Case Note & Summary
These clubbed commercial arbitration petitions came before the Bombay High Court's Commercial Division to resolve a common preliminary question arising in applications under Section 9 of the Arbitration and Conciliation Act, 1996. The petitioners, which included financial and commercial entities as well as individuals, had sought interim measures from the court either before or during arbitral proceedings. The respondents opposed each petition on the ground that the document or instrument containing the arbitration agreement or clause was either not stamped or insufficiently stamped under the Indian Stamp Act, 1899 or the Maharashtra Stamp Act, 1958. The court was therefore required to decide whether, after the Constitution Bench judgment in N.N.Global Mercantile v. Indo Unique Flame Ltd. & Ors., a court entertaining a Section 9 petition could grant interim relief despite noticing that the arbitration agreement suffered from a stamping deficiency. The court noted that the petitions were clubbed because they raised the same legal issue. It set out the background of the Arbitration and Conciliation Act, 1996, including the definition of arbitration agreement under Section 7, the power of judicial authority to refer parties to arbitration under Section 8, and the scheme of interim measures under Section 9. The court reproduced Section 9 and observed that the court has jurisdiction before, during, or after arbitral proceedings but before enforcement, and that the power under Section 9 is subject to two riders: arbitration must commence within ninety days if an order is passed before commencement, and once the tribunal is constituted, the court shall not entertain an application unless remedy under Section 17 is inefficacious. The court also referred to Section 11 regarding appointment of arbitrators. The arguments were sharply divided. One set of counsel argued that the Constitution Bench in N.N.Global had declared that the bar in Section 35 of the Stamp Act applies to arbitration agreements, so an unstamped or insufficiently stamped agreement is non-existent and unenforceable until validated under the Stamp Act. They contended that not every agreement is a contract; only enforceable agreements are contracts under Section 2(g) of the Indian Contract Act, 1872, and an unenforceable agreement is void. Stamping was said to be a substantive objection, and the court should not aid a party on the basis of an invalid document. The contrary set of counsel argued that N.N.Global dealt with an application under Section 11, whereas Section 9 stands on a different footing: Section 11 is part of evidentiary proceedings leading to an award, but Section 9 is merely an interim measure and not a stage to ascertain stamping. They submitted that the court should entertain the petition to protect rights from being frustrated. The court's analysis in the extracted text focused on the nature of the legal debate and the relevant statutory provisions, but the final decision and ratio on the maintainability of the Section 9 petitions were not included in the provided judgment text. The matter was reserved on 27 July 2023 and pronounced on 27 October 2023.
Headnote
A) Arbitration Law - Interim Measures - Maintainability of Section 9 Petition Despite Unstamped Arbitration Agreement - Arbitration and Conciliation Act, 1996, Sections 9, 7, 11; Indian Stamp Act, 1899, Section 35; Indian Contract Act, 1872, Section 2(g) - The court considered whether a petition under Section 9 for interim measures can be entertained when the arbitration agreement is unstamped or insufficiently stamped, in light of N.N.Global Mercantile v. Indo Unique Flame Ltd. & Ors. One set of counsel argued that the Constitution Bench had declared that Section 35 of the Stamp Act bars unstamped arbitration agreements, rendering them unenforceable and non-contracts under Section 2(g) Contract Act. The opposing counsel argued that N.N.Global arose under Section 11, which is evidentiary, while Section 9 is a mere interim measure and not the stage to examine stamping. The court set out the statutory framework and the rival contentions but the final holding on the issue was not included in the provided text (Paras 1-6). B) Contract Law - Enforceability of Agreements - Unstamped Agreements Not Contracts - Indian Contract Act, 1872, Section 2(g); Indian Stamp Act, 1899, Section 35 - The court noted the argument that only an enforceable agreement is a contract, and an unstamped agreement is void under Section 2(g) Contract Act read with Section 35 Stamp Act. The court referred to the distinction between agreements and contracts and the effect of stamping as a substantive objection, but did not pronounce a final decision in the extracted text (Paras 1-6).
Issue of Consideration
Whether in the wake of the Constitution Bench judgment in N.N.Global Mercantile Vs. Indo Unique Flame Ltd. & Ors., the Court, which is to decide the Petition filed under Section 9 of the Arbitration and Conciliation Act, 1996, seeking relief in form of interim measures, can entertain the same, despite noticing that the Agreement is not stamped or insufficiently stamped and suffers from a legal deficiency.
Law Points
- Arbitration agreement must be enforceable to be a contract
- Section 35 of Stamp Act bars unstamped instruments
- Section 9 interim measures are distinct from Section 11 evidentiary proceedings
- unstamped arbitration agreement may be non-existent until validated under Stamp Act
- not every agreement is a contract under Section 2(g) Contract Act



