Case Note & Summary
The petitioner, M/s. Reunion Engineering Co. Pvt. Ltd., was awarded a contract on 23 January 2002 by the respondent, M/s. Petronet MHB Ltd., to lay cables at three locations: Mangalore, Hasan, and Bangalore. On 25 May 2003, the petitioner submitted two bills amounting to Rs.3,98,36,227.20. The respondent certified an amount of Rs.3,97,06,417 but failed to make payment. The petitioner filed Company Petition No.15 of 2006 in the Karnataka High Court to recover dues, during which the respondent paid Rs.30,20,975 as part payment. The petitioner then invoked arbitration, and a subordinate of the respondent's Managing Director was appointed as arbitrator, which the petitioner challenged on grounds of bias. On 11 July 2007, the petitioner demanded the balance amount with interest. On 18 September 2007, a Statement of Claim was filed for the balance amount of Rs.19,54,593. The respondent filed a reply stating that amounts under different heads were deductible and nothing was due. Several affidavits and counter affidavits were filed, but no evidence was led by either party. On 6 March 2010, after hearing both sides, the sole arbitrator rejected the petitioner's claim. Aggrieved, the petitioner filed an Arbitration Petition under Section 34 of the Arbitration and Conciliation Act, 1996 on 4 June 2010. The court examined the arbitrator's findings, noting that the arbitrator had framed points for determination and concluded that the deductions made by the respondent were justified based on the documents on record. The court held that the arbitrator's findings were not perverse or patently illegal, and that the petitioner's failure to lead evidence was fatal to its claim. The court dismissed the petition, upholding the award.
Headnote
A) Arbitration Law - Challenge to Arbitral Award - Section 34 of Arbitration and Conciliation Act, 1996 - Interference with findings of fact - The court considered whether the arbitral award rejecting the claim for balance payment was perverse or patently illegal. Held that the arbitrator's findings on deductions and lack of evidence were based on material on record and not open to interference under Section 34. (Paras 1-10) B) Arbitration Law - No Evidence Led - Section 34 of Arbitration and Conciliation Act, 1996 - Burden of proof - The petitioner did not lead any evidence to support its claim. The arbitrator's conclusion that the deductions were justified was based on documents and not perverse. Held that the award cannot be set aside on ground of no evidence when parties chose not to lead evidence. (Paras 5-10)
Issue of Consideration
Whether the arbitral award rejecting the petitioner's claim for balance payment under a cable laying contract is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The court dismissed the Arbitration Petition No. 965 of 2010, upholding the arbitral award dated 6 March 2010.
Law Points
- Arbitration award
- Section 34 of Arbitration and Conciliation Act
- 1996
- interference with arbitral award
- no evidence led
- deductions justified
- no perversity
- no patent illegality



