Case Note & Summary
These appeals arose from a common judgment and order dated 28 April 2015 passed by a learned Single Judge of the Bombay High Court dismissing four arbitration petitions filed by Oil and Natural Gas Corporation Limited under Section 34 of the Arbitration and Conciliation Act, 1996. The petitions challenged a common arbitral award dated 9 October 2013 passed in favour of Jindal Drilling and Industries Limited. The underlying dispute concerned four independent contracts between ONGC and Jindal for drilling and related works. Jindal completed the works and submitted bills, which ONGC did not dispute but refused to pay on the ground that it had adjusted or exercised lien over an amount of Rs.63,87,38,070.76 kept as security to satisfy any award in a separate arbitration between ONGC and Discovery Enterprises Pvt. Ltd. Discovery was alleged to be a sister concern of Jindal, and ONGC sought to establish linkage through the group of companies doctrine. The arbitral tribunal allowed Jindal's claims. ONGC's Section 34 petitions were dismissed, leading to the present appeals. In the separate arbitration between ONGC and Discovery, ONGC had impleaded Jindal as a party. Jindal filed an application under Section 16 of the Act challenging jurisdiction, which the tribunal allowed on 27 October 2010. ONGC's appeal under Section 37 was dismissed by this Court on 27 June 2012. ONGC filed a Special Leave Petition before the Supreme Court. Meanwhile, the tribunal passed a final award on 6 June 2013 in favour of ONGC against Discovery, which Discovery did not challenge. In the present appeals, ONGC moved a transfer petition, and by order dated 1 September 2016, the Supreme Court transferred the appeals to itself and tagged them with the pending SLP/Civil Appeal. ONGC deposited the awarded amount of approximately Rs.160 crore, and Jindal was permitted to withdraw it on 6 January 2020 subject to bank guarantees. On 27 April 2022, the Supreme Court allowed ONGC's civil appeal, holding that the application for discovery and inspection of documents ought to have been decided by the arbitral tribunal before deciding the Section 16 application. It set aside the interim award and the High Court's Section 37 order, directed that Jindal's Section 16 application be decided afresh after deciding discovery and inspection, granted liberty to lead fresh evidence, and remanded the present appeals to this Court to be kept in abeyance until the Section 16 application was decided. The bank guarantees were to be kept alive. The reconstituted arbitral tribunal allowed discovery, received documents, and by order dated 3 April 2025 again allowed Jindal's Section 16 application, deleting Jindal from the array of parties in the ONGC-Discovery arbitration. The arbitration proceedings were terminated on 18 April 2025. In the present proceedings, ONGC argued that the appeals should remain in abeyance because it had challenged the order dated 3 April 2025 under Section 37, and that the parallel arbitration had a bearing on the appeals. ONGC contended that Discovery was a shell company with no assets and that the group of companies doctrine should link Jindal and Discovery. It relied on public funds and the subsistence of bank guarantees until January 2026. Jindal argued that the Supreme Court stay was only until the fresh Section 16 decision, which had now occurred, and that ONGC was seeking to rewrite the Supreme Court directions. Jindal asserted that ONGC had admitted liability under the four contracts and that the only defence of adjustment failed once linkage was not established. The extracted text ends before the final operative order; it records the submissions but does not include the court's final direction.
Headnote
A) Arbitration - Jurisdiction of Arbitral Tribunal - Section 16, Arbitration and Conciliation Act, 1996 - Non-signatory deletion - The Arbitral Tribunal, after considering discovery and fresh evidence, allowed Jindal's Section 16 application and directed deletion of Jindal from arbitration between ONGC and Discovery; the Supreme Court had earlier remanded the Section 16 application for fresh decision after deciding discovery, and the present appeals were kept in abeyance until that decision (Paras 8-10). B) Civil Procedure - Stay of Proceedings - Effect of Supreme Court remand directions - Arbitration and Conciliation Act, 1996, Sections 16 and 37 - ONGC contended that the stay on hearing of appeals should continue until its Section 37 appeal against the order dated 3 April 2025 is decided, while Jindal contended the stay ended once the Section 16 application was allowed; the court was called upon to determine whether hearing should proceed (Paras 10-12). C) Arbitration - Group of Companies Doctrine - Binding non-signatory - Arbitration and Conciliation Act, 1996, Section 16 - ONGC sought to link Jindal and Discovery through group of companies doctrine to recover awarded sums from Discovery; Jindal argued that linkage had not been established and that ONGC admitted liability under separate contracts, so its defence of adjustment failed (Paras 11-12).
Issue of Consideration
Whether hearing of the present appeals should be kept in abeyance until ONGC's appeal under Section 37 of the Arbitration and Conciliation Act, 1996 against the Arbitral Tribunal's order dated 3 April 2025 is decided, or whether the stay ordered by the Supreme Court ceased upon the Tribunal's fresh decision of Jindal's Section 16 application.
Law Points
- Section 34 challenge to arbitral award under Arbitration and Conciliation Act
- 1996
- Section 16 jurisdiction of arbitral tribunal to rule on its own jurisdiction
- non-signatory deletion from arbitration proceedings
- group of companies doctrine for binding non-signatories
- effect of Supreme Court remand and stay directions
- abeyance of appeals pending related proceedings
- bank guarantee security during arbitration appeals


