Case Note & Summary
The Bombay High Court heard an appeal from an order refusing temporary injunction in a suit challenging a demolition notice issued by the Municipal Corporation of Greater Mumbai under Section 354A of the Mumbai Municipal Corporation Act, 1888. The appellants, who claimed lawful occupation of structures on the sixth and seventh floors of a building, alleged that the structures existed since before 1958 and that only tenable repairs were carried out. The corporation issued notice dated 21 October 2020 alleging unauthorised reconstruction of the building without permission. The trial court dismissed the injunction application by order dated 23 August 2024 on the ground that demolition work had already been carried out above the fifth floor. The appellants contended that the notice was never served on them, that Section 354A requires service on the affected person, and that the word 'person' should be read harmoniously with definitions of owner and occupier. They further submitted that the notice lacked an exact description of the alleged unauthorised work and was contradicted by a speaking order dated 15 March 2022 which recorded that the building up to the fifth floor was authorised. The appellants argued that Section 354A can only be invoked for ongoing unlawful construction, and if the construction is complete, Section 351 applies. They relied on various judicial precedents on service of notice and natural justice. The High Court heard further arguments after noticing that the appeal was originally argued on an unamended Section 354A, which was amended in 2012 to replace 'Commissioner' with 'Designated Officer'. The final operative decision was not included in the provided text, but the judgment was pronounced on 9 June 2025.
Headnote
A) Municipal Law - Demolition Notice - Service of Notice - Mumbai Municipal Corporation Act, 1888, Sections 354A, 3(m), 3(n), 484, 485 - The appellants contended that the suit notice was never served on them, and the word 'person' in Section 354A must be read harmoniously with definitions of owner and occupier to require service on all affected persons before the drastic action of demolition within 24 hours. The court considered the argument in the context of precedents on service and natural justice (Paras 4, 4(b), 4(c), 4(f), 4(g)). B) Municipal Law - Demolition Notice - Specific Description of Unauthorised Work - Mumbai Municipal Corporation Act, 1888, Section 354A(1) - The appellants argued that the notice must contain an exact description of the alleged unauthorised work, and the vague allegation of unlawful reconstruction was contradicted by the speaking order which recorded that the building up to the fifth floor was authorised (Paras 4(a), 4(e)). C) Municipal Law - Demolition Notice - Invocation Only for Ongoing Work - Mumbai Municipal Corporation Act, 1888, Sections 354A, 351 - The appellants submitted that Section 354A is intended for ongoing unlawful construction; if immediate action is not taken and construction is complete, the corporation must proceed under Section 351, not continue under Section 354A (Paras 4(d)). D) Municipal Law - Demolition Notice - Satisfaction of Designated Officer - Mumbai Municipal Corporation Act, 1888, Sections 354A(1), 342 - The notice was issued without recording satisfaction that erection or work described in Section 342 was unlawfully commenced or carried out, rendering the action prima facie illegal (Paras 4(d), 4(i)).
Issue of Consideration
Whether the notice under Section 354A of the Mumbai Municipal Corporation Act, 1888 was validly issued and served; whether the temporary injunction should have been granted despite demolition already carried out above the fifth floor.
Final Decision
The final operative decision is not included in the provided text; the High Court heard further arguments and pronounced judgment on 9 June 2025.
Law Points
- Service of notice under Section 354A must be given to affected person
- Section 354A(1) requires satisfaction of designated officer that unlawful work is ongoing
- Notice must contain exact description of unauthorised work
- Section 354A cannot be invoked for completed construction
- Section 351 applies when construction is complete
- Harmonious reading of 'person'
- 'owner'
- 'occupier' required for service under Sections 3
- 484
- 485
- Natural justice requires prior notice before demolition



