High Court of Judicature at Bombay Hears Arbitration Petitions Challenging Arbitral Awards in Real Estate Development Dispute — Awards Dated 22-23 April 2022 in Favour of Claimants. Court considers whether awards passed under Arbitration and Conciliation Act, 1996 in relation to allotment and development of plots in Arrow City Manhattan Project are liable to be set aside, especially given arbitrator's adoption of findings from Claim No.5 across other claims.

High Court: Bombay High Court Bench: BOMBAY
  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The Bombay High Court heard a batch of connected arbitration petitions filed by Arrow Engineering Limited challenging arbitral awards passed in favour of various individual respondents who were original claimants in arbitration proceedings. The dispute concerned the Arrow City Manhattan Project, a residential development in Taluka Pen, District Raigad, where the respondents desired to purchase fully developed bungalow plots with amenities. The court noted that there were arguable issues raised by the petitioner and decided to hear and dispose of the petitions at the admission stage. The court also noted that the learned arbitrator in Claim No.5 had directed that his reasons and findings apply to all other references, and awards dated 22 April 2022 and 23 April 2022 were passed accordingly. The factual background shows that the respondents approached the petitioner for purchase of a plot, and allotment letter dated 15 October 2008 was issued for Plot No.EE-16 in Beta Sector Block-6 admeasuring 500 sq. yards. The petitioner obtained permission under Section 63(1)(a) of the Maharashtra Tenancy and Agriculture Lands Act for purchase of agricultural lands for the project. The respondents made payments, and an agreement dated 29 May 2009 was executed for an unidentified plot of 500 sq. yards at Rs.1,999 per sq. yard, total consideration Rs.9,99,500, with additional development charges. The respondents paid approximately 50% at execution, and later paid 10% for road construction, bringing their payment to about 60% of consideration. The project completion period with extended six months expired in November 2011. When no progress was made, the respondents sent letters and visited the office, but the petitioner cited delay due to CIDCO being appointed Special Planning Authority and awaiting master plan approval for NAINA. The respondents issued a notice dated 18 November 2015 calling upon the petitioner to perform the contract. The petitioner deposited Rs.3,29,950 on 26 November 2015 as refund, claiming delay due to change in law and government policies and that the transaction had become null and void. The respondents rejected the refund and invoked arbitration under Clause 43 on 5 December 2015. The petitioner contended that the agreement stood terminated due to the refund demand. The respondents filed an application under Section 9 of the Arbitration and Conciliation Act, 1996, and on 1 January 2016 the High Court recorded the petitioner's undertaking not to create third party interest or part with possession, which continued till disposal of arbitration. The Section 9 petition was later disposed of by consent on 21 July 2016, referring the dispute to a sole arbitrator. The respondents filed their Statement of Claim on 4 September 2016 seeking specific performance of the agreement or compensation in lieu thereof. The petitioner filed its Statement of Defence on 29 September 2016, and issues were framed on 5 December 2016. The learned arbitrator passed an award in favour of the respondents in Claim No.5 on 22 April 2022, and awards in the other nine references on 23 April 2022. The petitioner then filed the present arbitration petitions challenging these awards. The available text does not include the detailed arguments of the parties or the court's analysis and final decision, as the excerpt ends after the statement of facts. The court clubbed the petitions because they raised identical challenges, and the arbitrator had applied his findings from Claim No.5 across all references. The final holding and operative directions are not mentioned in the provided judgment text.

Headnote

A) Arbitration Law - Challenge to Arbitral Award - Admission Stage Disposal - Arbitration and Conciliation Act, 1996 - The High Court found arguable issues raised by petitioners and decided to hear and dispose of connected arbitration petitions at admission stage because identical challenges to arbitral awards dated 22 April 2022 and 23 April 2022 were raised. Held that common judgment should dispose of all petitions since reasons and findings on issues in Claim No.5 were applied to other references by the arbitrator. (Paras 1-2)

B) Contract Law - Specific Performance and Compensation - Development Agreement Allotment - Arbitration and Conciliation Act, 1996, Section 9 - The dispute arose from a development agreement dated 29 May 2009 for plot in Arrow City Manhattan Project; respondents/claimants sought specific performance or compensation due to petitioner's failure to complete project and hand over possession. The petitioner contended that project was delayed due to CIDCO notification and refunded amounts, claiming contract termination, while respondents invoked arbitration under Clause 43. Held that the factual chronology includes notices of default, refund attempt, and arbitration invocation leading to award in favour of claimants. (Para 3)

C) Arbitration Law - Interim Measures - Section 9 Arbitration and Conciliation Act, 1996 - The respondents filed Section 9 application, and on 1 January 2016 the High Court recorded petitioner's undertaking not to create third party interest or part with possession; the undertaking was continued till disposal of arbitration. Subsequently, by common order dated 21 July 2016, the Section 9 petition was disposed of by consent referring disputes to sole arbitrator. Held that interim protection was in place during arbitration proceedings. (Para 3)

D) Arbitration Law - Arbitral Award - Application of Findings Across Multiple References - Arbitration and Conciliation Act, 1996 - The arbitrator in Claim No.5 directed that reasons and findings apply to issues in each of the other nine references; awards dated 23 April 2022 were passed accordingly. Held that the common challenge in these petitions is based on the arbitrator's adoption of the Claim No.5 reasoning across all references. (Paras 1)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral awards dated 22 April 2022 and 23 April 2022 are liable to be set aside; whether the arbitrator's adoption of findings and reasons from Claim No.5 to other nine references is legally valid.

