Case Note & Summary
The petitioner, M/s. OM SLV Constructions, a proprietary concern represented by its proprietor Sri Venkatesh V., filed a writ petition under Articles 226 and 227 of the Constitution of India before the High Court of Karnataka at Bengaluru. The petitioner sought quashing of a communication dated 19.01.2023 issued by the Joint Commissioner of Rajarajeshwari Nagara of BBMP (respondent No.4) and a direction to the BBMP to make payment of pending bills as per Annexure-F to F4 series dated 08/10/2017, 10/10/2017, 10/01/2018, and 27/02/2018, and Annexure-N to N3. The petitioner had been awarded a contract by the BBMP for solid waste management in the Rajarajeshwari Division. The petitioner completed the work as per the work order, and the BBMP issued completion certificates. However, the BBMP did not make payment of the bills raised by the petitioner. The petitioner made several representations, but the BBMP did not respond. Finally, the Joint Commissioner issued the impugned communication dated 19.01.2023 rejecting the claim on the ground that the matter was pending before the Karnataka Lokayuktha. The petitioner contended that the rejection was arbitrary and without any basis, as the Lokayuktha proceedings were unrelated to the payment of bills. The respondents, including the State of Karnataka, BBMP, and the Lokayuktha, opposed the petition, arguing that the petition involved disputed questions of fact and that the petitioner had an alternative remedy of civil suit. The court, after hearing the parties, held that the BBMP, being a State under Article 12, must act fairly and reasonably. The court found that there was no serious dispute as to the liability, as the work had been completed and certified. The court quashed the communication dated 19.01.2023 and directed the BBMP to pay the pending bills along with interest at 12% per annum from the date of each bill until the date of payment. The court also directed that the payment be made within eight weeks.
Headnote
A) Constitutional Law - Writ Jurisdiction - Article 226 - Contractual Dispute - Payment of Bills - The High Court can entertain a writ petition for enforcement of contractual obligations where there is no serious dispute as to the liability and the action of the State or its instrumentality is arbitrary or in violation of Article 14. The court held that the BBMP, being a State under Article 12, must act fairly and reasonably, and its refusal to pay admitted dues without valid justification is arbitrary. (Paras 1-10) B) Contract Law - Government Contract - Payment for Services Rendered - Completion Certificate - The petitioner had completed the work of solid waste management as per the work order, and the BBMP had issued completion certificates. The court held that once the work is completed and certified, the contractor is entitled to payment, and the BBMP cannot withhold payment on grounds not supported by the contract or law. (Paras 11-20) C) Interest - Delayed Payment - Section 34 CPC - The court held that in the absence of a contractual rate of interest, the court can award interest at 12% per annum from the date of the bill until payment, applying the principle of restitution and to compensate for the delay. (Paras 21-25) D) Limitation - Delay and Laches - The petition was filed within a reasonable time after the communication dated 19.01.2023, and the bills pertained to work done in 2017-2018. The court held that there was no inordinate delay or laches disentitling the petitioner to relief, as the petitioner had been pursuing the matter with the authorities. (Paras 26-30)
Issue of Consideration
Whether the communication dated 19.01.2023 issued by the Joint Commissioner of BBMP rejecting the petitioner's claim for payment of pending bills is sustainable in law, and whether the petitioner is entitled to payment of the said bills along with interest.
Final Decision
The court allowed the writ petition, quashed the communication dated 19.01.2023, and directed the BBMP to pay the pending bills along with interest at 12% per annum from the date of each bill until payment, within eight weeks.
Law Points
- Writ of certiorari
- writ of mandamus
- Article 226
- Article 227
- contractual obligation
- payment of bills
- BBMP
- solid waste management
- Karnataka Lokayukta
- communication quashed
- pending bills
- interest
- 12% per annum
- Section 34 CPC
- Section 3(1)(x) SC/ST Act (not applicable)
- limitation
- delay
- laches
- alternative remedy
- disputed questions of fact
- writ jurisdiction
- public law remedy
- private law remedy
- contract
- work order
- completion certificate
- no dispute as to liability
- admission
- promissory estoppel
- legitimate expectation
- unjust enrichment
- restitution
- interest on delayed payment
- commercial contract
- government contract
- Article 14
- Article 19(1)(g)
- right to carry on business
- right to payment
- statutory duty
- public duty
- municipal corporation
- local authority
- state within Article 12.




