High Court of Judicature at Bombay Heard Appeal by Co-operative Housing Society Against Interim Injunction Restraining Termination of Developer in Redevelopment Dispute. Appeal Challenged Single Judge Order That Stayed Termination Letter and Barred Third-Party Rights Pending Suit for Specific Performance.

High Court: Bombay High Court Bench: BOMBAY
  • 6
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from the redevelopment of a co-operative housing society's property at Kher Nagar, Bandra (East), Mumbai. Maharashtra Housing and Area Development Authority (MHADA) owned land admeasuring 1066.94 sq.mtrs along with a G+2 building. By a lease deed and sale deed both dated 4 January 2016, MHADA transferred the land and building respectively to Kher Nagar Sai Prasad Co-operative Housing Society Ltd., the appellant society. Pittie Antariksh GRL Pvt. Ltd., the respondent developer, was involved after the society floated a tender on 29 March 2021. The developer was provisionally selected in a Special General Body Meeting on 31 July 2021. A comfort letter dated 7 August 2021 stated that final selection and appointment would follow compliance with Section 79A of the Maharashtra Co-operative Societies Act, 1960. The parties exchanged revised offers and counter-offers through emails and letters in August and October 2021, culminating in an offer letter dated 23 October 2021 providing additional area of 528 sq.ft. MOFA carpet area and Rs.17,51,000 as lumpsum hardship allowance per member. The society's Special General Body Meeting held on 24 October 2021 approved the developer by more than 75% majority, and the society confirmed the appointment by letter dated 31 October 2021 as per the offer letters dated 30 August 2021 and 23 October 2021. Subsequently, draft development agreements were exchanged, but disputes arose over terms such as time being the essence, completion period, termination clause, and additional area. The developer by email dated 13 January 2023 stated that the society's proposed additional total area of 578 usable carpet area was not acceptable, and the society on 27 January 2023 alleged that there was no concluded contract and negotiations were ongoing. The developer asserted in a letter dated 9 February 2023 that a concluded contract existed and that substantial work had been undertaken. The society issued a termination letter dated 24 May 2023, terminating the developer citing alleged delay. The developer responded on 12 June 2023 and 21 June 2023, contending the termination was unlawful. The society then issued a public notice inviting fresh tenders. The developer filed Commercial Suit (L) No. 27651 of 2023 on 25 September 2023 seeking a declaration of a valid, binding contract, specific performance, declaration that the termination letter was illegal, and mandatory injunction. In the interim application, the developer sought an injunction restraining the society from entering into any agreement or appointing another developer and a stay of the termination letter. The learned Single Judge by order dated 1 February 2024 allowed the interim application in terms of those prayers. The society, aggrieved by that interim order, filed the present Commercial Appeal (L) No. 9061 of 2024 under Section 13 of the Commercial Courts Act, 2015. The core legal issues were whether there was a concluded and binding contract between the parties, whether the termination letter was valid, whether the appointment complied with Section 79A of the Maharashtra Co-operative Societies Act, 1960, and whether the interim injunction was justified. The available judgment excerpt does not include the detailed arguments of counsel or the court's final analysis and operative directions; it ends abruptly before the reasoning and decision of the Division Bench. Thus, the final outcome of the appeal cannot be determined from the provided text.

Headnote

A) Commercial Appeal - Maintainability - Section 13 Commercial Courts Act, 2015 - The appeal was filed under Section 13 against an interim order allowing an interim application in a commercial suit - The order granted injunction restraining the society from appointing another developer and stayed the termination letter - The court's reasoning and final directions are not mentioned in the provided excerpt (Paras 1-2)

B) Contract Law - Formation of Contract - Specific Performance - The developer claimed a valid binding contract recorded in letters dated 30 August 2021 and 23 October 2021, while the society alleged no concluded contract as negotiations continued - The correspondence showed revised offers and counter-offers; the society ultimately terminated the developer citing delay - The court's analysis on whether a concluded contract existed is not available (Paras 3-8)

C) Co-operative Societies - Redevelopment - Section 79A Maharashtra Co-operative Societies Act, 1960 - Appointment of developer by society requires compliance with Section 79A - A comfort letter stated final selection and appointment would be done after complying with the procedure under Section 79A; the Special General Body Meeting on 24 October 2021 approved the developer by more than 75% majority - The legal effect of this compliance was a key issue (Paras 3-5)

D) Interim Injunction - Termination of Developer - Letter dated 24 May 2023 - The developer sought stay of the termination letter and restraint on third-party rights; the Single Judge allowed the interim application - The appeal challenged that order, but the final reasoning and decision are not included in the available text (Paras 1, 8)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the learned Single Judge was justified in granting interim injunction restraining the society from terminating the developer and creating third-party rights pending the suit for specific performance; whether there was a valid, binding and subsisting contract between the society and developer as recorded in letters dated 30 August 2021 and 23 October 2021; whether the termination letter dated 24 May 2023 was lawful; whether the appointment of the developer complied with Section 79A of the Maharashtra Co-operative Societies Act, 1960

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Not mentioned in the provided excerpt. The impugned order of the Single Judge dated 1 February 2024 allowed the interim application, but the final disposition of the present appeal is not included in the truncated judgment text.

