Bombay High Court Dismisses Appellant's Second Appeal in Contract Recovery Suit as Time-Barred Under Article 113 of Limitation Act. Right to sue accrued when contractor had knowledge of final bill and imposition of penalty and forfeiture of security deposit in 1967, and legal notice in 1975 did not extend limitation for recovery of Rs.33,650 against State under Indian Limitation Act, 1963.

High Court: Bombay High Court Bench: AURANGABAD In Favour of Prosecution
  • 4
Judgement Image
Font size:
Print

Case Note & Summary

This second appeal arose from a civil suit filed by a registered partnership firm, M/s. D. V. Save, through its partner, against the State of Maharashtra through the Collector, Parbhani. The dispute related to an earth-work and lining contract for Mile Nos. 26 and 27 under the Purna Project, awarded by the Executive Engineer, Irrigation and Power Department. The contractor sought declaration and recovery of Rs.33,650/- on account of forfeited security deposit, penalties, and work done under the final bill. The State defended on merits and also raised limitation, contending the cause of action arose in 1967. The trial court decreed the suit, but the first appellate court reversed and dismissed it as time-barred. The present second appeal was filed against that appellate decree. The contract was allotted pursuant to a work order dated 16.12.1964. Mile No.26 work was to be completed within one year and Mile No.27 within twenty-four months from that date. During execution in 1966-67, the State imposed penalties and took action under Clause 3(a) of the contract, forfeiting security deposit and withdrawing work. The final measurement was called on 12.04.1967 and closed on 26.04.1967; security deposit was forfeited on 27.04.1967. On 28.07.1967, the Executive Engineer informed the contractor that the final bill had been received and asked attendance by 31.07.1967, followed by another communication dated 09.09.1967. Although the contractor claimed he could not attend due to typhoid, his own evidence indicated he saw the final bill on 01.09.1967 but did not sign it because measurement books and other papers were not provided. The contractor did not raise any grievance or take proceedings until he served a legal notice on 17.06.1975 and then filed the suit on 29.08.1975. The core legal issue, argued by both sides and decided by the High Court, was whether the suit was barred by limitation under Article 113 of the Limitation Act, 1963. The appellant also sought to rely on the distinction between Articles 58 and 113 to argue that the right to sue accrued only after an unequivocal threat; the State argued mere correspondence could not extend limitation. The question of non-registration of the partnership under Section 69 of the Partnership Act formed part of the order admitting the appeal, but counsel restricted arguments to limitation only, so that issue was not decided. The appellant submitted that the contractor was never served with the final bill along with measurement books and other relevant papers; he had reason to believe bills were still in process. Cause of action arose only when the legal notice dated 17.06.1975 was not responded. Reliance was placed on Shakti Bhog Food Industries Ltd. v. Central Bank of India, Union of India v. West Coast Paper Mills Ltd., and Shyamkumar Lalaramji Jaiswal v. Dattatraya. Counsel emphasized the difference in language between Articles 58 and 113, arguing that under Article 113 the right to sue accrues only on clear or unequivocal threat to infringe the right. The respondent State contended that starting point of limitation remains unaffected by conduct or correspondence, and that mere letters to authorities do not extend limitation; the cause of action accrued in 1966-67 and could not be revived by a 1975 legal notice. The High Court considered Article 113, which provides three years from when the right to sue accrues. It noted that the contractor was aware of penalty and forfeiture in 1966-67, saw the final bill on 01.09.1967, and had been called to the office earlier. The court held that cause of action comes into existence when a right is infringed or threatened, and here the plaintiff knew of deductions and the final bill. There was no correspondence or grievance from 1967 until 1975. The court acknowledged the difference between Articles 58 and 113 but held that even a liberal construction showed the right to sue accrued on seeing the final bill or even earlier when penalty and forfeiture were communicated. It concluded the appellate court rightly held the suit barred. The second appeal was dismissed. The judgment and decree dated 24.04.1995 of the Additional District Judge, Parbhani, in Regular Civil Appeal No.10/1985 were affirmed. No costs were mentioned.

Headnote

A) Limitation - Computation of Limitation - Article 113 of the Limitation Act, 1963 - Right to sue accrues - In a suit for recovery of security deposit, penalty and work dues arising from a government contract, limitation begins when the contractor has knowledge of the final bill and of penalty and forfeiture; the plaintiff saw the final bill on 01.09.1967 and was aware of deductions, but filed suit only on 29.08.1975 beyond three years - Held that subsequent legal notice in 1975 could not revive the cause of action and the suit was barred by limitation (Paras 13-16).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the lower Appellate Court was justified in applying Article 113 of the Indian Limitation Act, 1963 and holding that the plaintiff's suit for recovery of Rs.33,650/- was barred by limitation, particularly when the plaintiff claimed that limitation commenced only upon issuance of a legal notice dated 17.06.1975.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Second Appeal No.482 of 1995 dismissed. The judgment and decree dated 24.04.1995 passed by Additional District Judge, Parbhani in Regular Civil Appeal No.10/1985, dismissing the plaintiff's suit as barred by limitation, was affirmed. No costs were awarded.

