Case Note & Summary
The Supreme Court considered an appeal arising from an arbitration award in a construction contract dispute. The appellant, a construction company, contracted with the Oil and Natural Gas Corporation to construct 304 pre-fabricated housing units at Panvel, Phase-I. The appellant commenced but did not complete the work within the extended period, leading the corporation to terminate the contract and complete the work through another agency. Disputes were referred to two joint arbitrators. In their award dated 18 June 1991, the arbitrators awarded the appellant Rs.1,09,04,789 under various heads and the corporation Rs.41,22,178, resulting in a net amount of Rs.67,82,620 with 18% interest from the date of award until payment or decree. The appellant applied to make the award a rule of court, while the corporation filed objections seeking to set it aside. The learned Single Judge overruled the objections and made the award a rule of court. On appeal, the Division Bench partly allowed the corporation's appeal, rejecting the appellant's claims 4, 6, and 9 while upholding claims 1 and 13. The appellant then approached the Supreme Court challenging the rejection of these three claims. The legal issues were whether the Division Bench erred in setting aside the awards on claim No.4 (cement shortage), claim No.6 (balcony area measurement), and claim No.9 (price escalation). On claim No.4, the appellant argued that its letter dated 5 March 1984 was a counter-offer requiring 50 kg cement bags and giving precedence to its terms over tender conditions, and that the acceptance letter did not object to the weight stipulation; it contended that the arbitrators were entitled to construe the terms and that since the award was non-speaking, no interference was permissible. The corporation relied on the Schedule-A stipulation that it was not responsible for weight variations. On claim No.6, the appellant contended that the plans were modified and no balconies existed, but it could not produce any agreed or sanctioned modified plan. The corporation argued that the tender conditions and clause 10 of the appellant's own letter required exclusion of balcony area from built-up area measurement. On claim No.9, the corporation relied on the acceptance letter stating that the price was firm and not subject to escalation on any ground till completion of work, while the appellant sought escalation for the period after expiry of the original contract period. The Court reasoned that because there was no formal contract, terms had to be inferred from the tender notice and correspondence. On claim No.4, it noted that the matter was borderline and that the court's attempt should always be to support the award within the letter of law; thus it restored the arbitrator's award. On claim No.6, the Court held that the stipulation clearly excluded balcony area from built-up area and that an arbitrator, being a creature of the agreement, cannot award amounts prohibited by the terms; since no modified plan was shown, the Division Bench was correct. On claim No.9, the Court held that the express stipulation of firm price and no escalation bound the parties and the arbitrators, so the award for escalation was beyond authority. Accordingly, the appeal was partly allowed: the award on claim No.4 was restored, while the awards on claims No.6 and No.9 were set aside. The judgment reiterated that an arbitrator must operate within the four corners of the agreement and cannot award amounts ruled out by the contract terms, while non-speaking awards are not to be interfered with if a plausible construction exists.
Headnote
A) Arbitration - Non-speaking Award - Judicial Interference - Not mentioned - The arbitral award was non-speaking and the court observed that the attempt of the court should always be to support the award within the letter of law. Since two views were possible on the construction of the cement supply stipulations, the Division Bench erred in setting aside claim No.4. Held that the award on claim No.4 is affirmed. B) Contract - Formation and Interpretation - Counter-offer and Acceptance - Not mentioned - There was no formal contract; terms had to be inferred from the tender notice and correspondence. The appellant's letter dated 5 March 1984 stipulated 50 kg cement bags and precedence over tender conditions, and the corporation's acceptance letter dated 10 January 1985 did not object to the weight stipulation. The Division Bench overlooked these letters and relied solely on the tender schedule. Held that the arbitrator's construction was permissible. C) Arbitration - Arbitrator's Authority - Prohibition in Agreement - Not mentioned - An arbitrator is a creature of the agreement and must operate within its four corners; he cannot award amounts ruled out or prohibited by the terms. The agreement expressly excluded balcony area from built-up area measurement. Held that the arbitrators overstepped authority by including balcony area and the award under claim No.6 was rightly set aside. D) Contract - Measurement of Built-up Area - Exclusion of Balconies - Not mentioned - Clause (10) of the appellant's own letter dated 5 March 1984 and tender conditions required measurement of built-up area excluding balcony area. No agreed or sanctioned modified plan was shown, so construction must be assumed as per original plans with balconies. Held that Division Bench decision on claim No.6 is affirmed. E) Contract - Price Escalation - Firm Price Clause - Not mentioned - The acceptance letter dated 10 January 1985 stated that the price is firm and not subject to escalation on any ground till completion of work. This express stipulation bound the parties and arbitrators. Held that the arbitrators could not award escalation for period after expiry of original contract, and Division Bench decision on claim No.9 affirmed.
Issue of Consideration
Whether the Division Bench erred in setting aside the arbitral awards under claim No.4 (cement shortage), claim No.6 (balcony area measurement), and claim No.9 (price escalation); whether the arbitrators exceeded their authority by awarding amounts contrary to express contractual terms.
Final Decision
Appeal partly allowed: Division Bench judgment reversed regarding claim No.4 (cement shortage award of Rs.3,70,221.50 restored); Division Bench decision affirmed regarding claims No.6 and No.9 (arbitrators' awards under those heads set aside).
Law Points
- Arbitrator must operate within four corners of agreement
- cannot award amounts prohibited by contract terms
- court should support award within letter of law
- non-speaking award no interference if two views possible
- construction of contract from tender and correspondence
- firm price no escalation clause bars escalation claim
- built-up area measurement excludes balcony area


