Case Note & Summary
The dispute arose from a contract for the construction of a Minor Irrigation Project between the State of Orissa and the respondent contractor. The work was due for completion on 3rd August 1977 but was completed on 31st March 1978. Disputes regarding payment led the contractor to raise claims and seek arbitration. An arbitrator was appointed, and after reviewing the claims and counterclaims, awarded a lump sum of Rs. 14.67 lakhs with interest. The Subordinate Judge modified the interest date, and the High Court partially allowed an appeal but upheld the award's validity. The State challenged the award, arguing it was unreasoned and lacked specificity. The Supreme Court dismissed the appeal, stating that an unreasoned award does not invalidate the award and that the lump sum award was permissible. The court found no misconduct by the arbitrator and no apparent legal errors in the award. The court reiterated that an award is conclusive unless misconduct or invalidity is proven under the Arbitration Act. The application for leave to appeal was dismissed.
Headnote
A) Arbitration Law - Unreasoned Award - Grounds for Setting Aside - Arbitration Act, 1940, Sections 30, 35 - The court held that an unreasoned award is not a valid ground for setting aside an award, and a lump sum award is permissible. The arbitrator's conduct was found to be proper, and there was no error of law apparent on the face of the award. Held that the High Court was correct in refusing to accept the challenge to the award (Paras 582G-583A).
Issue of Consideration
Whether the unreasoned award can be set aside and the validity of the lump sum award.
Final Decision
The Supreme Court dismissed the appeal, affirming the validity of the arbitration award and the High Court's decision to modify the interest awarded.
Law Points
- Arbitration
- unreasoned award
- lump sum award
- error on face of award
- misconduct of arbitrator



