Supreme Court of India Dismisses Appeals in Arbitration Act Matter — Upholds Non-Speaking Arbitral Award in Construction Contract Dispute. The Court held that an umpire was not obligated to give reasons on the arbitrability of claims in a non-speaking award absent specific reference or agreement; the consolidated award signified consideration of all claims under the Arbitration Act, 1940.

In Favour of Prosecution
  • 0
Judgement Image
Font size:
Print

Case Note & Summary

Background: The dispute arose out of a construction contract between the Tamil Nadu Electricity Board and a contractor for inter-connecting tunnels for Suruliyar Hydroelectric Project. The initial tender value was Rs.47 lakhs, revised to Rs.69 lakhs on January 16, 1975. The site was taken over on January 18, 1975, with a 24-month completion period, but work was completed on August 25, 1978, after expiry. Over Rs.92 lakhs was paid to the contractor. A dispute arose regarding further amounts claimed by the contractor. Facts: The contractor issued notice for appointment of an arbitrator under clause 50; the Board delayed nomination, so the contractor appointed a sole arbitrator. The Board then initiated proceedings under Section 33 of the Arbitration Act, 1940, objecting that some claims were not arbitrable. The court recorded that arbitrability was to be decided by the arbitrator, and the Board had reserved its right to challenge the award later. The Board was allowed to nominate an arbitrator; the two arbitrators differed and an umpire was selected. The umpire, without giving reasons, awarded Rs.70,83,793 against a claim of about Rs.2.10 crores and directed release of earnest money deposit and bank guarantees. The Board applied to set aside the award; the contractor applied to make it rule of court. The civil court dismissed the Board's petition and made the award rule of court, and the Madras High Court Division Bench confirmed. Legal Issues: The core question was whether the umpire was required to give a reasoned decision on the non-arbitrability of some claims, and whether a non-speaking award could be set aside for failing to decide arbitrability. Another issue was whether the court could look into the contract to find that the umpire awarded amounts beyond contracted rates. Arguments: The Board, through Additional Solicitor General, argued that arbitrability is a jurisdictional issue and the umpire could not clothe himself with power by a consolidated non-speaking award without deciding the arbitrability of claims. The contractor argued that the award was non-speaking; absent specific reference requiring reasons, the umpire was not obliged to give a speaking order. The contractor contended that the consolidated sum showed consideration of all claims and that the contract was not part of the record, so the court could not examine it, relying on Tarapore & Co. v. Cochin Shipyard Ltd. and State of A.P. v. R.V. Rayanim. Court's Analysis: The Supreme Court examined the earlier Section 33 order that left arbitrability to the arbitrator and reserved the Board's right to challenge. It referred to Tarapore and Co. regarding specific reference of questions of law. It reasoned that in absence of a specific reference or agreement requiring reasons, a non-speaking award cannot be set aside on the ground of absence of reasons. The court observed that a consolidated award implies consideration of all claims, including arbitrability. It also noted that where the award does not incorporate the contract, the court cannot look into the contract to detect an error apparent on the face of the record. Decision: The Supreme Court dismissed the appeals and upheld the arbitral award.

Headnote

A) Arbitration Law - Non-Speaking Award and Reasons - Arbitrator not obliged to give reasons on arbitrability - Arbitration Act, 1940, Section 33 - In a construction contract dispute, the umpire made a non-speaking award of Rs.70,83,793 against a claim of Rs.2.10 crores. The appellant contended the award was illegal because the umpire failed to give findings on arbitrability. The court reasoned that in the absence of a specific reference or agreement requiring a speaking award, a non-speaking award cannot be set aside for absence of reasons; the consolidated award implies that all claims were considered arbitrable. Held that a non-speaking award is not vitiated by omission to give reasons on jurisdictional issues.

B) Arbitration Law - Arbitrability and Jurisdiction - Scope of Arbitration Clause - Arbitration Act, 1940, Section 33 - The earlier Section 33 proceedings had left arbitrability to be decided by the arbitrator, with liberty to the Board to challenge the award later. The court analyzed whether the arbitrator was obliged to decide non-arbitrability by a reasoned order. Held that if no specific question was referred for reasoned decision, the arbitrator's incidental determination of arbitrability could not be attacked merely for lack of reasons.

C) Contract Law - Construction Contract - Extra Claims and Rates - Clauses 22 and 23 of Contract Specification No.1138 - The claims included higher rates for hard rock excavation and work after contract expiry. The court noted that the contract terms provided that no additional allowance above unit price would be made on account of material encountered. However, because the award did not incorporate the contract, the court could not look into the contract to find an error apparent on the face of the award. Held that the award was not liable to be set aside on that ground.

D) Arbitration Law - Setting Aside Award - Error Apparent on Face of Record - Arbitration Act, 1940 - The court considered the principle from Tarapore and Co. and State of A.P. regarding when a question of law is specifically referred. It distinguished cases where the contract is not part of the record. Held that where the arbitral award is non-speaking and does not refer to the agreement, the court cannot examine the contract to determine excess claims.

