Supreme Court Upholds Land Acquisition Under Section 4(1) of Land Acquisition Act, 1894 Subject to Undertaking for Alternative Access. Acquisition for Public Purpose Not Interfered With Where Beneficiary Undertook to Construct New Road and Shift Utilities Before Closing Existing Access to Factory.

In Favour of Prosecution
  • 0
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a notification issued under Section 4(1) of the Land Acquisition Act, 1894, by which certain lands were acquired for a public purpose. The appellant, Balarpur Industries Ltd., challenged the acquisition primarily on the ground that it blocked ingress and egress to its factory. The matter reached the Supreme Court by special leave against an order of the Division Bench of the Gujarat High Court dated April 15, 1996 in Special Civil Application No.8179 of 1995. The High Court order itself is not described in detail, but the challenge before the Supreme Court was to the validity of the land acquisition notification and its impact on access. Before the Supreme Court, learned counsel for the appellant argued that the lands acquired were needed for a public purpose, but the acquisition had the effect of blocking ingress and egress to the appellant's factory. The court had earlier issued notice to the respondents by order dated September 2, 1996, based on an admission made by the respondent in a counter-affidavit filed in the High Court. In response, the acquiring authority admitted the factual position in its counter-affidavit. More importantly, the beneficiary respondent, Respondent No.4, on whose behalf the acquisition was sought, filed a counter-affidavit in which it stated that it would close the existing road passing through the acquired land only after constructing a new road on the boundary of the existing road for necessary ingress and egress to the petitioner's factory. This undertaking effectively addressed the appellant's grievance by ensuring that the existing access would not be closed until an alternative road was built. The Supreme Court considered this admission and undertaking and held that there was no need to interfere with the acquisition, provided the undertaking was honoured. The court also addressed an additional practical concern raised by Ms. Indu Malhotra, learned counsel for the appellant, that telephone lines and electrical energy lines serving the appellant's factory would also need to be shifted from the existing road to the new road. The court directed that the shifting of these utility lines should also be done as part of the undertaking given by the respondent. The ratio of the decision is that when a land acquisition for a public purpose is challenged on the ground that it blocks ingress and egress, and the beneficiary gives a clear undertaking to construct a new road and shift utilities before closing the existing access, the acquisition need not be interfered with, subject to that undertaking. The appeal was accordingly disposed of with no order as to costs.

Headnote

A) Land Acquisition - Public Purpose - Ingress and Egress - Land Acquisition Act, 1894, Section 4(1) - The appellant challenged the notification under Section 4(1) on the ground that acquisition blocked ingress and egress to its factory; the beneficiary respondent assured in its counter-affidavit that it would close the existing road only after constructing a new road on the boundary for necessary ingress and egress; the court held that in view of the admission and undertaking there was no need to interfere with the acquisition, subject to the undertaking; also directed shifting of telephone lines and electrical lines as part of the undertaking. (Para 1)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether acquisition of land under Section 4(1) of the Land Acquisition Act, 1894 should be interfered with on the ground of blocking ingress and egress to the appellant's factory, when the beneficiary gave an undertaking to provide alternative access.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Appeal disposed of. The Supreme Court held that in view of the admission and undertaking given by the 4th respondent to provide necessary ingress and egress, there was no need to interfere with the acquisition; directed that shifting of telephone lines and electrical energy lines etc. to the appellant's factory be done as part of the undertaking; no costs.

Law Points

  • When beneficiary undertakes to construct new road and shift utilities before closing existing access
  • acquisition for public purpose upheld
  • Section 4(1) Land Acquisition Act
  • 1894
Subscribe to unlock Law Points Subscribe Now

Case Details

1996 LawText (SC) (11) 61

1996-11-22

K. Ramaswamy, G.B. Pattanaik

Ms. Indu Malhotra

Balarpur Industries Ltd.

State of Gujarat & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal by special leave challenging land acquisition notification and seeking interference due to blockage of ingress and egress to factory.

Remedy Sought

Appellant sought to challenge validity of notification under Section 4(1) and prevent acquisition from blocking access to its factory.

Filing Reason

The land acquisition under Section 4(1) of the Land Acquisition Act, 1894 blocked ingress and egress to the appellant's factory.

Previous Decisions

The Division Bench of the Gujarat High Court passed an order dated April 15, 1996 in Special Civil Application No.8179 of 1995, which was challenged by special leave.

Issues

Whether the land acquisition under Section 4(1) of the Land Acquisition Act, 1894 should be interfered with when it blocked ingress and egress to the appellant's factory, given the respondent's undertaking to provide alternative access.

Submissions/Arguments

Appellant challenged validity of the notification under Section 4(1), contending that the acquisition for public purpose blocked ingress and egress to its factory. Respondent No.4, the beneficiary, submitted in counter-affidavit that it would close the existing road only after constructing a new road on the boundary for necessary ingress and egress to the appellant's factory. Appellant's counsel submitted that telephone lines and electrical energy lines etc. to the factory also needed to be shifted from the existing road to the new road.

Ratio Decidendi

When a land acquisition for public purpose is challenged on the ground of blocking ingress and egress, and the beneficiary undertakes to construct a new road and shift utilities before closing the existing access, the acquisition need not be interfered with, subject to that undertaking.

Judgment Excerpts

This respondent submits that it stands by its said commitment and assures this Hon’ble Court that it would close the existing road passing through the acquired land only after it has constructed a new road on the boundary of the existing road for necessary ingress and egress to the petitioner’s factory. We direct that this should also be done as part of the undertaking given by the respondent.

Procedural History

Special leave petition was filed against the order of the Division Bench of Gujarat High Court dated April 15, 1996 in Special Civil Application No.8179 of 1995. The Supreme Court issued notice to respondents as per order dated September 2, 1996. The acquiring authority and beneficiary respondent filed counter-affidavits admitting facts and giving undertaking. The Court heard learned counsel and disposed of the appeal on November 22, 1996.

Acts & Sections

  • Land Acquisition Act, 1894: Section 4(1)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Gujarat High Court Dismisses Appeal Against Rejection of Plaint in Property Suit — Suit Barred by Limitation and Res Judicata. Order VII Rule 11 CPC Application Allowed as Plaint Discloses No Cause of Action and is Time-Barred.
Related Judgement
High Court Bombay High Court Upholds Specific Performance of Unregistered Agreement Under MOFA — Loan Defence Rejected. Agreement for sale under Maharashtra Ownership Flats Act, 1963 is enforceable despite non-registration.