Law Points

  • Legal points not extracted
  • Section 13 of the Commercial Courts Act
  • 2015 provides an appeal against interim orders passed by a Commercial Court
  • Section 79A of the Maharashtra Co-operative Societies Act
  • 1960 requires compliance before final appointment of a developer by a co-operative housing society
  • an interim injunction may be granted to preserve the subject matter of a suit for specific performance
  • a valid binding contract requires offer and acceptance without ongoing negotiations
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (BOM) (04) 57

Commercial Appeal (L) No. 9061 of 2024 in Interim Application (L) No. 27970 of 2023 in Commercial Suit (L) No. 27651 of 2023

2025-04-25

Alok Aradhe, CJ, M. S. Karnik, J

Citation not available, 2025:BHC-OS:7030

Zal Andhyarujina, Nishant Shashidharan, Shrey Sancheti, Paluck Bengali, Shreyas Moharir, Ashraf Diamondwala, Sharan Jagtiani, Karl Tamboly, Pooja Kane, Shradha Achliya, Bharat Jain, Anant Ratnaparkhi, Kavish Arora, IC Legal

Kher Nagar Sai Prasad C.H.S. Building No.2, M.H.B. Colony, Kher Nagar, Bandra (East), Mumbai 400051

Pittie Antariksh GRL Pvt. Ltd., 5th Floor, Dheeraj Plaza, 23 Hill Road, Bandra (West), Mumbai-400050

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Commercial appeal under Section 13 of the Commercial Courts Act, 2015 challenging an interim order granting injunction in a commercial suit for specific performance of a redevelopment contract.

Remedy Sought

The appellant society sought to set aside the Single Judge's order dated 1 February 2024 which allowed the interim application and granted injunction restraining the society from entering into any agreement or appointing another developer and staying the termination letter dated 24 May 2023.

Filing Reason

The society terminated the developer vide letter dated 24 May 2023 alleging delay; the developer filed a commercial suit for declaration of valid binding contract, specific performance, and injunction; the Single Judge granted interim relief; aggrieved, the society filed the present appeal.

Previous Decisions

The learned Single Judge of the Bombay High Court by order dated 1 February 2024 allowed the Interim Application (L) No. 27970 of 2023 in Commercial Suit (L) No. 27651 of 2023 and made it absolute in terms of prayer clauses (a) and (b).

Issues

Whether the learned Single Judge erred in granting interim injunction restraining the society from terminating the developer and creating third-party rights pending the suit for specific performance. Whether there was a valid, binding and subsisting contract between the society and developer as recorded in letters dated 30 August 2021 and 23 October 2021. Whether the termination letter dated 24 May 2023 issued by the society was illegal and contrary to law. Whether the appointment of the developer complied with Section 79A of the Maharashtra Co-operative Societies Act, 1960.

Submissions/Arguments

The developer contended that there was a concluded contract between the parties based on the letters dated 30 August 2021 and 23 October 2021 and that substantial work had been undertaken; the termination was unlawful and illegal. The society contended that there was no concluded contract as negotiations were ongoing; it alleged delay by the developer in forwarding revised terms and thus terminated the appointment. The society relied on the comfort letter stating that final selection and appointment would be done after complying with Section 79A of the Maharashtra Co-operative Societies Act, 1960.

Ratio Decidendi

Not mentioned in the provided excerpt.

Judgment Excerpts

The challenge in this Commercial Appeal under Section 13 of the Commercial Courts Act is to the judgment and order dated 1st February 2024 passed by the learned Single Judge of this Court in the Interim Application seeking reliefs in terms of prayer clauses (a) and (b) during the pendency of the Commercial Suit filed by the Respondent/original plaintiff – Pittie Antariksh GRL Pvt. Ltd. A comfort letter dated 7th August 2021 was issued to the developer by the society inter alia stating that the final selection and appointment of the plaintiff as a developer shall be done after complying with the procedure laid down under Section 79A of the Maharashtra Co-operative Societies Act, 1960. The society addressed a letter dated 24th May 2023 (Termination Letter) to the developer terminating the plaintiff as its developer inter alia on account of alleged delay by the developer in forwarding the revised terms of redevelopment to the society.

Procedural History

On 29 March 2021, the society floated a tender for redevelopment. In the Special General Body Meeting held on 31 July 2021, the respondent developer was provisionally selected. After revised offers, the society appointed the developer in the Special General Body Meeting held on 24 October 2021 by more than 75% majority. The society issued a termination letter dated 24 May 2023. The developer filed Commercial Suit (L) No. 27651 of 2023 on 25 September 2023 and sought interim reliefs. The Single Judge allowed the Interim Application (L) No. 27970 of 2023 on 1 February 2024. Aggrieved, the society filed Commercial Appeal (L) No. 9061 of 2024 under Section 13 of the Commercial Courts Act.

Acts & Sections

  • Commercial Courts Act, 2015: 13
  • Maharashtra Co-operative Societies Act, 1960: 79A
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court Quashes Land Acquisition Award for Lack of Notification Under Section 13 of the Maharashtra Project Affected Persons Rehabilitation Act, 1999. Acquisition Proceedings for Resettlement of Project-Affected Persons Found Void Due to Non-Decla...
Related Judgement
High Court Bombay High Court Dismisses Appeal Against Rejection of Impleadment Application in Property Suit — No Right to Implead as Defendants Without Legal Interest. Court holds that mere relationship or desire to be heard does not confer right to be implea...