Case Note & Summary
The dispute arose between the State of U.P. and Harish Chandra & Co. regarding an arbitration award related to a construction contract. The contract, signed on 26th October 1979, involved excavation and construction work, which was to be completed by 31st May 1982. However, the contractor failed to complete the work on time, leading to additional costs for the State. The contractor sought arbitration for various claims, and the arbitrator awarded interest at 15% from the date of the claim until the date of payment. The trial court upheld the award but modified the interest rate to 15.5%. The State appealed against the trial court's decision, and the contractor cross-appealed against the reduction of interest by the High Court to 6%. The Supreme Court examined whether the arbitrator had the authority to grant pre-reference interest and whether the High Court's reduction of interest was justified. The court concluded that the arbitrator did have the power to grant such interest under the Interest Act, 1978, and that Clause 1.9 of the contract did not bar the claim for interest. The court also found that the trial court's discretion to award 15.5% interest was improperly overridden by the High Court. Consequently, the Supreme Court modified the High Court's judgment, reinstating the trial court's interest rate and confirming the award. The court did not impose costs and vacated interim orders.
Headnote
A) Arbitration Law - Power of Arbitrator - Authority to Grant Pre-Reference Interest - Arbitration Act, 1940, Section 30 - The court held that the arbitrator had the authority to grant interest for the pre-reference period as per the Interest Act, 1978, and thus the appellant's contention was rejected. (Paras 3-4). B) Contract Law - Interpretation of Contractual Clauses - Clause 1.9 of the Contract - The court found that Clause 1.9 did not bar the claim for interest on the amounts due for work done, as it only pertained to specific disputes regarding payments lying with the Government. (Paras 4-5). C) Discretionary Power of Courts - Interest Rate Determination - The court ruled that the trial court had the discretion to award 15.5% interest on the decretal amount, which the High Court improperly reduced to 6%. The Supreme Court reinstated the trial court's interest rate. (Paras 5-6).
Issue of Consideration
Whether the arbitrator had the power to grant interest prior to the date of reference and whether the High Court's reduction of interest was justified.
Final Decision
The Supreme Court allowed the cross-appeal, reinstating the trial court's interest rate of 15.5% from the date of the decree until payment, and dismissed the appeal by the State of U.P.
Law Points
- Arbitration
- Interest
- Jurisdiction
- Contractual Clauses
- Discretionary Power


