Supreme Court Dismisses Appeal by Housing Board in Flat Allotment Dispute — Upholds High Court Direction for Possession Upon Deposit of Balance. The Court Holds that Execution of Agreement Cannot Be Insisted Upon Without Completing Construction and Rejects Claim for Interest on Balance When Flat Remained Incomplete.

In Favour of Prosecution
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

This appeal by special leave arose from an order of the High Court of Patna dated 8.5.1995 by which a Division Bench refused to modify an earlier order dated 2.2.1993. The appellants were the Bihar State Housing Board, its Managing Director and its Executive Engineer at Harun-Ranchi. The respondent was Lalit Ram, an allottee under a housing scheme of the Board. The dispute pertained to a flat bearing No.H-1/200 allotted to the respondent by allotment order dated 9.12.1983 at a tentative cost of Rs.85,400. The respondent was required to pay an initial amount of Rs.17,230 after adjusting an advance of Rs.6,500, leaving Rs.10,730 to be paid within thirty days. The respondent paid this amount only in 1987 in the sum of Rs.17,541, presumably with interest. Clause 6 of the allotment order required the balance of Rs.68,320 to be paid in monthly installments along with interest. The respondent contended that he could not execute the required agreement because the flat remained incomplete; he informed the Board that he had to take another house on rent. He then filed a writ petition before the High Court seeking appropriate reliefs. By order dated 2.2.1993, the High Court directed that upon deposit of the balance amount of Rs.68,320, the Housing Board would deliver vacant possession of the flat with all fittings and fixtures within one month from the last deposit, and the Board was to indicate the date for execution of agreement when the respondent deposited the last installment. On 15.2.1993, the Executive Engineer required the respondent to execute the agreement after depositing Rs.68,320 within two months and to take physical possession. It was admitted that the respondent paid that amount. The Housing Board thereafter moved the High Court on three occasions seeking modification of the order dated 2.2.1993, but the High Court declined each time, culminating in the order challenged before the Supreme Court. Before the Supreme Court, learned counsel for the Housing Board mainly contended that the amount of Rs.85,400 was only tentative and the allottee was liable to pay revised rates; additionally, the Board claimed that respondent was liable to pay interest on the Rs.68,320 because he failed to pay the monthly installment of Rs.980 from the date of allotment. The Court at first blush considered the interest claim to have merit, but upon closer examination found the other side of the picture. The respondent alleged that the flat in its incomplete form was being used by the Housing Board for storing cement stock. It was undisputed that the flat remained incomplete. The appellants blamed the respondent for non-execution of agreement, but the Court held that liability to execute the agreement cannot be insisted upon without completing the construction of the flat. In the above situation, the Court found no fit case for interference with the High Court order. The Supreme Court dismissed the appeal and granted two months' time to the Housing Board to comply with the directions issued by the High Court in the order dated 2.2.1993.

Headnote

A) Housing Allotment - Delivery of Possession - High Court direction to deliver vacant possession with fittings and fixtures upon deposit of balance amount upheld - Not mentioned - The High Court directed the Housing Board to deliver vacant possession within one month from the last deposit of Rs.68,320 as per clause 6 of the allotment order; the Supreme Court found no fit case for interference and granted two months to comply. Held that the High Court order did not warrant modification.

B) Contract Enforcement - Execution of Agreement - Liability to execute agreement cannot be insisted upon without completing construction of flat - Not mentioned - The Housing Board blamed the respondent for non-execution of agreement, but the court observed that the flat remained incomplete and that liability to execute the agreement cannot be insisted without completing the construction. Held that the appellants could not insist on execution of agreement before completing the flat.

C) Interest on Delayed Payment - Claim for Interest on Balance Amount - Claim for interest on Rs.68,320 not accepted where flat was incomplete and used for storing cement - Not mentioned - The Housing Board argued that respondent was liable to pay interest on the balance amount for failure to pay monthly installments; the court noted the flat remained incomplete and was used by the Housing Board for storing cement stock, thereby rejecting the claim. Held that the appeal was dismissed.

