Supreme Court Dismisses Special Leave Petition in Tender Eligibility Dispute; Satisfactory Completion of Prior Works is a Precondition Under Tender Condition. Tender Condition Requiring Two Completed Runway/National Highway Works Valued at Rs.400 Lakhs Each or One Work Valued at Rs.600 Lakhs Interpreted as Mandatory Completion as on Application Date, Not Ongoing Contracts.

In Favour of Prosecution
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The matter arose from a special leave petition filed before the Supreme Court against an order of the Division Bench of the High Court of Madhya Pradesh at Jabalpur dated August 14, 1996 in LPA No.138/96. The dispute concerned a tender condition for construction work that required prior satisfactory completion of specified runway or National highway works. The petitioners, a construction company, had filed writ petitions seeking a direction to the Airport Authority of India to issue tender forms, claiming they satisfied the tender condition. The learned single Judge dismissed the writ petitions, and the Division Bench affirmed the dismissal. Pursuant to an interim order, the petitioners submitted their tender forms, but at final hearing the writ petitions were dismissed. The petitioners contended that they had past experience in executing national highway works, with two contracts of more than the required amount, certificates from Executive Engineer and Superintending Engineer showing satisfactory performance, and completion of major part of the work within the scheduled time. They argued that failure to give tender forms violated their fundamental right to compete for the contract. The core legal issue was whether the High Court erred in interpreting the tender condition as requiring completed works rather than ongoing contracts with substantial progress. The Court examined Tender Condition No.2, which required satisfactory completion of at least two runway/National highway works each of value Rs.400 lakhs or one work of Rs.600 lakhs during the last five years, along with annual turnover of Rs.500 lakhs in each of the last three years and possession of computerized hot mix plant and concrete batching plant. The Court held that the word 'completed' unambiguously indicated that as on the date of application for tenders, the applicant must have completed the required works; it was a precondition. The petitioners admitted that they had not completed the works, though they claimed major part was completed. Therefore, the refusal to issue tender forms and the non-consideration of their tenders were not illegal. The Court distinguished the decision in New Horizons Ltd. v. Union of India, which dealt with refusal of tender forms at inception based on unproved previous experience, not a condition requiring completed works as a precondition. Accordingly, the special leave petitions were dismissed, and the High Court's view was upheld.

Headnote

A) Tender Law - Eligibility Criteria - Interpretation of 'Satisfactorily Completed' - Tender Condition No.2 - The condition required tenderers to have satisfactorily completed at least two runway/National highway works each of value Rs.400 lakhs or one work of Rs.600 lakhs during the last five years. The Court held that the word 'completed' means that as on the date of application for tenders, the applicant must have completed the required works. Ongoing contracts with only major part completed do not satisfy this precondition. Hence the refusal to issue tender forms was not illegal (Pages 1-2).

B) Precedent - Applicability of New Horizons Ltd. v. Union of India - Distinguishing Previous Experience After Submission from Completion Precondition - The petitioners relied on New Horizons Ltd. [(1995) 1 SCC 478] to argue that previous experience should be considered after submission. The Court distinguished the case, holding that New Horizons concerned refusal of tender forms at inception based on unproved previous experience, not a condition requiring completed works as a precondition. Thus the precedent was not applicable (Page 2).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the High Court erred in holding that the petitioners did not meet Tender Condition No.2 requiring satisfactory completion of at least two runway/National highway works, when the petitioners had ongoing contracts with only major part completed; and whether the precedent in New Horizons Ltd. v. Union of India applies.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The special leave petitions were dismissed. The Supreme Court held that the tender condition required satisfactory completion of at least two runway/National highway works as on the date of application. Since petitioners admitted they had not completed the works, the refusal to give tender forms and non-consideration were not illegal.

Law Points

  • The word 'completed' in tender condition means that as on the date of application for tenders
  • the tenderer must have completed the required prior works
  • ongoing contracts with major part completed do not satisfy the precondition. The decision in New Horizons Ltd. v. Union of India is distinguishable because it concerned previous experience after submission of tender
  • not a condition requiring completion of works as a precondition.
Subscribe to unlock Law Points Subscribe Now

Case Details

1996 LawText (SC) (09) 93

1996-09-17

K. Ramaswamy, G.B. Pattanaik

M/S. Shapers Construction (P) Ltd. & Anr.

Airport Authority of India & Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Special leave petition against High Court order dismissing writ petitions seeking direction to provide tender form for construction contract.

Remedy Sought

Petitioners sought tender forms and consideration of their tenders for the contract, alleging they met Tender Condition No.2.

Filing Reason

Respondents refused to issue tender forms on ground petitioners did not satisfy the condition of having satisfactorily completed required prior works.

Previous Decisions

Learned single Judge and Division Bench of High Court of M.P. at Jabalpur dismissed the writ petitions; special leave petitions filed thereafter.

Issues

Whether the High Court erred in holding that petitioners did not meet Tender Condition No.2 requiring satisfactory completion of at least two runway/National highway works, when petitioners had ongoing contracts with major part completed Whether the decision in New Horizons Ltd. v. Union of India applies to allow consideration of previous experience after submission of tender, as opposed to completion precondition

Submissions/Arguments

Petitioners contended they had past experience in national highway works, two contracts of more than required amount, certificates from Executive Engineer and Superintending Engineer showing satisfactory performance, and major part of work completed within scheduled time. Petitioners argued that completion of work is different from tendering contracts and that refusal to give tender form violated their fundamental right to compete. Petitioners relied on New Horizons Ltd. v. Union of India to argue that previous experience should be considered after submission of tender. Respondents maintained that the tender condition required completed works and that petitioners admitted they had not completed the works.

Ratio Decidendi

The tender condition requiring satisfactory completion of at least two runway/National highway works valued at Rs.400 lakhs each or one work of Rs.600 lakhs during last five years must be fulfilled as on the date of application for tender. Ongoing works with major part completed do not satisfy the word 'completed'. The decision in New Horizons Ltd. is distinguishable as it concerned previous experience after submission, not completion precondition.

Judgment Excerpts

The word 'completed' would indicate that as on the date of application for the tenders, he should have completed at least two runway/National highway works, preferably rigid pavement works involving considerable earth filling. In other words, the completion of the work of at least two runway/National highway is a pre-condition. On their own admission, they had not completed, though the major part of the work as professed by them is completed.

Procedural History

Learned single Judge of High Court of M.P. at Jabalpur dismissed writ petitions; Division Bench dismissed LPA No.138/96 on August 14, 1996; pursuant to interim order, petitioners submitted tender forms but writ petitions dismissed at final hearing; special leave petitions filed.

Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows State's Appeal in Contempt Case Over Road Construction Location - Court Holds That Substantial Compliance With PIL Direction Suffices When Alternative Road Constructed for Public Benefit
Related Judgement
High Court Bombay High Court Dismisses Petitions Challenging Termination of Probationary Employees in MSETCL — Probation Period Extended Validly Under Service Rules. Termination of Probationer Without Stigma Upheld as Employer's Discretion Under Regulation 11...