Case Note & Summary
The dispute arose from a redevelopment project of a co-operative housing society in Mumbai. Ambit Urbanspace, a developer, entered into a Development Agreement dated May 21, 2024 with Poddar Apartment Co-operative Housing Society Limited to redevelop the society's building. The developer filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim protective measures pending arbitration. The relief sought was essentially eviction of tenants occupying five enclosed garages located within the same plot but as separate structures. These garages were originally retained by the vendor, late Sushilabai Makhanlal Poddar, when she conveyed the property to the society by a Deed of Conveyance dated May 12, 1972. The garages were tenanted to Respondents Nos.5 to 8, and Respondent No.9 was alleged to be an illegal occupant. The landlords, Respondents Nos.2 to 4, were the executors of the vendor's estate and supported the developer's petition. The tenants were not members of the society and were not signatories to the Development Agreement or the Supplemental Development Agreement dated October 21, 2024. The agreements purported to include the tenants as parties in the title clause but had no signature placeholders for them. The tenants contended they were not consulted about the redevelopment and were unaware of its terms. The core legal issues were whether the Section 9 court could grant interim measures against third parties who were not parties to the arbitration agreement, and whether there was any dispute between the parties to the arbitration agreement that needed securing. The developer argued that the Development Agreement required the tenants to vacate the garages and accept open parking spaces, and relied on the agreement's provisions. The landlords argued that the tenants' use of the garages was unauthorised and that they deserved only open parking spaces; mere silence did not constitute acquiescence. The tenants argued they were statutory protectees under the Maharashtra Rent Control Act, 1999 and that the landlords had charged commercial rent, including municipal assessment tax, indicating that commercial use was accepted. The court analysed the scope of Section 9, noting that interim measures may be sought only by a party to an arbitration agreement to preserve the subject-matter of the arbitration. Although third parties whose interests are affected can be joined to such proceedings to be heard, substantive relief cannot be granted against a third party who is not bound by the arbitration agreement. The court observed that the tenants had no privity to the Development Agreement and consequently no privity to the arbitration agreement. It further noted that the parties to the arbitration agreement—the developer, society, and landlords—had no inter-se dispute among themselves; all three supported each other and none had invoked arbitration against another. Therefore, there was no subject-matter of the arbitration to secure. The court suggested that the parties consider arbitrating with the tenants to balance equities, but the suggestion was rejected. The landlords also refused proposals to earmark units in the redeveloped building to secure the tenants' interests. The court concluded, based on the analysis available in the provided excerpt, that the Section 9 petition could not be maintained against the non-signatory tenants when there was no live dispute among the parties to the arbitration agreement. The excerpt ended before the final operative order, but the court's reasoning indicated that the petition would be dismissed or relief denied.
Headnote
A) Arbitration - Interim Measures - Section 9, Arbitration and Conciliation Act, 1996 - Jurisdiction can be exercised against third parties whose interests are affected, but only to balance equities when there is a live dispute between parties to the arbitration agreement. In this case, the parties to the arbitration agreement (Developer, Society, Landlords) had no inter-se dispute, and the Tenants were not parties, so there was no subject-matter to secure. The Court observed that interim measures under Section 9 could not be granted against non-signatory tenants in such circumstances. Held that the Section 9 petition lacked maintainability due to absence of privity and absence of inter-se dispute (Paras 7-12). B) Arbitration - Privity of Contract - Non-signatory tenants not bound by arbitration agreement - Section 9, Arbitration and Conciliation Act, 1996 - The Tenants had no privity to the Development Agreement and therefore no privity to the arbitration agreement. The Development Agreement purported to include the Tenants as parties in the title clause but had no signature placeholders for them, and the Supplemental Development Agreement did not even depict them as parties. Submissions based on the Development Agreement's requirements for the Tenants were undermined. Held that the Tenants could not be subjected to interim measures under an agreement they never executed (Paras 7-8). C) Landlord-Tenant - Maharashtra Rent Control Act, 1999 - Statutory protection of tenants - Maharashtra Rent Control Act, 1999 - The Tenants were statutory protectees under the Rent Act. The Landlords asserted that the only permitted use of the Subject Garages was to park identified cars and that current usage was unauthorised, but they had not taken any eviction proceedings for decades. The Tenants contended that the Landlords had charged rent as commercial premises, including additional municipal assessment tax. Held that the Developer could not seek eviction of statutory tenants through a Section 9 petition based on a Development Agreement to which the tenants were not signatories (Paras 15-16). D) Equitable Remedies - Conduct of Parties - Court's discretion to impose conditions - Section 9, Arbitration and Conciliation Act, 1996 - The Court suggested that the Landlords could earmark specific units in the redeveloped premises to secure competing interests pending resolution, but the Landlords firmly rebuffed this proposal. The suggestion to proceed to arbitration with the Tenants was also spurned. Held that the Court had discretion to impose equitable terms and conditions, but the parties' refusal to accept reasonable proposals necessitated a decision based on legal principles rather than negotiated equities (Paras 13-14).
Issue of Consideration
Whether a Section 9 petition under the Arbitration and Conciliation Act, 1996 can be maintained against tenants who are not parties to the arbitration agreement, where there is no dispute among the parties to the arbitration agreement, and whether such tenants can be evicted or dispossessed pending arbitration.
Law Points
- Section 9 interim measures may be granted only to a party to an arbitration agreement
- third parties can be joined but cannot be subjected to substantive relief without privity
- absence of inter-se dispute among arbitration agreement parties negates subject-matter to secure
- non-signatory tenants are not bound by arbitration agreement
- statutory tenants under Maharashtra Rent Control Act cannot be evicted by developer without landlord's proceedings
- court may impose equitable conditions but parties cannot claim absolute relief