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the High Court was justified in refusing to modify its earlier order directing delivery of possession of an allotted flat upon deposit of the balance amount, despite the Housing Board's claim for interest on delayed payment and revised cost; whether execution of agreement can be insisted upon before completion of construction.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed the appeal and granted two months' time to the Housing Board to comply with the directions issued by the High Court in the order dated 2.2.1993.

Law Points

  • Liability to execute agreement cannot be insisted upon without completing construction of flat
  • Allottee cannot be compelled to execute agreement when flat remains incomplete
  • Claim for interest on balance amount not accepted where flat incomplete and used for storing cement
  • High Court direction to deliver possession on deposit of balance amount confirmed
  • Supreme Court grants two months time to comply with High Court directions
Subscribe to unlock Law Points Subscribe Now

Case Details

1997 LawText (SC) (02) 87

1997-02-03

Madan Mohan Punchhi, K.T. Thomas

Sri Ranjit Kumar

Bihar State Housing Board and Others

Lalit Ram

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal by special leave against High Court order refusing to modify earlier direction in a writ petition concerning delivery of possession of an allotted flat.

Remedy Sought

Housing Board sought modification of High Court order dated 2.2.1993 before High Court, and thereafter challenged the refusal through appeal to Supreme Court.

Filing Reason

Dispute over non-execution of agreement for an incomplete allotted flat, payment of balance amount, and claim for interest on delayed payment.

Previous Decisions

High Court order dated 2.2.1993 directed Housing Board to deliver possession with fittings and fixtures upon deposit of Rs.68,320 within one month from last deposit; Housing Board's three subsequent modification applications declined, including order dated 8.5.1995.

Issues

Whether the High Court order dated 2.2.1993 should be modified to require payment of interest on balance amount from date of allotment. Whether the Housing Board could insist on execution of agreement before completing construction of the flat. Whether the appeal warranted interference given that the flat remained incomplete and was used by the Board for storing cement.

Submissions/Arguments

Housing Board argued that the allotment amount was tentative and the allottee was liable to pay revised rates. Housing Board claimed respondent was liable to pay interest on Rs.68,320 because he failed to pay monthly installment of Rs.980 from date of allotment. Respondent contended he could not execute agreement because flat remained incomplete, had to take another house on rent, and the flat was being used by Board for storing cement.

Ratio Decidendi

Liability to execute an agreement for an allotted flat cannot be insisted upon without completing construction of the flat. Where the flat remains incomplete and is being used by the Housing Board for its own purposes, a claim for interest on the balance amount from the allottee is not sustainable. The High Court's direction to deliver possession upon deposit of the balance amount was found to be just and not requiring modification.

Judgment Excerpts

if the respondent would deposit the balance amount of Rs.68,320/- as mentioned in clause 6 of the allotment order, the Housing Board shall deliver vacant possession of the flat to him with all the fittings and fixtures required to be done 'within one month from the date of last deposit of the amount'. liability to execute the agreement cannot be insisted on without completing the construction of the flat. While dismissing this appeal we grant two months’ time from to the Housing Board to comply with the directions issued by the High Court in the order dated 2.2.1993.

Procedural History

Allotment order dated 9.12.1983 for flat H-1/200 at tentative cost of Rs.85,400; respondent paid initial amount in 1987; respondent filed writ petition before Patna High Court; High Court passed order dated 2.2.1993 directing delivery of possession on deposit of Rs.68,320; Executive Engineer letter dated 15.2.1993 required agreement execution within two months; Housing Board sought modification on three occasions, declined; High Court order dated 8.5.1995 refusing modification challenged before Supreme Court.

Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Dismisses Appellant in Civil Procedure Execution Sale Case Upholding Commissioner's Authority to Fix Upset Price on Court's Direction. Order XXI Rule 66 CPC Requires Court to Settle Sale Proclamation and Fix Amount for Recovery, but No ...
Related Judgement
High Court Bombay High Court Upholds Denial of Legal Heirship Certificate to Second Wife in Pension Dispute Under Maharashtra Civil Services (Pension) Rules, 1982. Court Interprets Rule 116(6)(a)(i) in Consonance with Hindu Personal Law, Refusing to Recognize V...