Bombay High Court Admitted Arbitration Appeals in Land Acquisition Compensation Dispute Under National Highways Act, 1956. The appeals involved challenge to a common order that set aside an additional arbitral award enhancing compensation to Rs.650 per sq.mtr with 10% statutory easement rights under Section 33(4) of the Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: NAGPUR
  • 5
Judgement Image
Font size:
Print

Case Note & Summary

These ten arbitration appeals arose from land acquisition compensation disputes under the National Highways Act, 1956. The appellants were landowners whose lands in village Babhulkhed, Taluka Balapur, District Akola were compulsorily acquired for widening of National Highway No.6. The Ministry of Road Transport and Highways issued a notification under Section 3-A of the National Highways Act on 25.11.2011, followed by a final notification under Section 3-D on 30.10.2012. The Competent Authority cum Special Land Acquisition Officer passed an award under Section 3-G(1) on 30.03.2013, awarding compensation of Rs.1,18,872 for land bearing Gat No.7 admeasuring 1300 sq.mtr for the lead appellant. Aggrieved, the appellant sought enhancement under Section 3-G(5) before the arbitrator, who passed a primary award on 03.08.2019 partly allowing some claims and rejecting others without reasons. The appellant then filed an application under Section 33(4) read with Section 33(1) of the Arbitration and Conciliation Act, 1996 for an additional award on omitted claims. The arbitrator allowed that application and passed an additional award on 27.11.2020, enhancing compensation to Rs.650 per sq.mtr based on ready reckoner for lands on highway, plus 10% statutory easement rights. Both the appellant and the National Highway Authority of India filed applications under Section 34 of the Arbitration and Conciliation Act before the Principal District Judge, Akola. The NHAI sought to set aside only the additional award, while the appellant challenged the primary award and sought resumption of arbitral proceedings. By common order dated 21.03.2023, the Principal District Judge allowed the NHAI's application, set aside the additional award, and dismissed the appellant's application. The appellants filed the present arbitration appeals. Their main contentions were that the NHAI had mounted a partial challenge to the arbitral award, which is impermissible under Section 34; that the doctrine of merger applied to the additional award; that the primary award remained intact after setting aside the additional award, leaving them without remedy; and that the arbitrator had sufficient material, including ready reckoner, to enhance compensation. The respondent NHAI supported the Principal District Judge's order and argued that the arbitrator was not justified in passing the additional award. The High Court admitted the appeals and heard them finally, after recording that all appeals involved a similar issue. The provided judgment text ends before the court's analysis and final decision; therefore, the final holding and ratio are not included. The appeals were reserved for judgment on 05.03.2025 and pronounced on 16.04.2025.

Headnote

A) Arbitration Law - Additional Arbitral Award - Section 33(4) of Arbitration and Conciliation Act, 1996 - The appellant filed an application under Section 33(4) read with Section 33(1) seeking an additional award for claims omitted in the primary award dated 03.08.2019; the arbitrator allowed the application and passed an additional award on 27.11.2020 granting compensation of Rs.650 per sq.mtr based on ready reckoner of lands on highway along with 10% statutory easement rights; the Principal District Judge later set aside the additional award on the ground that the arbitrator was not justified in passing it (Paras 6-9).

B) Arbitration Law - Setting Aside of Arbitral Award - Section 34 of Arbitration and Conciliation Act, 1996 - The appellant contended that the NHAI had challenged only the additional award, not the primary award, and that a partial challenge to an arbitral award cannot be permitted under Section 34; the appellant relied on the doctrine of merger, arguing that after passing of additional award, it merged with the primary award and if the additional award was bad in law, the entire award should be set aside leaving parties free to begin arbitration again under Section 3-G(5) of the National Highways Act, 1956 (Paras 8-9).

C) Land Acquisition Law - Compensation Determination - Sections 3-A, 3-D, 3-G(1), 3-G(5) of National Highways Act, 1956 - Land bearing Gat No.7, admeasuring 1300 sq.mtr at village Babhulkhed, Taluka Balapur, District Akola was acquired for widening of National Highway No.6; the competent authority awarded Rs.1,18,872 on 30.03.2013; the appellant sought enhancement before the arbitrator, who partly allowed the claim in the primary award and later enhanced compensation to Rs.650 per sq.mtr in the additional award; the appeals challenged the setting aside of the enhanced compensation (Paras 4-9).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether partial challenge to an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996 is permissible; Whether an additional award passed under Section 33(4) merges with the primary award and should be set aside along with the primary award; Whether the arbitrator had material to enhance compensation to Rs.650 per sq.mtr; Whether the Principal District Judge erred in setting aside the additional award while leaving the primary award intact

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Doctrine of merger applies to additional award under Section 33(4) of Arbitration and Conciliation Act
  • 1996
  • partial challenge to arbitral award under Section 34 is impermissible
  • arbitrator must have material to enhance compensation
  • if additional award is set aside
  • entire award should be set aside
  • Section 3-G(5) of National Highways Act
  • 1956 provides arbitration for compensation determination
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (BOM) (04) 190

Arbitration Appeal No. 08 of 2024 with Arbitration Appeal Nos. 13 of 2024, 14 of 2024, 20 of 2024, 22 of 2024, 23 of 2024, 29 of 2024, 32 of 2024, 37 of 2024, 09 of 2024

2025-04-16

Smt. M.S. Jawalkar, J.

