Supreme Court Upholds Department's Appeal in Arbitration Escalation Dispute, Holding 25% Escalation Not Applicable to Department-Supplied Materials. Contractor Not Entitled to Further Rs 5,81,421 Under Section 47 CPC as Escalation Award Covered Only Works Executed at Tendered Rates, Not Cost of Cement and Steel Supplied by Department.

In Favour of Prosecution
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a works contract between Himachal Pradesh Nagar Vikas Pradhikaran (appellant) and M/s Aggarwal & Co. (respondent) concerning execution of certain works. After a dispute, the matter was referred to arbitration on the High Court's directions. The arbitrator held delay attributable to the Executive Engineer and awarded a 25% increase over and above tendered rates for all works executed after stipulated completion date, 21 May 1989. The award was made rule of court. While implementing the award, the appellant calculated amount payable as Rs 4,99,307 after deducting cost of cement and steel supplied by the department and taxes. The respondent claimed a further Rs 5,81,421 contending the 25% escalation applied also to the value of department-supplied cement and steel. The appellant objected under Section 47 CPC. The High Court overruled the objection and directed payment of further sum, prompting this appeal by special leave. Chronologically, agreement was executed, works were delayed beyond 21-05-1989, arbitrator passed award on 25-04-1992. Letter dated 12-11-1993 detailed gross work done after 21-05-1989 Rs 69,78,354, less cost of material Rs 23,25,685, net Rs 46,52,669, 25% increase Rs 11,63,167, less income tax and surcharge Rs 26,055, net Rs 11,37,112, withheld recoveries Rs 6,37,805, net payable Rs 4,99,307. Respondent claimed further Rs 5,81,421. High Court allowed. Legal issues were whether 25% escalation awarded by arbitrator covered cost of cement and steel supplied by department and whether High Court erred. Appellant contended escalation only on tendered rates, not raw materials; department supplied cement and steel at contract rates and bore escalation. Respondent argued award final and relied on P.M. Paul v. Union of India. Court noted object of awarding escalated cost was contractor procured material from open market at prevailing prices. Under Clause 10 of contract, department required to supply material at prevailing rates as on date of execution and entitled to deduct same from amounts payable. Department supplied cement and steel at rates prevailing on supply dates, not increased rates; amount worked out Rs 23,25,785. Therefore contractor did not bear escalation on those materials; not entitled to 25% on their cost. P.M. Paul distinguishable. High Court's direction erroneous. Appeal allowed; order of High Court set aside; no costs.

Headnote

A) Arbitration Law - Execution of Award - Interpretation of Escalation Award - Code of Civil Procedure, 1908, Section 47 - The arbitrator awarded a 25% increase over and above tendered rates for all works executed after the stipulated completion date. The dispute was whether this escalation applied to the cost of cement and steel supplied by the department. The Court held that the object of awarding escalated costs was to compensate contractor for securing materials from open market at prevailing prices; since the contractor did not procure these department-supplied materials, no entitlement to 25% on their value arose. Held that the High Court erred in directing payment of the further sum.

B) Contract Law - Escalation Clauses - Exclusivity of Tendered Rates for Works - Clause 10 of Contract - Clause 10 required the department to supply material at rates prevailing on the date of execution and to deduct the same from amounts payable. The department supplied cement and steel at prevailing rates without charging increased rates, so the contractor suffered no escalation burden for those materials. The Court held that 25% escalation awarded was limited to the tendered rates for works executed and did not extend to department-supplied material costs. Held that the appeal is allowed without costs.

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the 25% escalation awarded by the arbitrator over and above tendered rates for all works executed after the stipulated date of completion applied to the cost of cement and steel supplied by the appellant department, and whether the High Court erred in directing payment of further sum under Section 47 CPC.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Appeal allowed; High Court order directing payment of further sum set aside; no costs.

Law Points

  • 25% escalation under arbitration award applies only to tendered rates for works executed and not to cost of department-supplied materials
  • contractor not entitled to escalation on materials supplied by department where department bore price increase
  • escalation clause compensates contractor for procuring materials from open market at prevailing prices
  • Section 47 CPC objection to execution of award permissible
Subscribe to unlock Law Points Subscribe Now

Case Details

1997 LawText (SC) (01) 160

1997-01-27

K. Ramaswamy, G.T. Nanavati

Shri H.K. Puri, Shri Upadhyay

Himachal Pradesh Nagar Vikas Pradhikaran

M/s Aggarwal & Co.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal by special leave against High Court order in execution proceedings of arbitration award; dispute over entitlement to further amount under award.

Remedy Sought

Appellant sought setting aside of High Court direction to pay further Rs 5,81,421 to respondent under arbitration award.

Filing Reason

Respondent claimed further sum of Rs 5,81,421 beyond Rs 4,99,307 paid in implementation of award; appellant objected under Section 47 CPC, but High Court overruled objection and directed payment.

Previous Decisions

Arbitrator award dated April 25, 1992 granted 25% increase over tendered rates; award made rule of court; High Court in O.M.P. No. 626/93 in Ex. P. No. 27/1993 directed payment of further sum.

Issues

Whether 25% escalation awarded by arbitrator applies to cost of cement and steel supplied by department Whether High Court erred in directing payment of further sum under Section 47 CPC

Submissions/Arguments

Appellant: 25% enhancement relates to tendered rates for works executed, not to rates of raw materials supplied by appellant; cement and steel supplied by department at contract rates; no extra payment intended for these items. Respondent: Award recorded delay due to laches of Executive Engineer and awarded 25% more than agreed normal rate; award final and cannot be interfered with; relied on P.M. Paul v. Union of India.

Ratio Decidendi

25% escalation award interpreted to apply only to tendered rates for works executed by contractor, not to cost of cement and steel supplied by department; contractor not entitled to escalation on materials supplied by department where department bore price escalation and contractor did not procure from open market; Section 47 CPC objection to execution accepted.

Judgment Excerpts

After considering whole matter submitted to me by both the parties, both verbally and in writing I have come to this conclusions that delay lies on the part of the respondent - Executive Engineer, It is awarded that the plaintiffs shall be paid by the respondent- Executive Engineer an increase of 25% over and above their tendered rates for all works executed by them after the stipulated date of completion i.e. 21.5.89. The very object of awarding escalated cost was that the contractor had secured the material from the open market at the price prevailing at the relevant time and used the same for execution of the work.

Procedural History

Dispute referred to arbitrator on directions of High Court; Arbitrator passed award dated 25-04-1992 awarding 25% increase; award made rule of court; respondent claimed further sum; appellant filed objection under Section 47 CPC; High Court by judgment dated 02-05-1996 in O.M.P. No. 626/93 in Ex. P. No. 27/1993 overruled objection and directed payment; hence special leave appeal to Supreme Court.

Acts & Sections

  • Code of Civil Procedure, 1908: Section 47
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Petition Challenging Minister's Order Setting Aside Registration of Co-operative Housing Society. Minister's Order Upholding Challenge to Society's Registration Based on Non-Compliance with Section 6 of Maharashtra Co-oper...
Related Judgement
Supreme Court Supreme Court Acquits Accused in Robbery Case Due to Doubtful Arrest and Lack of Identification. Conviction under Sections 392/397 IPC Set Aside as Prosecution Failed to Establish Identity of Robbers Beyond Reasonable Doubt.