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the umpire was required to give a decision supported by reasons on the non-arbitrability of some of the items in terms of the contract; whether a non-speaking award can be set aside for failure to decide arbitrability of claims; whether the court can look into the contract to find an error apparent on the face of the award

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed the appeals and upheld the arbitral award.

Law Points

  • Non-speaking arbitral award
  • arbitrator not required to give reasons on arbitrability
  • consolidated award implies consideration of all claims
  • court cannot examine contract not incorporated in award
  • Section 33 Arbitration Act 1940
  • arbitrability is jurisdictional issue
  • no error apparent on face of record
Subscribe to unlock Law Points Subscribe Now

Case Details

1997 LawText (SC) (02) 149

1997-02-18

K. Ramaswamy, S. Saghir Ahmad

V.R. Reddy, Additional Solicitor General; Poti, Senior Counsel

Tamilnadu Electricity Board

M/s. Bridge Tunnel Constructions & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration dispute arising from construction contract for Suruliyar Hydroelectric Project, challenging non-speaking arbitral award and arbitrability of claims

Remedy Sought

Appellant sought to set aside the arbitral award and resist making it rule of court; respondent sought to enforce the award and make it rule of court

Filing Reason

Dispute over further amounts claimed by contractor for work done, including extra rates for hard rock excavation and work after contract expiry; appellant challenged arbitrability and award

Previous Decisions

Civil court dismissed appellant's petition to set aside award and made award rule of court. Division Bench of Madras High Court confirmed on December 20, 1990

Issues

Whether the umpire was required to give a decision supported by reasons on the non-arbitrability of some of the items in terms of the contract Whether a non-speaking award can be set aside for failure to decide arbitrability of claims Whether the court can look into the contract to find an error apparent on the face of the award

Submissions/Arguments

Appellant argued that the award was illegal due to omission of umpire to give findings and reasons on arbitrability, as arbitrability is a jurisdictional issue; the arbitrator cannot clothe himself with power in a non-speaking award to award a consolidated sum without deciding arbitrability. Respondent argued that the award was non-speaking and in the absence of specific reference directing the arbitrator to decide arbitrability, the umpire was not obliged to give a speaking order; the consolidated sum implied consideration of arbitrability; the contract was not part of the record so the court could not look into it; relied on Tarapore & Co. v. Cochin Shipyard Ltd. and State of A.P. v. R.V. Rayanim.

Ratio Decidendi

In the absence of a specific reference or agreement requiring a speaking award, a non-speaking arbitral award cannot be set aside for absence of reasons on arbitrability. A consolidated award implies that the arbitrator considered all claims including arbitrability. Where the award does not incorporate the contract, the court cannot look into the contract to find an error apparent on the face of the record.

Judgment Excerpts

I hereby award and direct as follows: (1) The Respondent shall pay the claimant a sum of Rupees Seventy Lakhs eighty three thousand seven hundred and ninety three only (Rs. 70,83,793/-) and release the earnest money deposit and Bank Guarantees furnished by the claimant in lieu of Security Deposit, in full settlement of all claims and counter-claims. After the award is made, as the petitioner Board has already reserved its right, it would enable the Board to raise this point, in the event of any need arising for setting aside the award in Court. When the arbitrator had given a consolidated sum towards all the claims, it would mean that he had considered the arbitrability of some of the claims in terms of the contract and that, therefore, he has not committed any error in reaching that conclusion which is apparent on the face of the record.

Procedural History

Agreement executed for construction of inter-connecting tunnels for Suruliyar Hydroelectric Project. Initial tender value Rs.47 lakhs revised to Rs.69 lakhs on 16-01-1975. Site taken over on 18-01-1975; completion due within 24 months; work completed on 25-08-1978 after expiry. Dispute arose over further payment. Respondent issued notice for appointment of arbitrator under clause 50; appellant delayed nomination; respondent appointed sole arbitrator after expiry of prescribed time. Appellant initiated proceedings under Section 33 of Arbitration Act, 1940. Court in Section 33 proceedings recorded that arbitrability to be decided by arbitrator, liberty to Board to challenge award later; condoned delay and allowed appellant to nominate arbitrator. Two arbitrators differed; umpire selected. Umpire made non-speaking award of Rs.70,83,793 against claim of Rs.2.10 crores; directed release of earnest money deposit and bank guarantees. Appellant applied to set aside award; respondent applied to make award rule of court. Civil court dismissed appellant's petition and made award rule of court. Division Bench of Madras High Court confirmed on 20-12-1990 in O.S.A. Nos. 109 and 110 of 1988. Appeals by special leave to Supreme Court.

Acts & Sections

  • Arbitration Act, 1940: Section 33
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Reviewed Convictions of Accused Persons in Unlawful Assembly and Culpable Homicide Case. Convictions Under Sections 148, 304 Part I Read with 149, and 323 Read with 149 IPC Were Challenged After High Court Confirmed Session Court's Deci...
Related Judgement
Supreme Court Supreme Court Upholds Conviction of Accused in Ashram Murder Case Under Section 302 Read with Section 34 IPC. Multiple Head Injuries from Hockey Sticks and Lathis Confirmed as Sufficient in Ordinary Course to Cause Death, Rejecting Plea to Scale Down...