High Court of Judicature at Bombay Adjudicated Commercial Arbitration Petition Under Section 34 of Arbitration and Conciliation Act, 1996; Final Verdict Not Stated in Provided Excerpt. Petition Raised Issues of Necessary Parties and Interpretation of Payment Obligations Under Supply Agreement and Multi-Party Agreement Clauses 5.4.2, C, and D.

High Court: Bombay High Court Bench: BOMBAY
  • 6
Judgement Image
Font size:
Print

Case Note & Summary

The judgment dealt with a Commercial Arbitration Petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 before the High Court of Judicature at Bombay, Commercial Division. The Petitioner, Shriram EPC Ltd., sought setting aside of an Award dated 5 February 2019 and an Order dated 3 September 2016 passed by the Sole Arbitrator. The Respondent, Parker-Hannifin India Pvt. Ltd., had partly succeeded in its claim before the Arbitrator. The underlying dispute arose from a Purchase Order dated 15 March 2012 for 480 hydraulic drives and 960 hydraulic cylinders, custom-made to the Petitioner's specifications, at a total contract price of INR 6,81,60,000. A Supply Agreement dated 26 March 2012 followed. Under its clauses, the Petitioner was required to pay a non-refundable advance of 10%, and before first delivery, procure a usance Letter of Credit from CIAL to cover the remaining 90%; failure to procure the Letter of Credit constituted default entitling termination. A Multi-Party Agreement was executed on 2 August 2012 between CIAL, APL, the Petitioner and the Respondent, though signed only by the latter two. It clarified payment mechanism, with CIAL to open an irrevocable inland letter of credit for 90% and the Petitioner to pay the balance directly. Clause C stated that Supply Agreement terms remained valid and enforceable inter se among the parties, and Clause D provided that the Supply Agreement would prevail in conflict. A Letter of Credit for the first lot was issued by APL on 4 August 2012 and accepted; the first lot was delivered without objection. For the second lot, the Respondent repeatedly sought a Letter of Credit, but it was not opened. Meetings took place, assurances were given, but the Petitioner did not take delivery of ready lots. The Respondent sent a demand letter on 22 August 2013 and eventually terminated the agreements on 23 December 2014. Arbitration was invoked on 16 June 2015 under Clause 26.7.3. On 9 September 2015, the High Court appointed a Sole Arbitrator under Section 11, noting no dispute about the arbitration clause. The Petitioner filed a Section 16 application challenging jurisdiction, arguing that CIAL and APL were necessary parties and that the MPA incorporated the arbitration clause among all four parties; the Sole Arbitrator dismissed it on 3 September 2016, holding that the Supply Agreement was not affected by the MPA and rejecting the stamp duty objection. In the final Award, the Sole Arbitrator partly allowed the Respondent's claims for manufactured lots, raw material, and spare parts, and rejected the Petitioner's counterclaim. In the Section 34 petition, the Petitioner argued that its liability was limited to the 10% advance, that the phrase "Purchaser shall procure" could not be read as making it liable for the entire amount, and that the MPA had omitted the procurement wording and maintained CIAL's obligation. The excerpt records only the Petitioner's submissions and does not include the Respondent's arguments or the Court's analysis and decision. The judgment was reserved on 19 December 2024 and pronounced on 4 August 2025, but the provided text ends mid-argument. Therefore, the final outcome, ratio decidendi, and directions are not available from the excerpt.

Headnote

A) Arbitration - Jurisdiction of Arbitral Tribunal - Necessity of joining parties to multi-party agreement - Arbitration and Conciliation Act, 1996, Sections 16, 11 - The Petitioner challenged jurisdiction contending that CIAL and APL were necessary parties because Clause C of the Multi-Party Agreement incorporated the Supply Agreement's terms and dispute resolution clause among all four parties. The Sole Arbitrator, after interpreting the relevant clauses, concluded that the Supply Agreement was not affected by the MPA and dismissed the Section 16 application. The provided excerpt does not state the High Court's final holding on this ground (Paras 2, 3, 6).

B) Contract - Payment Obligations - Interpretation of 'Purchaser shall procure' clause - Arbitration and Conciliation Act, 1996, Section 34; Supply Agreement Clause 5.4.2 - The Petitioner argued that its liability was confined to the 10% advance and that the obligation to open the Letter of Credit for the remaining 90% rested with CIAL, so reading 'Purchaser shall procure' as requiring direct payment would rewrite the contract. The Arbitrator partly allowed the Respondent's claim for the balance amount, but the excerpt does not contain the High Court's final determination on the interpretation (Paras 2, 3, 4, 5).

C) Arbitration - Stamp Duty Objection - Admission of document in Section 11 proceedings - Arbitration and Conciliation Act, 1996, Sections 11, 16 - The Petitioner raised absence of requisite stamp duty on the Supply Agreement; the Sole Arbitrator rejected the objection relying on the Section 11 Order and the document's admission by the Petitioner. The final treatment of this objection by the High Court is not stated in the excerpt (Para 2).

D) Contract - Multi-Party Agreement - Prevalence of Supply Agreement and incorporation of dispute resolution clause - Arbitration and Conciliation Act, 1996, Section 7 - Clause C of the MPA provided that Supply Agreement terms remain valid and enforceable inter se among the parties, and Clause D provided that the Supply Agreement prevails in case of conflict; the Petitioner relied on this to include CIAL and APL in arbitration. The Sole Arbitrator held that the Supply Agreement was not affected by the MPA. The excerpt ends before the High Court's final reasoning (Paras 2, 6).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether CIAL and APL were necessary parties to the arbitration because of the Multi-Party Agreement incorporating the Supply Agreement's terms and arbitration clause; whether the Petitioner's liability was limited to the 10% advance payment with the obligation to open the Letter of Credit resting on CIAL; whether the Sole Arbitrator correctly dismissed the Section 16 application and partly allowed the Respondent's claim; and whether the Award should be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Not mentioned in the provided excerpt; the judgment was reserved on 19 December 2024 and pronounced on 4 August 2025, but the operative decision is not included.