2025:BHC-NAG:4098

Mr. Ranjeet Singh Gahilot, Advocate for Appellants; Mr. S. C. Joshi, Assistant Government Pleader for Respondent/State; Mr. Anish A. Kathane, Advocate for Respondent No.2

Nursahar Shakil Ahmed Through Power of Attorney Holder Shakil Ahmad Khan Gulam Mohammad Khan; Sajid Iqbal Shekh Mehmood and Ors.; Abdul Sagir Abdul Zaheer; Ismail Abedali Najmi; Ashok Vishnudas Dharamthok; Murlidhar Pralhad Raut; Arshiya Nusrat Khalil Ahmed; Mohommad Zafar Mohhomad Kasam; Aashiya Nusrat Khalid Ahmed; Javed Ahmed Shekh Mahmood

Competent Authority (Land Acquisition) National Highway No.6 and Special Land Acquisition Officer, Balapur, Dist. Akola; Project Director, National Highway Authority of India, Project Implementation Unit-Amaravati

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration appeals arising from order passed under Section 34 of Arbitration and Conciliation Act, 1996 relating to land acquisition compensation under National Highways Act, 1956

Remedy Sought

Appellants sought to set aside the common order dated 21.03.2023 passed by Principal District Judge, Akola, which allowed NHAI's Section 34 application to set aside additional award and dismissed appellants' Section 34 application; sought restoration of additional compensation of Rs.650 per sq.mtr with 10% statutory easement rights

Filing Reason

Principal District Judge set aside the additional arbitral award dated 27.11.2020 that enhanced compensation, and dismissed appellants' challenge to the primary award; appellants contended that partial challenge to award and separate quashing of additional award was impermissible under Section 34 and doctrine of merger

Previous Decisions

Arbitrator passed primary award on 03.08.2019 partly allowing claims; Additional Award passed on 27.11.2020 under Section 33(4) enhancing compensation to Rs.650/sq.mtr with 10% easement rights; Principal District Judge, Akola by common order dated 21.03.2023 allowed NHAI's Section 34 application and set aside additional award, and dismissed appellants' Section 34 application

Issues

Whether partial challenge to an arbitral award under Section 34 of Arbitration and Conciliation Act, 1996 is permissible Whether an additional award passed under Section 33(4) merges with the primary award and should be set aside along with the primary award Whether the arbitrator had material to enhance compensation to Rs.650 per sq.mtr Whether the Principal District Judge erred in setting aside the additional award while leaving the primary award intact

Submissions/Arguments

Appellant contended that NHAI challenged only the additional award, not the primary award, and that partial challenge to arbitration award cannot be permitted under Section 34; doctrine of merger applies; if additional award bad in law, entire award should be quashed leaving parties free to begin arbitration again; arbitrator had sufficient material from ready reckoner to award Rs.650 per sq.mtr; relied on Vinod Sahebrao Pingle and Mcdermott International Inc. Respondent NHAI supported the order passed by the Principal District Judge, Akola. Appellant argued that due to quashing of additional award, arbitration proceedings cannot be resumed and additional compensation was taken away.

Judgment Excerpts

ADMIT. Heard finally with the consent of the learned Counsel appearing for the parties. As all the Appeals are involving a similar issue, they are taken up together for decision. NHAI had challenged only the Additional Award dated 27.11.2020 and the Primary Award dated 03.08.2019 is still in place. partial challenge to the arbitration award cannot be permitted under Section 34 of the A & C Act.

Procedural History

Ministry of Road Transport and Highways published notification dated 25.11.2011 under Section 3-A of National Highways Act, 1956; final notification under Section 3-D on 30.10.2012; award under Section 3-G(1) on 30.03.2013 awarding Rs.1,18,872; appellant challenged under Section 3-G(5); arbitrator passed primary award on 03.08.2019 partly allowing claims; appellant filed application under Section 33(4) read with 33(1) for additional award; additional award passed on 27.11.2020 granting Rs.650/sq.mtr with 10% statutory easement rights; appellant filed Civil Misc Application No.82/2021 under Section 34, NHAI filed Civil Misc Application No.75/2022 under Section 34; Principal District Judge passed common order on 21.03.2023 allowing NHAI's application and dismissing appellant's; appeals filed before High Court; admitted and heard finally on 05.03.2025 reserved, pronounced 16.04.2025.

Acts & Sections

  • National Highways Act, 1956: 3-A, 3-D, 3-G(1), 3-G(5)
  • Arbitration and Conciliation Act, 1996: 33(1), 33(4), 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Karnataka Grants Anticipatory Bail to Accused in Rape Case Based on Promise of Marriage — Petitioner Directly Approached High Court Without Exhausting Remedy Before Sessions Court Under Section 482 BNSS. Court Held That While Direct A...
Related Judgement
Supreme Court Supreme Court Upholds State Employer's Stand in Service Recruitment Matter; Reserved Category Candidates Who Availed Age and Physical Relaxations Cannot Be Migrated to Unreserved Vacancies. Standing Order No. 85 Para 14(f) Prevails Over Standing Orde...