Law Points

  • Period of limitation under Article 113 of the Limitation Act
  • 1963 begins when the right to sue accrues
  • cause of action arises when a right is infringed or threatened to be infringed
  • mere issue of legal notice after limitation has begun does not extend or revive limitation
  • distinction between Article 58 and Article 113 does not assist a plaintiff who had knowledge of final bill and deductions
  • where contractor was aware of penalty
  • forfeiture of security deposit
  • and final bill by 1967
  • suit filed in 1975 is barred by three-year limitation
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (BOM) (07) 5

Second Appeal No. 482 of 1995

2025-07-17

S. G. Chapalgaonkar

2025:BHC-AUG:18951

S. S. Bora (Advocate for Appellant), V. S. Badakh (AGP for Respondent-State)

M/s. D. V. Save, a registered partnership firm, through its partner Shri Moreshwar Dinanath Save

The State of Maharashtra through the Collector, Parbhani

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil suit for declaration and recovery of Rs.33,650/- arising from a government earth-work and lining contract, involving forfeiture of security deposit, imposition of penalty, and withdrawal of work; appealed up to second appeal before Bombay High Court.

Remedy Sought

Appellant (original plaintiff) sought setting aside of appellate decree and restoration of trial court's decree for recovery of Rs.33,650/- with interest at 6% per annum and notice charges of Rs.125/-.

Filing Reason

State forfeited security deposit and imposed penalties, and despite preparation of final bill, amount claimed was not paid; after legal notice dated 17.06.1975 went uncomplied, suit was instituted on 29.08.1975.

Previous Decisions

Trial Court (Civil Judge Senior Division, Parbhani) in Regular Civil Suit No.27/1975 decreed suit on 12.01.1984 awarding Rs.33,650/- with 6% interest and notice charges Rs.125/-; Additional District Judge, Parbhani in Regular Civil Appeal No.10/1985 allowed State's appeal on 24.04.1995, dismissing suit as barred by limitation and also citing Section 69 Partnership Act.

Issues

Whether the plaintiff's suit for recovery of Rs.33,650/- was barred by limitation under Article 113 of the Limitation Act, 1963, considering that the plaintiff saw the final bill and was aware of penalty and forfeiture in 1967? Whether the distinction in language between Article 58 and Article 113 of the Limitation Act affects the starting point of limitation, and whether a subsequent legal notice can revive a time-barred cause of action?

Submissions/Arguments

Appellant: The contractor was never served with final bill and measurement books; he had reason to believe bills were in process; cause of action arose only when legal notice dated 17.06.1975 was not responded; reliance on Shakti Bhog Food Industries Ltd. v. Central Bank of India, AIR 2020 SC 2721; Union of India v. West Coast Paper Mills Ltd., AIR 2004 SC 1596; Shyamkumar Lalaramji Jaiswal v. Dattatraya, 2023 (1) Mh.L.J. 430; distinction between Articles 58 and 113 meant right to sue accrues only on clear or unequivocal threat. Respondent-State: Starting point of limitation remains unaffected by conduct or correspondence; mere attempts by litigant to persuade authorities by letters cannot extend limitation; cause of action accrued in 1966-67 when penalty imposed and security deposit forfeited; legal notice in 1975 cannot revive cause of action; suit barred by limitation.

Ratio Decidendi

Under Article 113 of the Limitation Act, 1963, limitation begins when the right to sue accrues, i.e., when the right is infringed or threatened. Knowledge of the final bill and of penalty and forfeiture of security deposit starts limitation; subsequent correspondence or legal notice cannot extend or revive limitation. Even if Article 58 uses different language, liberal interpretation of Article 113 shows the right to sue accrued on the date the contractor saw the final bill, and a suit filed beyond three years is barred.

Judgment Excerpts

Plain reading of aforesaid provision depicts that limitation period shall begin to run when right to sue accrues. Although it cannot be disputed that there is difference in starting point of limitation period in Article 58 and 113 of the Limitation Act and language is not comparable to each other, even giving liberal construction to language incorporated in Article 113 of Limitation Act, right to sue accrued to plaintiff when he has seen final bill or even prior to that action of imposing penalty and forfeiture of security deposit was taken against him and communicated to him.

Procedural History

Original suit filed on 29.08.1975 as Regular Civil Suit No.27/1975 before Civil Judge Senior Division, Parbhani. Trial Court decreed suit on 12.01.1984. State filed Regular Civil Appeal No.10/1985 before District Judge, Parbhani; Additional District Judge allowed appeal on 24.04.1995, reversing trial decree and dismissing suit as barred by limitation and under Section 69 Partnership Act. Appellant filed Second Appeal No.482 of 1995; appeal admitted on 26.02.1996 on substantial questions of law about limitation and non-registration of partnership. At hearing, counsel restricted arguments to limitation only. High Court dismissed second appeal on 17.07.2025.

Acts & Sections

  • Indian Limitation Act, 1963: Article 113, Article 58
  • Indian Partnership Act, 1932: Section 69
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Appellant's Second Appeal in Contract Recovery Suit as Time-Barred Under Article 113 of Limitation Act. Right to sue accrued when contractor had knowledge of final bill and imposition of penalty and forfeiture of security ...
Related Judgement
High Court High Court of Bombay at Goa Partly Allows Claimants' Appeal in Motor Accident Compensation Case, Reducing Contributory Negligence from 50% to 25%. The Court Held That Truck Driver's High Speed and Failure to Testify Warranted Adverse Inference, While...