Case Note & Summary
The Supreme Court dealt with two civil appeals concerning the entitlement of the appellant to collect toll fees from the Bharatpur-Deeg section of a road project and the applicable interest rate on the awarded amount. The disputes arose from an arbitration award favoring the appellant, which was later set aside by the District Judge. The appellant, MSK Projects, had been contracted by the State of Rajasthan to construct the Bharatpur bye-pass under a Build Operate and Transfer (BOT) model. The project included a total length of 10.85 km, with the appellant completing the work and starting toll collection in 2000. However, local agitation and a state-issued notification restricted vehicle entry into Bharatpur, prompting the appellant to invoke arbitration. The arbitral tribunal ruled in favor of the appellant, awarding compensation for losses due to the delay in issuing the notification. The State challenged this award, leading to the District Judge setting it aside, arguing that the agreement did not obligate the State to issue the notification and that the appellant was not entitled to compensation. The High Court later reinstated the right to collect tolls from the Bharatpur-Deeg section, but reduced the interest rate from 18% to 10%. The Supreme Court upheld the High Court's decision, affirming that the Bharatpur-Deeg section was part of the project and that the appellant was entitled to collect toll fees. The court also confirmed the reduction of interest based on current economic conditions, emphasizing that the arbitrator must operate within the scope of the reference and cannot decide issues not presented during arbitration. The court directed the tribunal to reconsider the matter regarding the non-execution of the second phase of the project and the potential toll recovery from the Bharatpur-Deeg section. The appeals were disposed of with the appellant entitled to a specific amount awarded by the tribunal, adjusted for interest if not already paid.
Headnote
A) Arbitration Law - Jurisdiction of Arbitral Tribunal - Scope of Reference - Arbitral Tribunal cannot exceed the terms of reference provided by the parties. - Arbitration and Conciliation Act, 1996, Section 34 - The court held that the tribunal must adhere strictly to the issues referred to it and cannot decide matters outside its jurisdiction. (Paras 6-8). B) Contract Law - Toll Fee Collection - Right to Collect Toll - The appellant was entitled to collect toll fees from the Bharatpur-Deeg section as it was part of the integrated project. - Indian Tolls Act, 1851 - The court found that the Bharatpur-Deeg section was integral to the project, thus allowing toll collection from that section. (Paras 20-24). C) Interest Rate - Reduction of Interest - Courts can adjust the interest rate based on economic realities. - Interest Act, 1978, Section 3 - The court upheld the reduction of interest from 18% to 10% based on prevailing banking rates and economic conditions. (Paras 16-19).
Issue of Consideration
Whether the appellant was entitled to collect toll fees from the Bharatpur-Deeg section and the appropriate interest rate applicable.
Final Decision
The Supreme Court upheld the High Court's decision allowing the appellant to collect toll fees from the Bharatpur-Deeg section and confirmed the reduction of interest from 18% to 10%. The court directed the arbitration tribunal to reconsider the non-execution of the second phase of the project and the potential toll recovery.
Law Points
- Arbitration
- Toll Fee
- Interest Rate
- Jurisdiction of Arbitral Tribunal
- Compensatory Nature of Toll