Law Points

  • Section 34 of Arbitration and Conciliation Act
  • 1996
  • Section 16 jurisdiction
  • Section 11 order
  • necessary parties
  • multi-party agreement incorporation
  • letter of credit obligation
  • purchaser shall procure interpretation
  • liquidated damages
  • stamp duty admission
  • waiver
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (BOM) (08) 42

Commercial Arbitration Petition No. 909 of 2019

2025-08-04

R.I. Chagla, J.

2025:BHC-OS:12656

Mr. Kevic Setalvad, Senior Counsel a/w Mrs. Rajalakshmy Mohandas, Mr. Amey Kulkarni, Ms. Mukta Chorge, Mr. Nehal Farukh Azam i/b Rajalakshmy Associates for the Petitioner; Mr. Zubin Behramkamdin, Senior Counsel a/w Vijay Purohit, Faizan Mithaiwala, Pratik Jhaveri, Niyari Bhogayta, Vinit Kamdar i/b P&A Law Officers for the Respondent

Shriram EPC Ltd.

Parker-Hannifin India Pvt. Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Commercial arbitration petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award dated 5 February 2019 and an order dated 3 September 2016 passed by the Sole Arbitrator under Section 16 of the Act.

Remedy Sought

The Petitioner sought setting aside of the Award dated 5 February 2019 and the Order dated 3 September 2016.

Filing Reason

The Petitioner was aggrieved by the arbitral award which partly allowed the Respondent's claims and rejected the Petitioner's counterclaim, and by the rejection of its Section 16 application challenging jurisdiction.

Previous Decisions

The Sole Arbitrator dismissed the Section 16 application on 3 September 2016 and passed the Award on 5 February 2019 partly allowing the Respondent's claims. The High Court appointed the Sole Arbitrator on 9 September 2015 under Section 11.

Issues

Whether CIAL and APL were necessary parties to the arbitration proceedings due to the Multi-Party Agreement incorporating the Supply Agreement's arbitration clause among all four parties? Whether the Petitioner's liability under the Supply Agreement was restricted to the 10% advance payment, with the obligation to open the Letter of Credit for the remaining 90% resting on CIAL? Whether the Sole Arbitrator rightly dismissed the Petitioner's Section 16 application challenging jurisdiction and stamp duty? Whether the Arbitral Award dated 5 February 2019 should be set aside under Section 34 of the Arbitration and Conciliation Act, 1996?

Submissions/Arguments

Petitioner submitted that CIAL and APL are necessary parties because Clause C of the MPA incorporated the Supply Agreement terms and dispute resolution clause among all four parties to the MPA. Petitioner argued that its obligation was only to pay the 10% advance, and the liability to open the Letter of Credit for the balance 90% vested with CIAL. Petitioner contended that the words 'Purchaser shall procure' in Clause 5.4.2 of the Supply Agreement cannot be read to mean that the Purchaser shall pay the entire amount in the event CIAL defaults, as that would amount to re-writing the contract. Petitioner also submitted that the MPA omitted the procurement wording and that CIAL's obligation to open the Letter of Credit remained with CIAL. Respondent had claimed recovery of the balance 90% amount from the Petitioner in addition to warehousing charges and liquidated damages.

Ratio Decidendi

Not mentioned in the provided excerpt; the text ends before the Court's analysis and final reasons.

Judgment Excerpts

By this Petition filed under Section 34 of the Arbitration and Conciliation Act, 1996, the Petitioner is impugning (i) Award dated 5th February 2019, passed by the learned Sole Arbitrator, rejecting the Petitioner’s contention and partly allowing the claim of the Respondent; and (ii) Order dated 3rd September 2016, passed by the learned Sole Arbitrator, rejecting the application filed by the Petitioner under Section 16 of the Arbitration Act. The learned Sole Arbitrator, after interpreting the relevant clauses of the Supply Agreement as well as the MPA, concluded that the Supply Agreement is not affected by the MPA and rejected the Petitioner’s contention that CIAL and APL are necessary parties to the arbitration proceedings. He has referred to the words “Purchaser shall procure” in Clause 5.4.2 of the Supply Agreement and has submitted that this cannot be read to mean that the Purchaser shall pay the entire amount in the event CIAL defaults in its obligation.

Procedural History

Purchase Order issued on 15 March 2012; Supply Agreement executed on 26 March 2012; Multi-Party Agreement executed on 2 August 2012; Letter of Credit for first lot issued by APL on 4 August 2012; emails exchanged from September 2012 regarding second lot letter of credit; meeting held on 4 October 2012; Respondent's demand letter dated 22 August 2013; termination letters dated 23 December 2014; arbitration notice dated 16 June 2015; Section 11 petition allowed on 9 September 2015 appointing Sole Arbitrator; Section 16 application dismissed on 3 September 2016; Award passed on 5 February 2019; Commercial Arbitration Petition No. 909 of 2019 filed; judgment reserved on 19 December 2024 and pronounced on 4 August 2025.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 11, Section 16, Section 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Judicature at Bombay Adjudicated Commercial Arbitration Petition Under Section 34 of Arbitration and Conciliation Act, 1996; Final Verdict Not Stated in Provided Excerpt. Petition Raised Issues of Necessary Parties and Interpretation of...
Related Judgement
High Court Bombay High Court Dismisses Interim Application Seeking Modification of Consent Order in Testamentary Proceedings. Court Holds That Once Consent to Equal Apportionment Was Recorded, Addition of 'By Making a Joint Application' Was Not Required Absent ...