Government Restrained from Interfering with Contractor's Work. Performance Guarantee Encashment Found Wrongful; Mandatory Injunction for Reimbursement of Rs.5,50,00,000/- Granted Under Section 9 of Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: GOA In Favour of Accused
  • 5
Judgement Image
Font size:
Print

Case Note & Summary

The Government of Goa, represented by the Director of Tourism, filed an appeal under Section 37(1)(a) of the Arbitration and Conciliation Act, 1996, challenging an order dated 29 April 2009 passed by the learned Principal District Judge, South Goa, Margao, in Arbitration Application No. 7 of 2009. The respondent, Jaisu Shipping Co. Pvt. Ltd., had filed an application under Section 9 of the Act seeking interim relief. The respondent was a contractor appointed under an agreement dated 5 January 2007 with the appellant for the removal of a vessel. Disputes arose, and the appellant issued a show cause notice dated 5 June 2008 and encashed a performance guarantee of Rs.5,50,00,000/-. The respondent sought interim orders restraining the appellant from interfering with its work, terminating the agreement, or taking further action pursuant to the show cause notice, and also sought a mandatory injunction for reimbursement of the encashed amount. The District Judge allowed the application, granting both prohibitory and mandatory injunctions. The appellant challenged this order in the High Court. The High Court, after hearing arguments, upheld the District Judge's order, finding that the respondent had made out a strong prima facie case, the balance of convenience was in its favor, and irreparable injury would be caused if the injunction was not granted. The court noted that the performance guarantee was wrongfully appropriated and that the mandatory injunction was necessary to restore the status quo pending arbitration. The appeal was dismissed.

Headnote

A) Arbitration - Interim Measures - Section 9 of the Arbitration and Conciliation Act, 1996 - Mandatory Injunction - The court considered whether a mandatory injunction can be granted under Section 9 to direct reimbursement of an allegedly wrongfully encashed performance guarantee. Held that where a strong prima facie case exists and balance of convenience favors the applicant, a mandatory injunction can be granted to restore status quo ante pending arbitration (Paras 3-10).

B) Arbitration - Performance Guarantee - Wrongful Encashment - Section 9 of the Arbitration and Conciliation Act, 1996 - The court examined whether the encashment of the performance guarantee by the appellant was wrongful. Held that the appellant's action in appropriating the guarantee without proper justification constituted a breach, warranting interim protection for the respondent (Paras 5-8).

C) Arbitration - Interim Relief - Balance of Convenience - Section 9 of the Arbitration and Conciliation Act, 1996 - The court assessed the balance of convenience between the parties. Held that the respondent would suffer irreparable injury if the injunction was not granted, whereas the appellant could be adequately compensated by damages (Paras 9-12).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the learned District Judge was justified in granting interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, including a mandatory injunction for reimbursement of the amount of the performance guarantee and restraining the appellant from interfering with the respondent's work.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court dismissed the appeal and upheld the order of the learned Principal District Judge, South Goa, Margao, dated 29 April 2009, granting interim relief under Section 9 of the Arbitration and Conciliation Act, 1996.

Law Points

  • Section 9 of the Arbitration and Conciliation Act
  • 1996
  • interim measures
  • mandatory injunction
  • performance guarantee
  • wrongful encashment
  • balance of convenience
  • prima facie case
  • irreparable injury
Subscribe to unlock Law Points Subscribe Now

Case Details

2010 LawText (BOM) (08) 132

Appeal from Order No. 39 of 2009

2010-08-05

A. S. Oka, F. M. Reis

Mr. S. S. Kantak, Advocate General with Mr. Abhijeet Kamat, Additional Government Advocate for the Appellant; Mr. S. D. Lotlikar, Senior Advocate with Ms. Jimi John, Advocate for the Respondent

Government of Goa, represented by the Director of Tourism

Jaisu Shipping Co. Pvt. Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal under Section 37(1)(a) of the Arbitration and Conciliation Act, 1996 against an order granting interim relief under Section 9 of the Act.

Remedy Sought

The appellant sought to set aside the order of the District Judge granting prohibitory and mandatory injunctions in favor of the respondent.

Filing Reason

The appellant challenged the interim order on the ground that the District Judge erred in granting mandatory injunction and restraining the appellant from interfering with the respondent's work.

Previous Decisions

The learned Principal District Judge, South Goa, Margao, allowed Arbitration Application No. 7 of 2009 on 29 April 2009, granting interim relief including a mandatory injunction for reimbursement of Rs.5,50,00,000/-.

Issues

Whether the District Judge was justified in granting a mandatory injunction under Section 9 of the Arbitration and Conciliation Act, 1996 directing reimbursement of the performance guarantee amount. Whether the balance of convenience and prima facie case favored the grant of interim relief.

Submissions/Arguments

The appellant argued that the District Judge erred in granting a mandatory injunction which is not ordinarily granted at an interim stage. The respondent contended that the performance guarantee was wrongfully encashed and that without interim protection, the arbitration would be rendered infructuous.

Ratio Decidendi

Under Section 9 of the Arbitration and Conciliation Act, 1996, a court can grant interim measures including mandatory injunctions if a strong prima facie case is made out, balance of convenience favors the applicant, and irreparable injury would result if the relief is not granted. The wrongful encashment of a performance guarantee can be remedied by a mandatory injunction to restore the status quo pending arbitration.

Judgment Excerpts

The above Appeal filed under Section 37(1)(a) of the Arbitration and Conciliation Act, 1996, challenges the Judgment and Order dated 29th April, 2009... The Respondents are also secured by an order of mandatory injunction directing the Appellants to reimburse the amount of Rs.5,50,00,000/- having earlier come to a conclusion that the Performance Guarantee was wrongly appropriated by the Appellants in encashing the same.

Procedural History

The respondent filed an application under Section 9 of the Arbitration and Conciliation Act, 1996 before the Principal District Judge, South Goa, Margao, which was allowed on 29 April 2009. The appellant filed an appeal under Section 37(1)(a) of the Act before the High Court of Bombay at Goa, which was heard and dismissed on 5 August 2010.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9, Section 37(1)(a)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Bombay at Goa Upholds Interim Injunction in Arbitration Matter — Government Restrained from Interfering with Contractor's Work. Performance Guarantee Encashment Found Wrongful; Mandatory Injunction for Reimbursement of Rs.5,50,00,000/...
Related Judgement
High Court Bombay High Court Allows Land Owners' Petition Against Refusal to Register Sale Deeds in MIDC Area. Notification Under Section 1(3) of MIDC Act Does Not Bar Registration of Plots in Layouts Sanctioned Prior to Notification.