Bombay High Court Dismisses State's Challenge to Arbitral Award in Construction Dispute — Compensation for Delay Upheld. Majority Award on Claim for Losses Due to Delay Not Perverse or Contrary to Contract Terms Under Section 34 of Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 5
Judgement Image
Font size:
Print

Case Note & Summary

The State of Maharashtra, through the Chief Engineer (Special Projects), Public Works Department, and the Executive Engineer, filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated 29 March 2002. The dispute arose from a construction contract for the Bhiwandi-Wada Road and Palghar-Manor-Wada Road projects. The respondent, Bharat Constructions, was awarded the work on 1 November 1990, with a completion period of 30 calendar months from 1 December 1990. The work was delayed, and the petitioners granted extensions of time. Disputes arose regarding amounts due, leading to arbitration before a three-member tribunal. The majority arbitrators partly allowed the respondent's claims, including claim No.2 for compensation for losses due to delay. The dissenting arbitrator rejected claim No.2. The petitioners challenged only the majority award on claim No.2, arguing that the award was contrary to the contract terms, perverse, and against public policy. The court, after hearing arguments, held that the scope of interference under Section 34 is limited. The majority award was based on evidence and plausible reasoning; the court found no perversity or patent illegality. The petition was dismissed, upholding the majority award on claim No.2.

Headnote

A) Arbitration Law - Section 34 of Arbitration and Conciliation Act, 1996 - Scope of Interference - Challenge to majority award on claim for compensation for delay - Court held that the scope of interference under Section 34 is limited to grounds of patent illegality, perversity, or conflict with public policy; the court cannot re-appreciate evidence or substitute its own view. (Paras 5-10)

B) Arbitration Law - Compensation for Delay - Construction Contract - Majority Award - The majority arbitrators allowed claim No.2 for compensation for losses incurred due to delay in completion of work, relying on evidence of prolongation and extra expenditure. The dissenting arbitrator rejected the claim. The court held that the majority view was plausible and not perverse, and thus not open to interference. (Paras 3-8)

C) Arbitration Law - Public Policy - Perversity - The court held that a finding of fact by the arbitral tribunal, even if erroneous, does not amount to perversity unless it is based on no evidence or is so unreasonable that no reasonable person would arrive at it. The majority award did not suffer from such infirmity. (Paras 7-10)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the majority arbitral award granting compensation for losses due to delay in completion of work under claim No.2 is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996, on grounds of being contrary to the terms of the contract, perverse, or in conflict with the public policy of India.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The petition is dismissed. The majority award on claim No.2 is upheld.

Law Points

  • Section 34 of Arbitration and Conciliation Act
  • 1996
  • scope of interference with arbitral award
  • compensation for delay in construction contract
  • majority award vs dissenting award
  • perversity
  • public policy
Subscribe to unlock Law Points Subscribe Now

Case Details

2022 LawText (BOM) (12) 69

Arbitration Petition No. 245 of 2002

2022-12-06

Manish Pitale, J

Mr. Kedar Dighe, AGP for petitioners-State; Mr. M. P. Vashi, Senior Counsel a/w. Ms. Prachi Khandge, i/by. M. P. Vashi & Associates for respondent

The State of Maharashtra, Through the Chief Engineer (Special Projects), Public Works Department and another

Bharat Constructions

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award.

Remedy Sought

The petitioners (State of Maharashtra) sought to set aside the majority award on claim No.2, which granted compensation for losses due to delay in completion of work.

Filing Reason

The petitioners contended that the majority award on claim No.2 was contrary to the terms of the contract, perverse, and against the public policy of India.

Previous Decisions

The arbitral tribunal passed a majority award on 29 March 2002, partly allowing the respondent's claims, with a dissenting award by one arbitrator. The petition was admitted on 18 November 2002, limited to challenge on claim No.2. A review petition was filed and allowed to correct an inadvertent disposal observation.

Issues

Whether the majority award on claim No.2 (compensation for delay) is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.

Submissions/Arguments

Petitioners (State): The majority award erroneously allowed claim No.2; it is contrary to the contract terms, perverse, and against public policy. Respondent (Bharat Constructions): The award is based on evidence and plausible reasoning; no interference warranted under Section 34.

Ratio Decidendi

The scope of interference under Section 34 of the Arbitration and Conciliation Act, 1996, is limited to grounds of patent illegality, perversity, or conflict with public policy. The court cannot re-appreciate evidence or substitute its own view. The majority award on claim No.2 was based on evidence and plausible reasoning, and was not perverse or contrary to the contract terms.

Judgment Excerpts

The majority arbitrators partly upheld the claims of the respondent. The challenge in the petition was limited to the majority award on claim No.2, which pertained to compensation for losses incurred due to delay in completion of work. The scope of interference under Section 34 is limited to grounds of patent illegality, perversity, or conflict with public policy.

Procedural History

The arbitral tribunal passed a majority award on 29 March 2002. The petitioners filed Arbitration Petition No. 245 of 2002 under Section 34 of the Arbitration and Conciliation Act, 1996. The petition was admitted on 18 November 2002, limited to challenge on claim No.2. A review petition was filed and allowed to correct an inadvertent disposal observation. The petition was heard and dismissed on 6 December 2022.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses State's Challenge to Arbitral Award in Construction Dispute — Compensation for Delay Upheld. Majority Award on Claim for Losses Due to Delay Not Perverse or Contrary to Contract Terms Under Section 34 of Arbitration and ...
Related Judgement
High Court Bombay High Court Acquits Four Accused in Murder Case Due to Unreliable Testimony of Interested Witnesses and Lack of Corroboration. Conviction under Sections 302, 307, 324, 143, 147, 148, 149 IPC set aside as sole eye-witness was a close relative of...