Case Note & Summary
The dispute arose from a contract for supply of coal between M/s. Kirkend Coal Company, later renamed New Marine Coal Company Ltd., as plaintiff, and Steel Authority of India and others as defendants. The plaintiff sued to recover Rs.1,13,000/- as value of coal supplied. The agreement required supply of Grade-I coal from December 7, 1962 to June 1967. A clause in Ext. C series allowed adjustment for quality or quantity from bills. The plaintiff supplied Grade-II coal but collected price for Grade-I, leading to overpayment. Fraud was discovered in 1969 after audit pointed out the mismatch. The defendants started adjusting overpayments from future bills. The trial court framed issues and adduced evidence, holding that despite the adjustment clause, the defendants needed to plead set-off or counterclaim and pay court fee; not having done so, the suit was decreed. On appeal, the High Court found that the adjustment clause entitled the defendants to adjust from future bills once fraud was discovered; however, because total quantity of coal supplied between December 7, 1962 and June 1967 and grade-wise prices were not on record, the defendants could not succeed in avoiding the decree, and the appeal was dismissed. The Supreme Court considered whether the High Court was justified in dismissing the appeal. It agreed with the High Court's finding that under the agreement, excess overpayment was required to be adjusted in pending or subsequent bills, binding on parties; the defendants were entitled to adjust overpayments from future supplies; and the plaintiff committed fraud in collecting Grade-I price for Grade-II coal. Once that fact was found, the High Court should have either called for a finding from the trial court or remitted the matter for additional evidence. The Supreme Court deemed the latter course more feasible. Accordingly, it set aside the High Court judgment and trial decree, remitted the suit to the trial court, and directed the trial court to give the defendants an opportunity to adduce evidence of total supplies from December 7, 1962 to end of December 1967 and prevailing Grade-I and Grade-II prices. If supply exceeded 12,038 tonnes, that quantity should also be considered; the trial court was to compute actual overpayment, adjust against the amount payable to the plaintiff, and draw a decree accordingly, all within six months. No costs were awarded.
Headnote
A) Contract Law - Adjustment Clause - Binding Nature of Contractual Adjustment Mechanism - The contract clause provided for adjustment for quality or quantity from bills; such clause was binding and permitted the buyer to adjust overpayments from pending or subsequent bills. The High Court correctly found that the appellants were entitled to adjust the excess payments after fraud was discovered in 1969, but it erred in dismissing the appeal solely for lack of evidence of total quantity and prices. Held that having found the contractual right, the court should have remitted the matter for further evidence rather than confirm the decree. B) Civil Procedure - Set-off and Counterclaim - Court Fee Requirement for Adjustment - The trial court held that unless the defendants pleaded set-off or counterclaim and paid court fee, they could not claim adjustment. The Supreme Court's approach implied that a contractual adjustment clause could operate without formal set-off/counterclaim, as the High Court found the adjustment right independent of pleading. Held that the defendant was entitled to adjustment under the contract, and the non-payment of court fee was not a valid ground to deny the contractual right. C) Evidence - Burden of Proof - Quantum and Price of Coal Supplies - The High Court found that the evidence on record showed about 12,038 tonnes of coal supplied, but total quantity supplied between December 7, 1962 and June 1967 and grade-wise prices were not produced. The Supreme Court held that after establishing entitlement to adjustment, the lack of evidence on quantum should have led to remand for additional evidence; the trial court was directed to permit evidence on total supplies and prices and compute the actual overpayment. Held that remand was necessary to determine the exact amount of overpayment and adjustment.
Issue of Consideration
Whether the High Court was justified in dismissing the appeal and confirming the decree of the trial Court on the facts of this case, particularly where the High Court found the appellants entitled to adjust overpayments but lacked evidence of quantity and price.
Final Decision
Appeal allowed; judgment and decree set aside; suit remitted to trial court with directions to allow appellants to adduce evidence of total coal supplies from December 7, 1962 to end of December 1967 and prevailing Grade-I/Grade-II prices; if supply exceeds 12,038 tonnes, that quantity also considered; trial court to compute actual overpayment, adjust and draw decree, within six months; no costs.
Law Points
- Contractual adjustment clause binds parties
- overpayment due to misrepresentation of grade is recoverable by adjustment from future bills
- fraud discovered later permits adjustment
- insufficiency of evidence on quantity and price requires remand
- no need for formal set-off/counterclaim when contract permits adjustment


