Bombay High Court Dismisses Developer's Challenge to Termination of Slum Rehabilitation Scheme Appointment — Upholds SRA's Power to Terminate Developer for Delay and Loss of Faith of Slum Dwellers. The court held that the CEO, SRA, validly exercised power under Section 32 of the Maharashtra Slums Act, 1971, and the termination was justified as the delay was attributable to the developer and the majority of slum dwellers had lost faith.

High Court: Bombay High Court
  • 1308
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, a developer, challenged the termination of his appointment to implement a Slum Rehabilitation Scheme (SR Scheme) on a property owned by MCGM and occupied by slum dwellers. The property was designated as R.R.2.1 (Rehabilitation and Resettlement) in the Development Plan. The slum dwellers formed a society, Millat-E-Society, and appointed the petitioner as developer in 2019. The petitioner filed a proposal with SRA in November 2019, and SRA issued an acceptance letter in April 2022. However, in September 2022, MCGM issued eviction notices under Section 89 of MRTP Act for implementation of a garden as per a 1960 Town Planning Scheme. The petitioner challenged these notices in court. Meanwhile, in December 2022, the society terminated the petitioner's appointment citing delay of four years and failure to protect against eviction. The CEO, SRA, terminated the petitioner's appointment on 2 August 2023, holding that the delay was attributable to the petitioner and that the majority of slum dwellers had lost faith. The AGRC dismissed the petitioner's appeal. The High Court dismissed the writ petition, holding that the CEO had power under Section 32 of the Slums Act to terminate the developer, and the termination was justified. The court noted that the petitioner's explanation of delay due to a 2002 court order was not raised before the SRA and was an afterthought. The court also found that the petitioner had ample opportunity to take steps before and after the Covid-19 lockdown but failed to do so. The termination was upheld.

Headnote

A) Slum Rehabilitation - Termination of Developer - Section 32 of Maharashtra Slums Areas (Improvement, Clearance and Redevelopment) Act, 1971 - The CEO, SRA, has the power to terminate a developer's appointment for implementing a Slum Rehabilitation Scheme if the delay in implementation is attributable to the developer and the majority of slum dwellers have lost faith in the developer. The court upheld the termination, noting that the petitioner failed to obtain approvals for nearly four years and the explanation of delay due to a court order was not raised before the SRA and was an afterthought. (Paras 8, 11-12)

B) Slum Rehabilitation - Delay in Implementation - Covid-19 Pandemic - The court considered the Covid-19 lockdown as a factor but found that the petitioner had ample opportunity before and after the lockdown to take steps, yet failed to do so. The delay was attributable to the petitioner, not to the SRA or MCGM. (Paras 7, 12)

C) Slum Rehabilitation - Loss of Faith - Majority Decision - The termination was also based on the majority of slum dwellers losing faith in the developer, as evidenced by the society's resolution to terminate the petitioner and appoint a new developer. The court held that the SRA and AGRC correctly considered this ground. (Paras 6, 8)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the CEO, SRA, had the power to terminate the petitioner's appointment as a developer for implementing the Slum Rehabilitation Scheme, and whether the termination was justified on grounds of delay and loss of faith of slum dwellers.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Writ petition dismissed. The orders of CEO, SRA dated 2 August 2023 and AGRC dated 13 February 2024 are upheld.

Law Points

  • Termination of developer by SRA under Section 32 of Maharashtra Slums Act is valid if delay is attributable to developer and majority of slum dwellers have lost faith
  • SRA has power to terminate developer even in absence of specific violation of agreement
  • Explanation of delay due to court order not raised before SRA is an afterthought
  • Interim order in earlier writ petition did not bar sanction of scheme on land designated as R.R.2.1.
Subscribe to unlock Law Points Subscribe Now

Case Details

2024 Lawtext (BOM) (5) 102

INTERIM APPLICATION NO.6934 OF 2024 IN WRIT PETITION NO.2436 OF 2024

2024-05-10

Amit Borkar, J.

Mr. Godbole (Senior Advocate for petitioner), Mr. Dhakephalkar (Senior Advocate for respondent No.6)

Prithvi Infra Projects, through its authorized signatory Umesh R. Shinde

Apex Grievance Redressal Committee

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition challenging termination of developer's appointment for Slum Rehabilitation Scheme.

Remedy Sought

Petitioner sought to quash the order of CEO, SRA dated 2 August 2023 terminating his appointment and the order of AGRC dated 13 February 2024 dismissing his appeal.

Filing Reason

Petitioner's appointment as developer was terminated by CEO, SRA on grounds of delay and loss of faith of slum dwellers.

Previous Decisions

CEO, SRA terminated petitioner's appointment on 2 August 2023; AGRC dismissed petitioner's appeal on 13 February 2024.

Issues

Whether the CEO, SRA had power to terminate the developer's appointment under Section 32 of the Slums Act. Whether the termination was justified on grounds of delay attributable to the petitioner and loss of faith of slum dwellers.

Submissions/Arguments

Petitioner argued that CEO had no power to terminate in absence of violation of Act or agreement; delay was due to SRA's bona fide impression of court order and Covid-19; meeting of society was not as per SRA circulars. Respondent argued that explanation of court order was an afterthought not raised before SRA; interim order did not bar scheme on R.R.2.1 land; petitioner took no steps for two years after Covid-19 restrictions eased.

Ratio Decidendi

The CEO, SRA has the power under Section 32 of the Maharashtra Slums Act to terminate a developer's appointment for implementing a Slum Rehabilitation Scheme if the delay in implementation is attributable to the developer and the majority of slum dwellers have lost faith. The court found that the petitioner failed to obtain approvals for nearly four years, and the explanation of delay due to a court order was not raised before the SRA and was an afterthought. The termination was justified.

Judgment Excerpts

The CEO, SRA, on 2 August 2023, passed an order terminating the petitioner's appointment as a developer to implement the SR Scheme on the said property and granted liberty to appoint a new developer by passing a fresh general body resolution. The CEO of SRA terminated the petitioner's appointment as a developer for the implementation of the SR Scheme broadly on the following grounds: (i) Since the appointment of the petitioner in the year 2019, no approvals were obtained by the petitioner for the period of around four years. The delay is attributable to the petitioner; (ii) the reason of the delay due to the initiation of legal proceedings against society and challenging eviction notices was not accepted; (iii) the majority of slum dwellers have lost faith in the petitioner.

Procedural History

Petitioner appointed as developer in 2019; SRA issued acceptance letter in April 2022; MCGM issued eviction notices in September 2022; society terminated petitioner in December 2022; CEO, SRA terminated petitioner on 2 August 2023; AGRC dismissed appeal on 13 February 2024; petitioner filed writ petition in Bombay High Court.

Acts & Sections

  • Maharashtra Slums Areas (Improvement, Clearance and Redevelopment) Act, 1971: Section 32
  • Maharashtra Regional Town Planning Act, 1966: Section 31(1), Section 89, Section 90
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Quashes Suspension of Courier License in Gold Smuggling Case — Violation of Natural Justice. Suspension Order Set Aside as Show Cause Notice Did Not Allege Any Act or Omission by Petitioner Under Courier Regulations, 1998.
Related Judgement
Supreme Court Supreme Court Upholds Union of India in Age Determination of High Court Judge Under Article 217(3) Constitution — Reverses High Court's Quashing of President's Order. President's decision based on Chief Justice of India's advice after disclosure of...