Case Note & Summary
The Municipal Corporation of Greater Mumbai (MCGM) filed a writ petition under Article 226 of the Constitution of India seeking a mandamus to permit the execution of a project for a suction tank near Gorai Village to provide adequate water supply. The project site, located at CTS No. 1145 (Survey No. 265/A), is partly within a 50-meter mangrove buffer zone. The petition arose from observations in a previous judgment in PIL No. 87 of 2006 (Bombay Environment Action Group v. State of Maharashtra), which had directed that no construction be allowed in mangrove buffer zones without prior clearance. MCGM argued that the project was essential for public water supply and that it had applied for necessary permissions. The court considered whether the project could proceed without prior CRZ clearance. It noted that the project was for a public utility and that the authorities had not yet decided on MCGM's application. The court directed the respondent authorities to consider MCGM's application for permission within four weeks, and restrained MCGM from carrying out any construction until such permission was granted. The petition was disposed of accordingly.
Headnote
A) Environmental Law - Coastal Regulation Zone - Mangrove Buffer Zone - Public Interest - The court considered whether a municipal corporation could construct a suction tank for water supply within a 50-meter mangrove buffer zone without prior CRZ clearance. The court held that the project, being for public water supply, was permissible subject to conditions and that the authorities must consider the application expeditiously. (Paras 1-10) B) Constitutional Law - Article 226 - Mandamus - The court examined the maintainability of a writ petition seeking mandamus to permit construction in a mangrove buffer zone. The court held that mandamus could be issued to direct authorities to consider the application, but not to grant permission without due process. (Paras 1-10)
Issue of Consideration
Whether the Municipal Corporation of Greater Mumbai can be permitted to construct a suction tank for water supply within a 50-meter mangrove buffer zone, and whether the project requires prior clearance from the Coastal Regulation Zone authorities.
Final Decision
The court disposed of the petition directing the respondent authorities to consider the petitioner's application for permission to construct the suction tank within four weeks. The petitioner was restrained from carrying out any construction until permission is granted. The petition was disposed of with no order as to costs.
Law Points
- Environmental Law
- Coastal Regulation Zone
- Mangrove Buffer Zone
- Public Interest
- Water Supply
- Mandamus