Case Note & Summary
The dispute arose from a contract between the appellant and the Union of India for the supply of 58,000 metric tonnes of sugar, with a stipulated delivery date of 31st October 1989. Following the issuance of a performance bank guarantee by the appellant, the contract was assigned to the Food Corporation of India (FCI), which opened a letter of credit. However, the authentication of the letter of credit was delayed, leading to a series of communications between the parties regarding the delivery schedule. The government initially canceled the contract on 8th November 1989 but later withdrew the cancellation. The appellant sought to fix a new delivery date, but FCI remained silent. Ultimately, the government canceled the contract again on 25th January 1990, citing failure to deliver by the original date. The matter was referred to arbitration, where the arbitrators ruled in favor of the appellant, stating that the performance bank guarantee should be refunded. The High Court initially upheld this decision, but on appeal, the Division Bench reversed it, asserting that the appellant had accepted a new delivery date of 14th/15th November 1989. The Supreme Court ultimately found that the High Court's presumptions were unwarranted and that the essence of the contract regarding time had not been properly considered. The court ruled that the cancellation of the contract was unjustified and that the appellant was entitled to the refund of the performance guarantee.
Headnote
A) Contract Law - Time is the Essence of Contract - The stipulation that shipment within the contracted delivery period is of the essence of the contract was upheld. - Arbitration Act, 1940, Section 30 - The court found that the original delivery date had become part of the letter of credit and the buyer's failure to specify a new delivery date constituted a waiver of the breach. Held that the cancellation of the contract was unjustified as the buyer had not communicated a new delivery date (Paras 29-30).
Issue of Consideration
Whether time was the essence of the contract and the authority of the High Court in interfering with an Arbitral Award under the Arbitration Act, 1940.
Final Decision
The Supreme Court ruled in favor of the appellant, stating that the cancellation of the contract was unjustified and that the performance bank guarantee should be refunded. The court emphasized that time was indeed the essence of the contract and that the buyer's failure to communicate a new delivery date constituted a waiver of the breach.
Law Points
- Arbitration
- Contract Law
- Performance Guarantee
- Time is the Essence of Contract
- Breach of Contract



