Case Note & Summary
The dispute arose from a contract awarded by the Municipal Corporation of Delhi to the respondent for the construction of staff quarters. The contract was rescinded by the Corporation on grounds of delay in completion. The respondent contested this decision, leading to arbitration under the Arbitration Act, 1940. The arbitrator found that delays were caused by factors outside the respondent's control and that the Corporation had not made time the essence of the contract. The arbitrator awarded the respondent a sum of Rs. 23,820 along with interest, while also allowing certain counterclaims from the Corporation. The Corporation's objections to the award were dismissed by the High Court, leading to a special leave petition to the Supreme Court. The Supreme Court examined whether the reasonableness of the arbitrator's reasons could be challenged under Article 136 of the Constitution. The court held that such reasonableness could not be questioned and emphasized the arbitrator's role as the sole judge of evidence. The court found no violation of natural justice and affirmed the arbitrator's conclusions regarding the essence of the contract. The petition was dismissed, and the respondent was awarded costs for the challenge up to the High Court, while each party was to bear its own costs for the Supreme Court proceedings.
Headnote
A) Arbitration - Reasonableness of Award - Reasonableness of reasons given by an arbitrator cannot be challenged under Article 136 - Arbitration Act, 1940, Sections 20, 30, 33 - The Supreme Court held that the reasonableness of the reasons given by an arbitrator in making his award cannot be challenged in proceedings under Article 136, emphasizing that the arbitrator is the sole judge of the quality and quantity of evidence (Paras 183-186). B) Natural Justice - Principles of Natural Justice - No violation of natural justice in the arbitration proceedings - Arbitration Act, 1940 - The court found no violation of principles of natural justice, as the arbitrator considered all relevant factors and material in making the award (Paras 186-187). C) Contract Law - Essence of Contract - Whether time was the essence of the contract is a mixed question of law and fact - The arbitrator's conclusion that time was not the essence of the contract was based on cogent reasons and materials on record (Paras 184-185). D) Reasonableness - Definition of Reasonable - The term 'reasonable' has a prima facie meaning in law - The court noted that the arbitrator acted reasonably and rationally, and the challenge to the award was rightly rejected (Paras 187-188).
Issue of Consideration
Whether the reasonableness of the reasons in the speaking award was justiciable under Article 136 of the Constitution.
Final Decision
The Supreme Court dismissed the special leave petition, affirming the High Court's decision to uphold the arbitrator's award. The court found no grounds for interference and ruled that the reasons provided by the arbitrator were reasonable and based on the evidence presented.
Law Points
- Arbitration
- Reasonableness of Award
- Natural Justice
- Appraisement of Evidence
- Essence of Contract