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Challenge to arbitral awards under Arbitration and Conciliation Act
  • 1996
  • Section 9 interim protection
  • application of findings in one claim to other identical references
Subscribe to unlock Law Points Subscribe Now

Case Details

2024 LawText (BOM) (02) 151

Arbitration Petition (L) No. 28284 of 2022 with Interim Application (L) No. 28294 of 2022 and connected petitions

2024-02-21

R.I. Chagla, J.

2024:BHC-OS:2734

Robin Jaisinghani, Jacinta D'silva, Abhinav Chandrachud, Saurish Shetye, Rohan Savant, Mukesh Gupta, Asmita Yadav

Arrow Engineering Limited

Punit Jitendra Chande & Anr., Chintan Tribhuvan Kapdi & Anr., Rasiklal Ranchhoddas Bhavsar & Anr., Sneha Muljibhai Patel, Ritesh Muljibhai Patel, Satish Amrutlal Shah & Anr., Vrajlata Chandrakant Shah & Anr., Dinesh Jhakshaniya, Ami Parag Mehta & Anr., Nikhil Amrutlal Rathod And Another

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration petitions challenging arbitral awards under the Arbitration and Conciliation Act, 1996 arising from a real estate development dispute regarding plot allotment and construction in Arrow City Manhattan Project.

Remedy Sought

Petitioner Arrow Engineering Limited sought setting aside of arbitral awards dated 22 April 2022 and 23 April 2022 passed in favour of respondents/claimants, and interim relief pending the petitions.

Filing Reason

Petitioner filed arbitration petitions challenging awards after arbitral tribunal decided claims in favour of respondents/claimants, including specific performance and compensation, and adopted findings from Claim No.5 across other references.

Previous Decisions

Arbitral Award dated 22 April 2022 in Claim No.5 and Awards dated 23 April 2022 in other nine references passed in favour of respondents/claimants; earlier, Section 9 order dated 1 January 2016 recorded petitioner's undertaking not to create third party interest; Section 9 petition disposed of by consent on 21 July 2016 appointing sole arbitrator; anticipatory bail application of Mr. Vineet Malhotra rejected on 12 August 2016.

Judgment Excerpts

This Court was of the opinion that there are arguable issues raised on behalf of the Petitioners in these Petitions and these Petitions can be heard and disposed of at the admission stage. The learned Arbitrator in the impugned Award in Claim No.5 has held that the reasons and findings on all the issues will apply to the issues in each of respective preferred references/claims before the learned Arbitrator. The Respondents who were the Original Claimants in the Arbitral Proceedings were desirous of purchasing a fully developed Bungalow to be constructed and developed by the Petitioner who was the Original Respondent in the Arbitral Proceedings with amenities such as Roads, Electricity, Switch, Drainage etc. for their own personal use under the Arrow City Manhattan Project.

Procedural History

Respondents/claimants approached Petitioner for purchase of developed plot; Allotment Letter dated 15 October 2008; payments made; Agreement dated 29 May 2009; project completion expired November 2011; notices exchanged in 2015; Petitioner deposited refund on 26 November 2015; Respondents invoked arbitration on 5 December 2015; Section 9 application filed, order dated 1 January 2016 recording undertaking; Section 9 petition disposed of on 21 July 2016 appointing sole arbitrator; Statement of Claim filed 4 September 2016; Statement of Defence filed 29 September 2016; issues framed 5 December 2016; arbitral awards passed on 22 April 2022 and 23 April 2022; present arbitration petitions filed thereafter.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
  • Maharashtra Tenancy and Agriculture Lands Act: Section 63(1)(a)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Writ Petitions Upholding Mandatory Nature of Separate Notices for No-Confidence Motion against Sarpanch and Up-Sarpanch. Common Notice under Rule 2(1) of Bombay Village Panchayats Sarpanch and Up-Sarpanch (No Confidence Mo...
Related Judgement
High Court High Court of Judicature at Bombay Hears Arbitration Petitions Challenging Arbitral Awards in Real Estate Development Dispute — Awards Dated 22-23 April 2022 in Favour of Claimants. Court considers whether awards passed under Arbitration and Concil...