Case Note & Summary
The plaintiff, M/s Ajay Deep Construction Pvt. Ltd., filed a suit against the Maharashtra State Police Housing & Welfare Corporation Ltd. for recovery of Rs.1,09,78,024 together with interest. The dispute arose from a construction contract for building 650 quarters for policemen at Amravati. The plaintiff completed the work within the stipulated time and the quality was undisputed. The plaintiff claimed payment for three unpaid items of work: extra items, star rate items, and escalation on star rate items. Additionally, the plaintiff claimed refund of excess interest recovered by the defendant from mobilisation advance, and interest on delayed payments of running account bills, escalation bills, and the final bill. The defendant contested the claims, arguing that the unpaid items were not due under the contract, the mobilisation advance interest was correctly recovered, and there was no stipulated date for payment of running bills. The court framed issues and after considering evidence, held that the plaintiff was entitled to payment for the three unpaid items as the work was completed and accepted. The court also held that the defendant could only recover interest on mobilisation advance at the contracted rate of 12% per annum, not 18%, and must refund the excess. Regarding delayed payments, the court found that the contract specified payment periods and the defendant's delays entitled the plaintiff to interest under Section 61 of the Indian Contract Act, 1872. The court awarded interest at 12% per annum on delayed payments of running account bills, escalation bills, and the final bill. The suit was decreed in favor of the plaintiff with costs.
Headnote
A) Contract Law - Construction Contract - Unpaid Work Items - The court considered whether the plaintiff was entitled to payment for three specific items of work (extra items, star rate items, and escalation on star rate items) which were not paid by the defendant. The court held that the plaintiff had completed the work and the defendant had accepted the benefit, thus the plaintiff was entitled to payment for these items as per the contract rates and recommendations of the project management consultant. (Paras 5-10) B) Contract Law - Mobilisation Advance - Recovery of Interest - The court examined whether the defendant was entitled to recover interest on mobilisation advance at 18% per annum when the contract stipulated interest at 12% per annum. The court held that the defendant could only recover interest at the contracted rate of 12% and must refund the excess recovered. (Paras 11-13) C) Interest Law - Delayed Payments - Running Account Bills and Escalation Bills - The court determined whether the plaintiff was entitled to interest on delayed payments of running account bills and escalation bills. The court held that the contract provided for payment within a specified period, and the defendant's delay in making payments entitled the plaintiff to interest under Section 61 of the Indian Contract Act, 1872. The court awarded interest at 12% per annum on delayed payments. (Paras 14-18) D) Interest Law - Final Bill - Interest on Unpaid Amount - The court considered whether the plaintiff was entitled to interest on the unpaid amount of the final bill. The court held that the plaintiff was entitled to interest on the unpaid amount from the date the amount became due until payment. (Paras 19-20)
Issue of Consideration
Whether the plaintiff is entitled to payment for three unpaid items of work, refund of excess interest recovered from mobilisation advance, and interest on delayed payments of running account bills, escalation bills, and final bill.
Final Decision
The suit is decreed in favor of the plaintiff with costs. The defendant is directed to pay the plaintiff the amount of Rs.1,09,78,024 together with interest at 12% per annum from the date of filing of the suit until payment. The defendant is also directed to refund the excess interest recovered from mobilisation advance.
Law Points
- Interest on delayed payments
- Mobilisation advance recovery
- Unpaid work items
- Construction contract interpretation
- Section 61 Indian Contract Act
- 1872



