Bombay High Court Upholds Arbitral Award for Unpaid Design and Construction Works in Section 34 Challenge Brought by Award Debtor. The Court held that the arbitral tribunal's error concerning joint and several liability of Designated Partners under the group company doctrine was severable and did not affect the efficacy of the award for admitted outstanding dues under an agreement containing an arbitration clause....
This matter arose from a commercial arbitration petition filed under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated August 16, 2024, passed by a sole arb...