Case Note & Summary
The dispute arose from an agreement of May 1955 by which the respondents sold their rights in a plot and factory at Faridabad to the appellants. The plot had been allotted to the respondents by the Faridabad Development Board, and they had erected buildings and started a factory named Bharat-Rubber Mills. Differences between the parties over the agreement were referred to arbitration, and the arbitrator made an award on August 4, 1955, which became a rule of court on August 23, 1956. Under clause 2 of the award, the appellants were liable to discharge the respondents' liability to the Board in the sum of Rs. 23,686-6-0. Clause 7 required payment within one and a half years or alternatively obtaining a complete discharge from the Board for the respondents. In default, the respondents were entitled to take back possession of the plot and factory. The appellants paid only Rs. 8,000 to the Board and forwarded verified claims of Rs. 10,000 under the Displaced Persons (Compensation and Rehabilitation) Act, 1954, which the Board was disinclined to accept. The respondents filed execution applications, the last dated January 15, 1964. The executing court directed execution to proceed, but a learned Single Judge of the High Court allowed the appellants' appeal and set aside that direction. The respondents then filed Letters Patent Appeal No. 139 of 1965, which a Division Bench allowed on September 15, 1967, restoring the executing court's order. The High Court granted a certificate under Article 133(1)(a) and (c) of the Constitution, and the appellants appealed to the Supreme Court. The core legal issues were whether the default occurred due to non-cooperation by the respondents, whether part payment to the Board created privity between the appellants and the Board, how clause 7 of the award should be interpreted, whether the default clause was penal, and whether the award decree could be treated as a consent decree. The appellants argued that the respondents refused to cooperate and that they were ready and willing to pay, and further that the penal clause should be relieved against. The Court found no support in the correspondence for the appellants' contention of non-cooperation; the appellants were not in a position to make the payment and had created impediments by insisting that the Board accept verified claims without proper scrutiny. The Board was under no legal obligation to accept those claims. On privity, the Court held that although the respondents transferred their entire interest to the appellants, the Board never agreed to substitute the appellants as debtors; even after accepting Rs. 8,000, the Board could recover the balance from the respondents. Interpreting clause 7 in the entire scheme of the award, the Court held that on default, not merely possession but title would also pass to the respondents; the appellants' liability to pay dues operated only if title vested in them. The award was not merely declaratory but clearly executable: if default occurred, the respondents could apply for execution to obtain possession. The Court held that the clause was not a penalty and that the term was contained in a decree passed by the court in terms of the award, so no relief could be granted against the terms of a decree. The award decree could not be treated as a consent decree because the award was valid independently of any decision by the parties not to object. Accordingly, the Supreme Court dismissed the appeal and affirmed the High Court's direction that execution should proceed.
Headnote
A) Execution Law - Default in Payment - Clause 7 Obligation - Not mentioned - The award required appellants to pay Rs. 23,686-6-0 to Faridabad Development Board within 1.5 years or obtain complete discharge; appellants paid only Rs. 8,000 and forwarded verified claims which Board did not accept; no evidence of non-cooperation by respondents; held default occurred because appellants failed to satisfy Board's dues (Paras 1-8). B) Contract Law - Privity of Contract - Transfer of Interest - Not mentioned - Although respondents transferred entire interest to appellants, Board never agreed to substitute appellants as debtors; Board could recover balance from respondents even after accepting partial payment; no privity between appellants and Board (Paras 1-8). C) Arbitration Law - Interpretation of Award - Return of Possession and Title - Not mentioned - Recital that respondents entitled to take back possession upon default considered in entire scheme of award; not merely possession but title also would pass to respondents (Paras 1-8). D) Arbitration Law - Condition Precedent - Liability Conditional on Title - Not mentioned - Appellants' liability to pay dues of Board would operate only if title to property vested in them; default negated obligation (Paras 1-8). E) Arbitration Law - Executability of Award Decree - Declaratory vs Executory - Not mentioned - Award not merely declaratory; clear intendment that respondents could apply for execution to obtain possession upon default (Paras 1-8). F) Civil Procedure - Penalty Clause - Relief Against Penalty - Not mentioned - Clause providing right to obtain possession on default not a penalty; term contained in decree passed by court in terms of award; no relief against terms of decree; award decree not consent decree because award valid independently (Paras 1-8).
Issue of Consideration
Whether default in payment under arbitration award clause was due to non-cooperation of respondents; whether Board accepted part payment creating privity; interpretation of clause 7 of award; whether clause was penal; whether award decree could be treated as consent decree
Final Decision
The Supreme Court dismissed the appeal and affirmed the High Court's direction that execution should proceed. The appellants' default entitled the respondents to take back possession of the plot and factory.
Law Points
- default in payment under award clause triggers return of possession
- no privity between transferee and creditor unless creditor agrees
- award clause interpreted in entire scheme
- liability conditional on vesting of title
- award decree executory not merely declaratory
- penalty clause in decree not relievable
- award decree not consent decree


